Quarterly Schedules | ||
| HRERA Panchkula | ||
| Project Registration Number : 314 OF 2017 DATED 17.10.2017 | ||
| Project Name : METRO VIEW | ||
| Project Number : RERA-PKL-581-2019 | ||
| Project Type : ONGOING | ||
| Report Online Submission Date : 29-Oct-2021 |
| Particulars | Expenditure already incurred up to the date of registration. (In Lakhs) | Total Estimated/ Revised cost of project. (In Lakhs) |
| Land | 512 | 512 |
| Building | 3976 | 4196 |
| Infrastructure facilities, etc. | 794 | 919 |
| Other costs including EDC, IDC, etc. | 781 | 781 |
| Total | 6063 | 6408 |
| Name of the approval | Status | Date |
| Layout Plan | Obtained Approval on | 07-12-2014 |
| Demarcation Plan | Obtained Approval on | 15-09-2007 |
| Zoning Plan | Obtained Approval on | 13-08-2014 |
| Service Plans | Obtained Approval on | 30-09-2015 |
| Electricity Plans | Obtained Approval on | 23-05-2016 |
| Name of the approval | Status | Date |
| Demarcation Plan | Obtained Approval on | 15-09-2007 |
| Zoning Plan | Obtained Approval on | 13-08-2014 |
| Service Plans | Obtained Approval on | 30-09-2015 |
| Electricity Plans | Obtained Approval on | 23-05-2016 |
| Site Plans | Obtained Approval on | 13-11-2009 |
| Building Plans | Obtained Approval on | 03-06-2015 |
| FIre NOC | Obtained Approval on | 27-09-2019 |
| Total Expenditure on the project | 5115 |
| Expenditure made upto the date of Registration | 4800 |
| EDC due as on the date of Registration | 781 |
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 2616 |
| 3 | Amount availed from the bank/financial institutions | 154 |
| 4 | Amount contributed by the promoters/his associates | 1398 |
| 5 | Any other receipt | 1925 |
| Total | 6093 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 512 |
| 2 | Cost of construction of apartments | 3981 |
| 3 | Cost of infrastructure & other structure | 819 |
| 4 | Other costs including EDC, taxes, etc | 781 |
| Total | 6093 | |
| Balance | 0 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.83 |
| 2 | Amount deposited in Escrow Account | 13.95 |
| 3 | Amount withdrawn during the quarter | 14.27 |
| 4 | Balance at the end of the quarter | 0.51 |
| Total Plots in the colony | 0 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | N.A | 0 |
| Total Apartments in the colony | 196 |
| Apartments sold upto the date of Registration | 151 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 1. 1710 SQFT - 24 UNITS, 2. 1495 SQFT -114 UNITS , 3. 1395 SQFT-52 UNITS, 4. 995 SQFT-6 UNITS | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 3981 |
| 2 | Apartments | 819 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 781 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 2760 |
| 3 | Amount availed from the bank/financial institutions | 138 |
| 4 | Amount contributed by the promoters/his associates | 1371 |
| 5 | Any other receipt | 1965 |
| Total | 6234 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 512 |
| 2 | Cost of construction of apartments | 4126 |
| 3 | Cost of infrastructure & other structure | 815 |
| 4 | Other costs including EDC, taxes, etc | 781 |
| Total | 6234 | |
| Balance | 0 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.51 |
| 2 | Amount deposited in Escrow Account | 155.36 |
| 3 | Amount withdrawn during the quarter | 155.83 |
| 4 | Balance at the end of the quarter | 0.04 |
| Total Plots in the colony | 0 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | N.A | 0 |
| Total Apartments in the colony | 196 |
| Apartments sold upto the date of Registration | 151 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 1. 1710 SQFT - 24 UNITS, 2. 1495 SQFT -114 UNITS , 3. 1395 SQFT-52 UNITS, 4. 995 SQFT-6 UNITS | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 815 |
| 2 | Apartments | 4126 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 781 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 2873 |
| 3 | Amount availed from the bank/financial institutions | 122 |
| 4 | Amount contributed by the promoters/his associates | 3273 |
| 5 | Any other receipt | 0 |
| Total | 6268 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 512 |
| 2 | Cost of construction of apartments | 4141 |
| 3 | Cost of infrastructure & other structure | 834 |
| 4 | Other costs including EDC, taxes, etc | 781 |
| Total | 6268 | |
| Balance | 0 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.04 |
| 2 | Amount deposited in Escrow Account | 79.61 |
| 3 | Amount withdrawn during the quarter | 79.41 |
| 4 | Balance at the end of the quarter | 0.24 |
| Total Plots in the colony | 0 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | N.A | 0 |
| Total Apartments in the colony | 196 |
| Apartments sold upto the date of Registration | 151 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 1. 1710 SQFT - 24 UNITS, 2. 1495 SQFT -114 UNITS , 3. 1395 SQFT-52 UNITS, 4. 995 SQFT-6 UNITS | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 834 |
