| 06-Mar-2025 |
DISPOSED |
Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts
of the case. Sh. Anitesh Singh (AR) is present on behalf of the promoter and
states that the application for the approval of standard design was made on
20.09.2021 prior to the registration of the project. The application was kept
pending by the concerned authority for the purpose of framing guidelines/
standard operating procedures of approvals of architectural control sheet/
standard design in respect of all such kind of projects of commercial plotted colonies
being developed in the state. It is further stated in the application that the
promoter had written a letter dated 03.02.2021 along with undertaking at DTCP
for issuance of approval and the final order for SOP got issued on 31.01.2022. The
promoter’s application was processed by DTCP and final approval was granted on
19.04.2024.
The promoter has requested vide application dated
30.08.2024 to release the security deposit as the delay in getting the approval
was solely in the purview of competent authority.
However, it is not disputed that the promoter was
granted conditional registration at its own accord and depositing of security
amount of Rs. 75 lakhs as a guarantee for submission of the requisite
clearances within the time specified in the conditional registration. It was
clearly mentioned in the registration certificate that this bank guarantee
shall be forfeited in case the conditions are not fulfilled by the promoter
within the stipulated time period mentioned in the conditions.
The bank guarantee of Rs. 50 lakhs submitted on
account of submission of approved service plans & estimates already stands
refunded to the promoter and on request of the promoter, the bank guarantees of
Rs. 25 lakhs bearing no. 572GT01212850003 dated 12.10.2021
(Original) and 572GT01232420004 dated 12.10.2021 (Revalidated) are already returned to the promoter on submission
of DD no. 301498 dated 19.06.2024 of the same amount.
Keeping in view the fact that the promoter has
submitted the approved standard designs with a delay of 131 days, the security
amount of Rs. 25 lakhs deposited in lieu of timely submission of the same is
hereby forfeited.
Since the compliances have been made, although with
a delay, the case is filed. |
ASHOK SANGWAN |
View Order |
19-May-2025 |
| 10-Oct-2024 |
PENDING |
The matter is adjourned to 06.03.2025. |
ASHOK SANGWAN |
--- |
--- |
| 12-Sep-2024 |
PENDING |
Matter is adjourned to 10.10.2024. |
ASHOK SANGWAN |
--- |
--- |
| 30-Aug-2024 |
PENDING |
MATTER FIXED FOR HEARING ON 12.09.2024 |
ASHOK SANGWAN |
--- |
--- |
| 01-Jul-2022 |
FIRST HEARING |
MATTER FIXED FOR HEARING ON 30.08.2024 |
ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
--- |
--- |