Comprehensive Complaint Details
Complaint Detail:RERA-GRG-5232-2019
Party Dtls Self / Adv Name District Current Status Next Date of Hearing Complaint Dispatched Complaint Dispatched On Dispatched Tracking Id Complaint Dispatched Remarks First-Hearing/Scrutinized Remarks View Notice
HARERA V/S
TULIP INFRATECH PVT. LTD.
Self GURUGRAM PENDING 24-Feb-2020 Yes 24-Aug-2020 EH639075726IN Notice for compliance of Sec42lD A-H and QPR
Notice Details
Notice Number Remarks Dispatching Date Dispatch Id View Notice
First Notice Notice Dispatched 14-Nov-2019 EH787684441IN
Second Notice Compliance of Section 42lD of the Real Estate Regulation and Development Act 2016. 24-Dec-2019 EH770713002IN
Third Notice Notice of sec42ld 16-Jul-2020 EH770731045IN
Fourth Notice Notice for compliance of Sec42lD 24-Aug-2020 EH639075726IN
Complaint Listing Details
Date of Hearing Status Proceedings of the day Bench Order Order Uploaded On
24-Feb-2020 PENDING --- ---
15-Jan-2020 PENDING 1.              As per record of the authority, it has been observed that in spite of mandatory provisions under section 11(1) of the Act, rule 14(1)(d) of the Rules and Regulations dated 21.5.2019 made thereunder, the promoter has failed to submit the updates on the webpage for the project. 2.              Hence, the promoter is again directed to submit REP-I (Part A-H) online as well as hard copy along the requisite documents in the Authority immediately without any failure. 3.              The authority has decided to impose a penalty of Rs 25,000/- per day with effect from 31.12.2019 i.e. the deadline for completing the online filling of REP-I (Part A-H), on failure to comply with the directions of the Authority. The penalty shall continue during which default continues which may cumulatively extend upto five percent of the estimated cost of the real estate project as determined by the Authority. 4.              The Authority has decided to issue a show cause notice in which  promoter is required to comply with the directions of the Authority within one month from the date of receipt of this notice otherwise show cause as to why their registration certificate should not be revoked under section-7 of the Real Estate (Regulation and Development) Act 2016 and Rule-7 of the Haryana Real Estate (Regulation and Development) Rules, 2017. 5.              The promoter is given a final opportunity of personal hearing on 24.02.2020 at 2.00 pm in the office of HARERA, Gurugram at the Conference Room, New PWD Rest House, Civil Lines, Gurugram, Haryana.  K K KHANDELWAL SAMIR KUMAR SUBHASH CHANDER KUSH View Order 24-Jan-2020
13-Jan-2020 FIRST HEARING Matter adjourned to 15.01.2020 K K KHANDELWAL SAMIR KUMAR SUBHASH CHANDER KUSH --- ---