| 2 | Apartments | 4141 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 781 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 2934 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 1386 |
| 5 | Any other receipt | 2002 |
| Total | 6322 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 512 |
| 2 | Cost of construction of apartments | 4174 |
| 3 | Cost of infrastructure & other structure | 855 |
| 4 | Other costs including EDC, taxes, etc | 781 |
| Total | 6322 | |
| Balance | 0 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.24 |
| 2 | Amount deposited in Escrow Account | 61 |
| 3 | Amount withdrawn during the quarter | 61 |
| 4 | Balance at the end of the quarter | 0.24 |
| Total Plots in the colony | 0 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | N.A | 0 |
| Total Apartments in the colony | 196 |
| Apartments sold upto the date of Registration | 151 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 1. 1710 SQFT - 24 UNITS, 2. 1495 SQFT -114 UNITS , 3. 1395 SQFT-52 UNITS, 4. 995 SQFT-6 UNITS | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 855 |
| 2 | Apartments | 4174 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 781 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 3024 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 1414 |
| 5 | Any other receipt | 1893 |
| Total | 6331 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 512 |
| 2 | Cost of construction of apartments | 4176 |
| 3 | Cost of infrastructure & other structure | 862 |
| 4 | Other costs including EDC, taxes, etc | 781 |
| Total | 6331 | |
| Balance | 0 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.24 |
| 2 | Amount deposited in Escrow Account | 10.1 |
| 3 | Amount withdrawn during the quarter | 10 |
| 4 | Balance at the end of the quarter | 0.34 |
| Total Apartments in the colony | 196 |
| Apartments sold upto the date of Registration | 151 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 1. 1710 SQFT - 24 UNITS, 2. 1495 SQFT -114 UNITS , 3. 1395 SQFT-52 UNITS, 4. 995 SQFT-6 UNITS | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 862 |
| 2 | Apartments | 4176 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 781 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 3461 |
| 3 | Amount availed from the bank/financial institutions | 1650 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 1231 |
| Total | 6342 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 512 |
| 2 | Cost of construction of apartments | 4177 |
| 3 | Cost of infrastructure & other structure | 872 |
| 4 | Other costs including EDC, taxes, etc | 781 |
| Total | 6342 | |
| Balance | 0 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.34 |
| 2 | Amount deposited in Escrow Account | 2.83 |
| 3 | Amount withdrawn during the quarter | 2.90 |
| 4 | Balance at the end of the quarter | 0.27 |
| Total Plots in the colony | 0 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | N.A | 0 |
| Total Apartments in the colony | 196 |
| Apartments sold upto the date of Registration | 151 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 1. 1710 SQFT - 24 UNITS, 2. 1495 SQFT -114 UNITS , 3. 1395 SQFT-52 UNITS, 4. 995 SQFT-6 UNITS | 14 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 872 |
| 2 | Apartments | 4177 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 781 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 3461 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 1186 |
| 5 | Any other receipt | 1695 |
| Total | 6342 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 512 |
| 2 | Cost of construction of apartments | 4177 |
| 3 | Cost of infrastructure & other structure | 872 |
| 4 | Other costs including EDC, taxes, etc | 781 |
| Total | 6342 | |
| Balance | 0 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.27 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0.27 |
| Total Plots in the colony | 0 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | N.A | 0 |
| Total Apartments in the colony | 196 |
| Apartments sold upto the date of Registration | 151 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 1. 1710 SQFT - 24 UNITS, 2. 1495 SQFT -114 UNITS , 3. 1395 SQFT-52 UNITS, 4. 995 SQFT-6 UNITS | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 872 |
| 2 | Apartments | 4177 |
| 3 | EDC, IDC, etc | 781 |
| 4 | Others Expenditure | 512 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 781 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 3581 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 1212 |
| 5 | Any other receipt | 1551 |
| Total | 6344 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 512 |
| 2 | Cost of construction of apartments | 4179 |
