| 25-Jun-2024 |
DISPOSED |
Ar. Neeraj Gautam (Associate Architectural
Executive) briefed the facts of the case.
Sh. Vedant (CS) appeared on behalf of the promoter
and states that the promoter was required to submit the approval of service
plans and estimates on or before 18.02.2022 (Friday), the approval was issued
by the DTCP on 21.02.2022 (Monday) and the same was submitted in the Authority.
The delay of three days in issuance of the approval from the Department of Town
& Country Planning occurred on account of the weekend. Despite the efforts
to expedite the process, the promoter was unable to obtain the approval within
the regular working days preceding the weekend. The AR of the promoter requests
to waive any penalties under section 63 of the Act, 2016 and not to forfeit the
security amount submitted in lieu of timely compliance.
However, it is not disputed that the promoter was
granted conditional registration at its own accord and depositing of security
amount in the form of bank guarantee in lieu of submission of the requisite
clearances within the time specified in the conditional registration. It was
clearly mentioned in the registration certificate that these BG shall be
forfeited in case the conditions are not fulfilled by the promoter within the
stipulated time period mentioned in the conditions.
Further, as per the decision taken by the Authority
in its meeting dated 01.01.2023, the compliances by the promoters must be made
without fail within the timeline of conditional registration failing which the
BG/ security be forfeited and further action be initiated as per the provisions
of the Act of 2016. |
ASHOK SANGWAN |
--- |
--- |