Comprehensive Complaint Details
Complaint Detail:RERA-GRG-4303-2022
Party Dtls Self / Adv Name District Current Status Next Date of Hearing Complaint Dispatched Complaint Dispatched On Dispatched Tracking Id Complaint Dispatched Remarks First-Hearing/Scrutinized Remarks View Notice
HARERA GURUGRAM THROUGH JYOTI V/S
REVITAL REALTY PVT LTD
Self GURUGRAM PENDING 23-Dec-2022 Yes 15-Jun-2022 EH316628746IN PROJECT RC COMPLIANCE HEARING PROJECT RC COMPLIANCES HEARING
Notice Details
Notice Number Remarks Dispatching Date Dispatch Id View Notice
First Notice PROJECT RC COMPLIANCE HEARING 15-Jun-2022 EH316628746IN
Complaint Listing Details
Date of Hearing Status Proceedings of the day Bench Order Order Uploaded On
23-Dec-2022 PENDING --- ---
09-Dec-2022 PENDING PROCEEDINGS DATED 09-12-2022 SH. DILIP KUMAR CHAUDHARY GM-PROJECTS AND SH. RAJ KUMAR KAUSHIK GM- BUSINESS DEVELOPMENT ARE PRESENT ON BEHALF OF THE PROMOTER. THE AR OF THE PROMOTER STATES THAT WE HAVE APPLIED FOR APPROVAL OF SERVICE PLANS AND ESTIMATES IN THE MONTH OF SEPTEMBER 2018 TO DTP GURUGRAM. THE SAME WAS FORWARDED FROM CHIEF ENGINEER HSVP PANCHKULA TO DTCP CHANDIGARH ON 10.06.2021 AND FINAL APPROVAL IS STILL PENDING. FURTHER COPY OF COLLABORATION AGREEMENT HAS BEEN SUBMITTED IN THE REGISTRY OF THE AUTHORITY ON 08.12.2022. UNDOUBTEDLY THERE IS A DELAY OF MORE THAN 45 MONTHS IN COMPLIANCE OF THE CONDITIONS OF RC NO. RCREPHARERAGGM288201820 DATED 23-10-2018. THE PROMOTER IS FURTHER DIRECTED TO SUBMIT A BG OR A CHEQUEDD OF RS. 2500000- WITHIN TWO WEEKS FOR SUBMISSION OF APPROVED SERVICE PLANS AND ESTIMATES WITHIN A PERIOD OF TWO MONTHS. THE MATTER TO COME UP ON 23.12.2022. K K KHANDELWAL VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA View Order 02-Jan-2023
25-Nov-2022 PENDING Proceedings dated: 25-11-2022 D.K. Choudhary (G. M. Project) and Rakesh Aggarwal (G.M. Project) is present on behalf of the promoter. The AR of the promoter states that they have applied for approval of fire scheme NOC on 23-05-2019 and the same is still pending. With regard to the execution report of collaboration agreement, it is stated that the same has been obtained and shall be submitted within a week. Matter to come up on 09-12-2022. K K KHANDELWAL VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA --- ---
11-Nov-2022 PENDING Proceedings dated: 11-11-2022 Ms. Jyoti Yadav, Planning Executive briefed about the facts of the project. None is present on behalf of the promoter. One final opportunity is being granted and if no one from the promoter submit the reply/appears it shall be assumed that they have nothing to say in this regard. Hence, thereafter The Authority shall be bound to proceed ex-parte. The matter to come up on 25.11.2022. K K KHANDELWAL VIJAY KUMAR GOYAL --- ---
09-Nov-2022 PENDING Due to public holiday on 09-11-2022, matter adjourned to 11-11-2022. K K KHANDELWAL VIJAY KUMAR GOYAL --- ---
01-Jul-2022 FIRST HEARING The promoter is directed to submit the deficit documents to comply with the conditions of registration certificate. Matter to come up on 09-11-2022. K K KHANDELWAL VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA --- ---
Documents Submitted
Dak ID Receiving Date Submitted By Remarks
35021 11/06/2022 JYOTI NEW COMPLAINT
37067 04/07/2022 ANIL KUMAR REPLY OF ONLINE SOU MOTO NOTICE- 4303-2022, DATED: 15.06.2022. (LATE SUBMISSION)