| 3 | Cost of infrastructure & other structure | 872 |
| 4 | Other costs including EDC, taxes, etc | 781 |
| Total | 6344 | |
| Balance | 0 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.27 |
| 2 | Amount deposited in Escrow Account | 2 |
| 3 | Amount withdrawn during the quarter | 0.7 |
| 4 | Balance at the end of the quarter | 1.57 |
| Total Plots in the colony | 0 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | N.A | 0 |
| Total Apartments in the colony | 196 |
| Apartments sold upto the date of Registration | 151 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 1. 1710 SQFT - 24 UNITS, 2. 1495 SQFT -114 UNITS , 3. 1395 SQFT-52 UNITS, 4. 995 SQFT-6 UNITS | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 872 |
| 2 | Apartments | 4179 |
| 3 | EDC, IDC, etc | 781 |
| 4 | Others Expenditure | 512 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 781 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 3757 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 1420 |
| 5 | Any other receipt | 1188 |
| Total | 6365 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 512 |
| 2 | Cost of construction of apartments | 4197 |
| 3 | Cost of infrastructure & other structure | 875 |
| 4 | Other costs including EDC, taxes, etc | 781 |
| Total | 6365 | |
| Balance | 0 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 1.57 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0.9 |
| 4 | Balance at the end of the quarter | 0.67 |
| Total Plots in the colony | 0 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | N.A | 0 |
| Total Apartments in the colony | 196 |
| Apartments sold upto the date of Registration | 152 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 1. 1710 SQFT - 24 UNITS, 2. 1495 SQFT -114 UNITS , 3. 1395 SQFT-52 UNITS, 4. 995 SQFT-6 UNITS | 1 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 875 |
| 2 | Apartments | 4197 |
| 3 | EDC, IDC, etc | 781 |
| 4 | Others Expenditure | 512 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 781 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 4148 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 1188 |
| 5 | Any other receipt | 1201 |
| Total | 6537 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 512 |
| 2 | Cost of construction of apartments | 4339 |
| 3 | Cost of infrastructure & other structure | 905 |
| 4 | Other costs including EDC, taxes, etc | 781 |
| Total | 6537 | |
| Balance | 0 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.67 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0.67 |
| Total Plots in the colony | 0 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | N.A | 0 |
| Total Apartments in the colony | 196 |
| Apartments sold upto the date of Registration | 168 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 1. 1710 SQFT - 24 UNITS, 2. 1495 SQFT -114 UNITS , 3. 1395 SQFT-52 UNITS, 4. 995 SQFT-6 UNITS | 16 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 905 |
| 2 | Apartments | 4339 |
| 3 | EDC, IDC, etc | 781 |
| 4 | Others Expenditure | 512 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 781 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 4249 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 1233 |
| 5 | Any other receipt | 1109 |
| Total | 6591 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 512 |
| 2 | Cost of construction of apartments | 4384 |
| 3 | Cost of infrastructure & other structure | 914 |
| 4 | Other costs including EDC, taxes, etc | 781 |
| Total | 6591 | |
| Balance | 0 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.67 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0.67 |
| Total Plots in the colony | 0 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | N.A | 0 |
| Total Apartments in the colony | 196 |
| Apartments sold upto the date of Registration | 171 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 1. 1710 SQFT - 24 UNITS, 2. 1495 SQFT -114 UNITS , 3. 1395 SQFT-52 UNITS, 4. 995 SQFT-6 UNITS | 3 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 914 |
| 2 | Apartments | 4384 |
| 3 | EDC, IDC, etc | 781 |
| 4 | Others Expenditure | 512 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 781 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 4326 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 1298 |
| 5 | Any other receipt | 1003 |
| Total | 6627 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 512 |
| 2 | Cost of construction of apartments | 4414 |
| 3 | Cost of infrastructure & other structure | 920 |
| 4 | Other costs including EDC, taxes, etc | 781 |
| Total | 6627 | |
| Balance | 0 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.67 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0.67 |
| Total Plots in the colony | 0 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | N.A | 0 |
