Comprehensive Complaint Details
Complaint Detail:RERA-GRG-1139-2021
Party Dtls Self / Adv Name District Current Status Next Date of Hearing Complaint Dispatched Complaint Dispatched On Dispatched Tracking Id Complaint Dispatched Remarks First-Hearing/Scrutinized Remarks View Notice
NISCHAL DUBEY AND ANR V/S
SUPERTECH LTD
ABHIJEET GUPTA GURUGRAM SINE DIE NA Not Yet FIRST HEARING DATED : 20.04.2021 --
Complaint Listing Details
Date of Hearing Status Proceedings of the day Bench Order Order Uploaded On
10-Feb-2023 SINE DIE The  brief background of the case is as under:   1.         The Union Bank of India had preferred a Company Petition CP(IB) bearing NO. 204/(ND) 2021 before NCLT under Section 7 of Insolvency and Bankruptcy Code 2016 against M/s Supertech Ltd. for non-payment of outstanding debt. The NCLT was pleased to admit the insolvency petition by its order dated 25.03.2022. Vide this order the NCLT inter alia initiated CIRP against the corporate debtor, and appointed, Hitesh Goel as the Interim Resolution Professional for the corporate debtor and declared moratorium as per Section 14 of the IBC.   2.        Mr. R.K. Arora, the suspended director of the corporate debtor filed an appeal bearing company appeal (AT) (Ins) no. 406 of 2022 on 07.04.2022 before NCLAT against the order dated 25.03.2022. The appeal was subsequently heard on multiple dates and NCLAT had continued the stay on constitution of the CoC till 10.06.2022. The NCLAT vide order dated 10.06.2022 modified the CoC stay order to the extent that the IRP may constitute the CoC only in relation to the project Eco-Village – II of the corporate debtor.   3.     An application dated 26.07.2022 from Mr. Hitesh Goel IRP was received stating therein that though all the projects of the corporate debtor apart from ECO village - II would be kept as ongoing project, but the construction of the other projects would continue with overall supervision of IRP with the assistance of ex-management, its employees, and workmen. So, the imposition of moratorium under section 14 of IBC would continue and proceedings of all the cases listed before the authority be adjourned sine die.   4.     Vide order dated 12.09.2022, the NCLAT has clarified that “the CIRP order has not been stayed. The Moratorium is continuing” and also vide order dated 14.10.2022, NCLAT made it clear that verification of the claim has to be with regard to all projects and is not only confined to Eco-village -II.                    The counsel for the respondent has produced a copy of order dated 31.01.2023 passed by NCLAT, Principal Bench, New Delhi passed in Company Appeal (AT) (Ins.) No.406 of 2022 and I.A. No.2246, 2646 and 2663 of 2022 in case titled as Ram Kishor Arora Suspended Director of Supertech Ltd. vs. Union of India and another which is re-produced as under:- Learned counsel for the parties have placed before us the order passed by the Hon’ble Supreme Court dated 27.01.2023 which is to the following effect:- “taking note of the submissions sought to be made in these matters,  we are clearly of the view that as at present, the offers said to have been made by the prospective resolution applicants may be evaluated and may be placed for consideration before the NCLAT but beyond that process, we would request the NCLAT to keep the proceedings in abeyance and await further order of this Court. List these maters on 16.02.2023”. In view of the aforesaid order of the Hon’ble Supreme Court, the appeal is adjourned to await further orders of Hon’ble Supreme Court. As per proceedings dated 12.08.2022  opinion of A. G. Haryana was sought, who has clearly opined vide his letter dated 28.11.2022  to adjourn sine die the matter. The IRP is directed to submit the status of case pending before the NCLAT within a week to this authority. In view of the above directions passed in order dated 31.01.2023,  the matter is adjourned sine die.  File be consigned to the registry. SANJEEV KUMAR ARORA View Order 03-Mar-2023
30-Sep-2022 PENDING Vide orders dated 25.03.2022, NCLT New Delhi initiated CIRP against the respondent i.e., M/s Supertech Limited and appointed Mr. Hitesh Goel as IRP for the corporate debtor and declared moratorium as per section 14 of IBC. It led to filing an appeal in NCLAT against that order by Mr. R.K. Arora, one of the suspended Director. That order was stayed by NCLAT and constitution of CoC was stayed and observed that IRP may constituted the CoC only in relation to project ECO village-Il of the corporate debtor and that appeal is pending for 12.08.2022.   