| 25-Jun-2024 |
DISPOSED |
Ar. Neeraj Gautam (Associate Architectural Executive)
briefed the facts of the case.
Sh. appeared on behalf of the promoter.
The AR of the promoter states that the delay in
submission of the approved service plans & estimates and architectural
control sheet was not on account of the promoter but due to the internal delays
in the office of DTCP, Haryana and litigation with the collaborator.
However, it is not disputed that the promoter was
granted conditional registration at its own accord and depositing of security
amount in the form of bank guarantee in lieu of submission of the requisite
clearances within the time specified in the conditional registration. It was
clearly mentioned in the registration certificate that these BGs shall be
forfeited in case the conditions are not fulfilled by the promoter within the
stipulated time period mentioned in the conditions.
The promoter has requested that two DDs bearing no. 301459 dated 19.06.2024 and
301497 dated 19.06.2024 of HSBC Bank amounting to Rs. 25 lakhs may be accepted
in lieu of the bank guarantee as security for conditional compliance of the
registration with respect to architectural control sheet.
In view of the above, the amount of Rs. 25 lakhs deposited vide DD no
301495 dated 19.06.2024 and 301497 dated 19.06.2024 be and is hereby forfeited
and bank guarantees no. 572GT02213560001 dated 22.12.2021, 572GT01232420001
dated 30.08.2023 (revalidated), 572GT02213560002 dated 22.12.2021 and 572GT01232420005 dated 30.08.2023(revalidated) be returned to the promoter under
intimation to the bank.
The matter stands disposed of. The detailed order shall follow. |
ASHOK SANGWAN |
View Order |
17-Jul-2024 |