| Total Apartments in the colony | 196 |
| Apartments sold upto the date of Registration | 173 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 1. 1710 SQFT - 24 UNITS, 2. 1495 SQFT -114 UNITS , 3. 1395 SQFT-52 UNITS, 4. 995 SQFT-6 UNITS | 2 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 920 |
| 2 | Apartments | 4414 |
| 3 | EDC, IDC, etc | 781 |
| 4 | Others Expenditure | 512 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 781 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 4408 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 1355 |
| 5 | Any other receipt | 887 |
| Total | 6650 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 512 |
| 2 | Cost of construction of apartments | 4433 |
| 3 | Cost of infrastructure & other structure | 924 |
| 4 | Other costs including EDC, taxes, etc | 781 |
| Total | 6650 | |
| Balance | 0 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.67 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0.67 |
| Total Plots in the colony | 0 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | N.A | 0 |
| Total Apartments in the colony | 196 |
| Apartments sold upto the date of Registration | 173 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 1. 1710 SQFT - 24 UNITS, 2. 1495 SQFT -114 UNITS , 3. 1395 SQFT-52 UNITS, 4. 995 SQFT-6 UNITS | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 924 |
| 2 | Apartments | 4433 |
| 3 | EDC, IDC, etc | 781 |
| 4 | Others Expenditure | 512 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 781 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 4617 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 1250 |
| 5 | Any other receipt | 833 |
| Total | 6700 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 512 |
| 2 | Cost of construction of apartments | 4475 |
| 3 | Cost of infrastructure & other structure | 932 |
| 4 | Other costs including EDC, taxes, etc | 781 |
| Total | 6700 | |
| Balance | 0 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.67 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0.67 |
| Total Plots in the colony | 0 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | N.A | 0 |
| Total Apartments in the colony | 196 |
| Apartments sold upto the date of Registration | 181 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 1. 1710 SQFT - 24 UNITS, 2. 1495 SQFT -114 UNITS , 3. 1395 SQFT-52 UNITS, 4. 995 SQFT-6 UNITS | 8 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 932 |
| 2 | Apartments | 4475 |
| 3 | EDC, IDC, etc | 781 |
| 4 | Others Expenditure | 512 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 781 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 4682 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 1262 |
| 5 | Any other receipt | 833 |
| Total | 6777 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 512 |
| 2 | Cost of construction of apartments | 4538 |
| 3 | Cost of infrastructure & other structure | 946 |
| 4 | Other costs including EDC, taxes, etc | 781 |
| Total | 6777 | |
| Balance | 0 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.67 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0.67 |
| Total Plots in the colony | 0 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | N.A | 0 |
| Total Apartments in the colony | 196 |
| Apartments sold upto the date of Registration | 184 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 1. 1710 SQFT - 24 UNITS, 2. 1495 SQFT -114 UNITS , 3. 1395 SQFT-52 UNITS, 4. 995 SQFT-6 UNITS | 3 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 946 |
| 2 | Apartments | 4538 |
| 3 | EDC, IDC, etc | 781 |
| 4 | Others Expenditure | 512 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 781 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 4741 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 1209 |
| 5 | Any other receipt | 856 |
| Total | 6806 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 512 |
| 2 | Cost of construction of apartments | 4562 |
| 3 | Cost of infrastructure & other structure | 951 |
| 4 | Other costs including EDC, taxes, etc | 781 |
| Total | 6806 | |
| Balance | 0 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.67 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0.67 |
| Total Plots in the colony | 0 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | N.A | 0 |
| Total Apartments in the colony | 196 |
| Apartments sold upto the date of Registration | 186 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 1. 1710 SQFT - 24 UNITS, 2. 1495 SQFT -114 UNITS , 3. 1395 SQFT-52 UNITS, 4. 995 SQFT-6 UNITS | 2 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 951 |
| 2 | Apartments | 4562 |
| 3 | EDC, IDC, etc | 781 |
| 4 | Others Expenditure | 512 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 781 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||