Further an application dated 26.07.2022 from Mr. Hitesh Goel IRP has been received stating therein that though all the projects of the corporate debtor apart from ECO village - II would be kept as ongoing project, but the construction of the other projects would continue with overall supervision of IRP with the assistance of ex-management, its employees and workmen. So, the imposition of moratorium under section 14 of IBC would continue and proceedings of all the cases listed before the authority be adjourned sine die. But plea raised in this regard is devoid of merit. While passing order dated 25.03.2022 though NCLT initiated CIRP against the corporate debtor, but that order was stayed and modified vide orders dated 26.07.2022 by NCLAT by observing that the construction of all other projects shall continue with over all supervision of IRP with the assistance of its ex-management, its employees and workmen. Though clarification w.r.t this order is pending for 28.09.2022 before NCLAT but IRP would be treated as a promoter for all intents and purposes except for ECO village-Il against whom CIRP has been initiated and is pending.      The authority has already requested to the Additional AG Haryana to examine whether as per reading of order dated 25.03.2022 and order dated 10.06.2022, moratorium in terms of Section 14 of the IBC is declared only against ECO village-Il project or in respect of all other projects of the corporate debtor i.e., M/s Supertech Limited. The requisite advice is still awaited. The counsel for the respondent had produced a copy of order passed by Hon’ble NCDRC wherein various complaints were listed and NCDRC after perusal of the order passed by NCLAT has deferred the matter for awaiting clarification from NCLAT regarding applicability of moratorium on project of M/s Supertech other than ECO village – 2. The counsel has further submitted that IRP has also moved an application before NCLAT for clarification and the case is fixed for 28.09.2022.   The counsel for the respondent has produced a copy of orders dated 26.08.2022 in case titled as EA/141/2021 and other bunch matters were heard in NCDRC vide which the NCDRC has deferred the matter till 13.12.2022 keeping in view the NCLAT orders dated 25.03.2022.   Now vide order dated 12.09.2022, the NCLAT has clarified that “the CIRP order has not been stayed. The Moratorium is continuing.            The complainant has moved an application stating therein that letters from M/s Supertech in  Hues project has been received and demanded the amount otherwise they threaten to cancel the unit and forfeit the amount which he has already paid since 2014.  He has also placed a copy of email dated 22.09.2022 sent by M/s  Supertech  to clear the outstanding dues by 05.10.2022 on failure they shall be compelled to cancel the unit. The counsel for the complainant has requested that M/s Supertech cannot demand the outstanding amount in case the moratorium is continuing and IRP has been appointed. It is directed that IRP shall be present on the next date of hearing to explain the detailed status of the moratorium imposed upon M/s Supertech Ltd. and to explain whether M/s Supertech Ltd. can demand the outstanding amount in case  moratorium is continuing on whole of the company. Further the authority shall also explore for engaging the services of an expert in NCLT matters to protect the rights and interest of allottees. Matter to come up on 10.02.2023 for further proceedings.  K K KHANDELWAL VIJAY KUMAR GOYAL View Order 27-Oct-2022
31-Aug-2022 PENDING Vide orders dated 25.03.2022, NCLT New Delhi initiated CIRP against the respondent i.e., M/s Supertech Limited and appointed Mr. Hitesh Goel as IRP for the corporate debtor and declared moratorium as per section 14 of IBC. It led to filing an appeal in NCLAT against that order by Mr. R.K. Arora, one of the suspended Director. That order was stayed by NCLAT and constitution of CoC was stayed and observed that IRP may constituted the CoC only in relation to project ECO village-Il of the corporate debtor and that appeal is pending for 12.08.2022.   Further an application dated 26.07.2022 from Mr. Hitesh Goel IRP has been received stating therein that though all the projects of the corporate debtor apart from ECO village - II would be kept as ongoing project, but the construction of the other projects would continue with overall supervision of IRP with the assistance of ex-management, its employees and workmen. So, the imposition of moratorium under section 14 of IBC would continue and proceedings of all the cases listed before the authority be adjourned sine die. But plea raised in this regard is devoid of merit. While passing order dated 25.03.2022 though NCLT initiated CIRP against the corporate debtor, but that order was stayed and modified vide orders dated 26.07.2022 by NCLAT by observing that the construction of all other projects shall continue with over all supervision of IRP with the assistance of its ex-management, its employees and workmen. Though clarification w.r.t this order is pending for 29.08.2022 before NCLAT but IRP would be treated as a promoter for all intents and purposes except for ECO village-Il against whom CIRP has been initiated and is pending.      