Quarterly Schedules | ||
| HRERA Panchkula | ||
| Project Registration Number : HRERA-PKL-FBD-116-2019 | ||
| Project Name : RPS PALM DRIVE (PHASE-I) | ||
| Project Number : RERA-PKL-512-2019 | ||
| Project Type : NEW | ||
| Report Online Submission Date : 07-Dec-2019 |
| S.No. | Particulars | Amount (In Lakhs) |
| 1 | Cost of the land (if included in the estimated cost) | 1307 |
| 2 | Estimated cost of construction of apartments | 3702 |
| 3 | Estimated cost of infrastructure & other structure | 675 |
| 4 | Other cost including EDC taxes, levies, etc | 589 |
| Total | 6272 |
| Total Expenditure on the project | 761 |
| Expenditure made upto the date of Registration | 2079 |
| EDC due as on the date of Registration | 324 |
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 209 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 25 |
| 5 | Any other receipt | 0 |
| Total | 224 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 185 |
| 2 | Expenditure on infrastructure & other structure | 33 |
| 3 | Other costs including EDC, taxes, etc | 13 |
| Total | 231 | |
| Balance | 7105 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 146 |
| 3 | Amount withdrawn during the quarter | 144 |
| 4 | Balance at the end of the quarter | 2 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | 104 (1 PLOT = 4 UNITS; HENCE 24 PLOTS = 96 UNITS) | 24 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 1 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 218 |
| 4 | Others Expenditure | 1860 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 324 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 7105 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 39 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 205 |
| 5 | Any other receipt | 0 |
| Total | 7349 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 186 |
| 2 | Expenditure on infrastructure & other structure | 19 |
| 3 | Other costs including EDC, taxes, etc | 41 |
| Total | 246 | |
| Balance | 6900 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 2 |
| 2 | Amount deposited in Escrow Account | 39 |
| 3 | Amount withdrawn during the quarter | 39 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | A1 | 11 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 186 |
| 2 | Apartments | 19 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 6900 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 177 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 72 |
| 5 | Any other receipt | 0 |
| Total | 7149 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 223 |
| 2 | Expenditure on infrastructure & other structure | 25 |
| 3 | Other costs including EDC, taxes, etc | 1 |
| Total | 249 | |
| Balance | 6651 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 177 |
| 3 | Amount withdrawn during the quarter | 177 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | A1 | 1 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 223 |
| 2 | Apartments | 25 |
| 3 | EDC, IDC, etc | 1 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 6651 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 0 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 1 |
| 5 | Any other receipt | 0 |
| Total | 6652 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 1 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 1 | |
| Balance | 6650 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 1 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 6650 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 0 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 351 |
| 5 | Any other receipt | 0 |
| Total | 351 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 316 |
| 2 | Expenditure on infrastructure & other structure | 35 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 351 | |
| Balance | 2505 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOTS | 13 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 5.39 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 2505 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 280 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 2785 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 160 |
| 2 | Expenditure on infrastructure & other structure | 19 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 179 | |
| Balance | 2076 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 280 |
| 3 | Amount withdrawn during the quarter | 280 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOTS | 3 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 2076 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 635 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 2711 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 116 |
| 2 | Expenditure on infrastructure & other structure | 15 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 131 | |
| Balance | 2348 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 635 |
| 3 | Amount withdrawn during the quarter | 635 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOTS | 19 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 2348 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 282 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 2630 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 248 |
| 2 | Expenditure on infrastructure & other structure | 29 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 277 | |
| Balance | 2353 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 282 |
| 3 | Amount withdrawn during the quarter | 282 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOT | 4 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 29 |
| 2 | Apartments | 248 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 2353 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 368 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 2721 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 107 |
| 2 | Expenditure on infrastructure & other structure | 127 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 234 | |
| Balance | 2487 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 368 |
| 3 | Amount withdrawn during the quarter | 368 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOT | 2 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 127 |
| 2 | Apartments | 107 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 2487 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 47 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 2534 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 87 |
| 2 | Expenditure on infrastructure & other structure | 10 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 97 | |
| Balance | 2437 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 47 |
| 3 | Amount withdrawn during the quarter | 47 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOT | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 10 |
| 2 | Apartments | 87 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 324 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 2437 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 333 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 2770 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 203 |
| 2 | Expenditure on infrastructure & other structure | 10 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 213 | |
| Balance | 2557 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 333 |
| 3 | Amount withdrawn during the quarter | 321 |
| 4 | Balance at the end of the quarter | 12 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOT | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 10 |
| 2 | Apartments | 203 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 324 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 2557 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 165 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 156 |
| 5 | Any other receipt | 0 |
| Total | 2878 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 101 |
| 2 | Expenditure on infrastructure & other structure | 220 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 321 | |
| Balance | 900 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 12 |
