| 25-Jun-2024 |
DISPOSED |
Ar. Neeraj Gautam
(Associate
Architectural Executive) briefed the facts of the case.
Sh. Anitesh Singh (AR) appeared on behalf of
the promoter.
The AR of the promoter states that
the delay in submission of the architectural control sheet was not on account
of the promoter but due to the internal delays in the office of DTCP, Haryana.
However, it is not disputed that
the promoter was granted conditional registration at its own accord and
depositing of security amount in the form of bank guarantee in lieu of
submission of the requisite clearances within the time specified in the conditional
registration. It was clearly mentioned in the registration certificate that
these BGs shall be forfeited in case the conditions are not fulfilled by the
promoter within the stipulated time period mentioned in the conditions.
The promoter has requested that
demand draft 301521 dated 21.06.2024
of HSBC Bank amounting to Rs. 25 lakhs may be accepted in lieu of the bank
guarantee as security for conditional compliance of the registration with
respect to architectural control sheet.
In view of the above, the amount of Rs. 25 lakhs
deposited vide DD no 301521 dated 21.06.2024 be and is hereby forfeited and
bank guarantees no. 572GT01212850004 dated 12.10.2021 and 572GT01232420003
dated 30.08.2023 (revalidated) be returned to the promoter under intimation to
the bank.
The
matter stands disposed of. The detailed order shall follow. |