The authority has  already requested to the Additional AG Haryana to examine whether as per reading of order dated 25.03.2022 and order dated 10.06.2022, moratorium in terms of Section 14 of the IBC is declared only against ECO village-Il project or in respect of all other projects of the corporate debtor i.e., M/s Supertech Limited. The requisite advice is still awaited. The counsel for the respondent had produced a copy of order passed by Hon’ble NCDRC wherein various complaints were listed and NCDRC after perusal of the order passed by NCLAT has deferred the matter for awaiting clarification from NCLAT regarding applicability of moratorium on project of M/s Supertech other than ECO village – 2. The counsel has further submitted that IRP has also moved an application before NCLAT for clarification and the case is fixed for 12.09.2022.   The counsel for the respondent has produced a copy of orders dated 26.08.2022 in case titled as EA/141/2021 filed  in NCDRC  vide which the NCDRC  has deferred the matter till 13.12.2022 keeping in view the NCLAT orders dated 25.03.2022.   Matter to come up on 30.09.2022  for further proceedings.   K K KHANDELWAL VIJAY KUMAR GOYAL View Order 21-Sep-2022
09-Aug-2022 PENDING Vide orders dated 25.03.2022,  NCLT New Delhi initiated CIRP against the respondent i.e. M/s Supertech Limited and appointed Mr. Hitesh Goel as IRP for the corporate debtor and declared moratorium as per section 14 of IBC. It led to filing an appeal in NCLAT against that order by Mr. R.K. Arora, one of the suspended Director.  That order was stayed by NCLAT and constitution of CoC was stayed and observed that IRP may constituted the CoC only in  relation to project ECO village-II of the corporate debtor and that appeal is pending for 12.08.2022. Now an application dated 26.07.2022 from Mr. Hitesh Goel IRP has been received stating therein that though all the projects of the corporate debtor apart from ECO village – II would be kept as on-going project, but the construction of the other projects would continue with overall supervision of IRP with the assistance of ex-management, its employees and workmen.  So the imposition of moratorium  under section 14 of IBC would continue and proceedings of all the cases  listed before the authority be adjourned sine die. But plea raised in this regard is devoid of merit. While passing order dated 25.03.2022 though NCLT  initiated CIRP against the corporate debtor but that order was stayed and modified vide orders dated 26.07.2022 by NCLAT by observing that the construction of all other projects shall continue with over all supervision of IRP with the assistance of its ex-management, its employees and workmen. Though clarification w.r.t this order is pending for 12.08.2022 before  NCLAT but IRP would be treated as a promoter for all intents and purposes except for ECO village-II against whom CIRP has been initiated and is pending. The authority hereby directs the Additional AG Haryana to examine whether reading of order dated 25.03.2022 and order dated 10.06.2022  moratorium in terms of Section 14 of the IBC is declared only against ECO village-II project or in respect of all other projects of the corporate debtor i.e. M/s Supertech Limited. Meanwhile,  the authority may fix up matter the date subsequent to the date fixed in this matter pending before NCLAT on 12.08.2022. Matter to come up on 31.08.2022 for further proceedings.  K K KHANDELWAL VIJAY KUMAR GOYAL View Order 09-Sep-2022
30-Mar-2022 PENDING In view  of judgment dated 11.11.2021 in title- M/s Newtech Promoters and Developers Pvt Ltd. Vs State of UP & Ors. Etc. passed by the  Apex Court, this forum has no jurisdiction to adjudicate the complaint in hands.File be transferred to the Authority.  Reader is directed to send the file immediately.  RAJINDER KUMAR --- ---
12-Jan-2022 PENDING None for complainant. Issue notice for next date.                            To come on  30.03.2022 for further proceedings/arguments. RAJINDER KUMAR View Order 28-Jan-2022
08-Nov-2021 PENDING Adjudicating Officer is on leave, matter is adjourned to 12.01.2022. RAJINDER KUMAR View Order 09-Nov-2021
03-Aug-2021 PENDING None for the complainant. 2.                        It is pointed out by the learned counsel for the respondent that the complainant has filed another complaint on the same  cause of action and that matter is listed for hearing on 08.11.2021. 2.                     Be put up on the same date i.e. 08.11.2021. RAJINDER KUMAR View Order 06-Aug-2021
20-Apr-2021 FIRST HEARING Due to spread of Covid-19 cases in and around area of the Hon’ble Authority, the cases fixed for today are not being taken up for hearing. Hence, as per the directions for the Hon’ble Authority, the case adjourned to 03.08.2021. 2.         However, it is directed that the respondent has already been served through e-mail and delivery of documents is also confirmed from the tracking report. So, it is directed to file written statement with a copy to the other side 4 weeks prior to the date fixed with a copy to the other side and the matter be put up on the date fixed mentioned above for arguments. SUBHASH CHAND GOYAL View Order 22-Apr-2021
Documents Submitted
Dak ID Receiving Date Submitted By Remarks
16690 24/02/2021 ABHIJEET GUPTA NEW COMPLAINT