| 2 | Amount deposited in Escrow Account | 165 |
| 3 | Amount withdrawn during the quarter | 177 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOT | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 220 |
| 2 | Apartments | 101 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 324 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 147 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 147 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 88 |
| 2 | Expenditure on infrastructure & other structure | 15 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 103 | |
| Balance | 798 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 147 |
| 3 | Amount withdrawn during the quarter | 147 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOT | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 15 |
| 2 | Apartments | 88 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 324 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 123 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 53 |
| 5 | Any other receipt | 0 |
| Total | 186 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 158 |
| 2 | Expenditure on infrastructure & other structure | 28 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 186 | |
| Balance | 812 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 123 |
| 3 | Amount withdrawn during the quarter | 116 |
| 4 | Balance at the end of the quarter | 7 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOT | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 28 |
| 2 | Apartments | 158 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 324 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 43 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 99 |
| 5 | Any other receipt | 0 |
| Total | 142 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 85 |
| 2 | Expenditure on infrastructure & other structure | 57 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 142 | |
| Balance | 870 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 7 |
| 2 | Amount deposited in Escrow Account | 43 |
| 3 | Amount withdrawn during the quarter | 43 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOT | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | RESIDENTIAL UNIT | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 57 |
| 2 | Apartments | 85 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 324 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 870 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 419 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 1289 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 80 |
| 2 | Expenditure on infrastructure & other structure | 30 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 110 | |
| Balance | 760 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 419 |
| 3 | Amount withdrawn during the quarter | 419 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOT | 1 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 30 |
| 2 | Apartments | 80 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 324 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 760 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 99 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 859 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 76 |
| 2 | Expenditure on infrastructure & other structure | 18 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 94 | |
| Balance | 665 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 99 |
| 3 | Amount withdrawn during the quarter | 99 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOT | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 18 |
| 2 | Apartments | 76 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 324 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 298 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 298 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 71 |
| 2 | Expenditure on infrastructure & other structure | 51 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 122 | |
| Balance | 543 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 298 |
| 3 | Amount withdrawn during the quarter | 298 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOT | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 51 |
| 2 | Apartments | 71 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 324 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 231 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 231 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 193 |
| 2 | Expenditure on infrastructure & other structure | 38 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 231 | |
| Balance | 337 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 231 |
| 3 | Amount withdrawn during the quarter | 231 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOT | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 38 |
| 2 | Apartments | 193 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 324 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 337 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 694 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 1031 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 183 |
| 2 | Expenditure on infrastructure & other structure | 15 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 198 | |
| Balance | 264 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 694 |
| 3 | Amount withdrawn during the quarter | 694 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOT | 2 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 15 |
| 2 | Apartments | 183 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 324 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 264 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 190 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 454 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 46 |
| 2 | Expenditure on infrastructure & other structure | 67 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 113 | |
| Balance | 165 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 190 |
| 3 | Amount withdrawn during the quarter | 190 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOT | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 67 |
| 2 | Apartments | 46 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 165 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 206 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 371 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 63 |
| 2 | Expenditure on infrastructure & other structure | 25 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 88 | |
| Balance | 168 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 206 |
| 3 | Amount withdrawn during the quarter | 206 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOT | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 25 |
| 2 | Apartments | 63 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 324 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 188 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 188 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 17 |
| 2 | Expenditure on infrastructure & other structure | 42 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 59 | |
| Balance | 168 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 188 |
| 3 | Amount withdrawn during the quarter | 188 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOT | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 109 |
| 2 | EDC due as on date | 324 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 168 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 580 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 748 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 206 |
| Total | 206 | |
| Balance | 12 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 580 |
| 3 | Amount withdrawn during the quarter | 580 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 119 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | RESIDENTIAL PLOT | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 206 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 206 |
| 2 | EDC due as on date | 118 |
| ||||||||||||||||||||||||||