Comprehensive Complaint Details
Complaint Detail:RERA-GRG-3149-2022
Party Dtls Self / Adv Name District Current Status Next Date of Hearing Complaint Dispatched Complaint Dispatched On Dispatched Tracking Id Complaint Dispatched Remarks First-Hearing/Scrutinized Remarks View Notice
HARERA GURUGRAM THROUGH ASHISH KUSH L C V/S
BRAHMA CENTER DEVELOPERS PVT. LTD
Self GURUGRAM PENDING 16-Jan-2026 Yes 16-Jul-2024 EH076077203IN RC Expired Show-cause notice for violating provisions of section 4 - not adhering to the declared time period with in which the promoter undertook to complete the project as per section 4(2)(l)(C).
Notice Details
Notice Number Remarks Dispatching Date Dispatch Id View Notice
First Notice Show-cause notice for violating provisions of section 4 - not adhering to the declared time period with in which the promoter undertook to complete the project as per section 42lC. 03-Jun-2022 EH316598390IN
Second Notice RC Expired 16-Jul-2024 EH076077203IN
Complaint Listing Details
Date of Hearing Status Proceedings of the day Bench Order Order Uploaded On
16-Jan-2026 PENDING --- ---
18-Dec-2025 PENDING None is present on behalf of the promoter.  One more and final opportunity is being given to the promoter to put appearance and apprise status of project failing which the concerned PE to put up on file to initiate penal proceeding. The matter to come up on 16.01.2026. VIJAY KUMAR GOYAL View Order 07-Jan-2026
13-Nov-2025 PENDING Sh. Shivaditya Mukherjee, Advocate is present on behalf of the promoter.The AR requests for time for applying for extension of registration. The matter to come up on 18.12.2025. ANU --- ---
29-Oct-2025 PENDING The matter is adjourned and fixed for 13.11.2025. ANU --- ---
27-Aug-2025 PENDING Ms. Anjalika Sharma (Advocate) is present on behalf of the promoter. The AR of the promoter stated that part OC has been obtained and applied for OC of remaining part. The AR of the promoter seeks 8 weeks’ time to submit the reply and is also applying for continuation of the project. In view of the above, the matter to come up on 29.10.2025 for filing compliance of above. VIJAY KUMAR GOYAL View Order 28-Oct-2025
30-Jul-2025 PENDING Ms. Swati Chaudhary (A.M Legal) is present on behalf of the promoter. The AR of the promoter stated that the reply has been filed today only. Further, states that part OC of the project has been obtained. In view of the above, the matter is adjourned and to come up on 27.08.2025. VIJAY KUMAR GOYAL View Order 26-Aug-2025
18-Jun-2025 PENDING THE MATTER IS FIXED FOR 30.07.2025. VIJAY KUMAR GOYAL --- ---
02-Apr-2025 PENDING The matter is fixed for 18.06.2025. VIJAY KUMAR GOYAL --- ---
19-Feb-2025 PENDING None is present on behalf of the promoter. One more and final opportunity is being given to the promoter to put appearance and apprise status of project. The matter to come up on 02.04.2025. VIJAY KUMAR GOYAL View Order 25-Mar-2025
08-Jan-2025 PENDING None is present on behalf of the promoter. One more and final opportunity is being given to the promoter to put appearance and apprise status of project. The matter to come up on 19.02.2025. VIJAY KUMAR GOYAL View Order 13-Jan-2025
20-Nov-2024 PENDING None is present on behalf of the promoter. One more and final opportunity is being given to the promoter to put appearance and apprise status of project. The matter to come up on 08.01.2025. VIJAY KUMAR GOYAL View Order 19-Dec-2024
30-Oct-2024 PENDING The presiding member is on leave. The matter is adjourned and fixed for 20.11.2024. VIJAY KUMAR GOYAL View Order 13-Nov-2024
11-Sep-2024 PENDING None is present on behalf of the promoter. One more and final opportunity is being given to the promoter to put appearance and apprise status of project. The matter to come up on 30.10.2024. VIJAY KUMAR GOYAL View Order 09-Oct-2024
28-Aug-2024 PENDING The presiding member is on leave. The matter is adjourned and fixed for 11.09.2024. VIJAY KUMAR GOYAL View Order 05-Sep-2024
26-Jul-2024 PENDING None is present on behalf of the promoter. One more and final opportunity is being given to the promoter to put appearance and apprise status of project. The matter to come up on 28.08.2024. VIJAY KUMAR GOYAL View Order 27-Aug-2024
30-Jun-2022 FIRST HEARING The matter could not taken up on 30.06.2022. Hence, date of hearing is fixed for 26.07.2024. VIJAY KUMAR GOYAL --- ---
Documents Submitted
Dak ID Receiving Date Submitted By Remarks
34206 02/06/2022 ASHISH NEW COMPLAINT
95573 01/08/2025 GUNJAN KUMAR REPLY OF SHOW CAUSE NOTICE DATED 15.07.2025
41361 21/09/2022 VINAY KUMAR REPLY TO SHOW CAUSE NOTICE OF OC/CC- 3149-2022, DATED: 03.06.2022.