Quarterly Schedules

HRERA Panchkula
Project Registration Number : HRERA-PKL-RWR-38-2018
Project Name : "VIPUL PRATHAM APARTMENTS" ON LAND MEASURING 6.369 ACRES
Project Number : RERA-PKL-517-2019
Project Type : ONGOING
Report Online Submission Date : 10-Dec-2019



ParticularsExpenditure already incurred up to the date of registration.
(In Lakhs)
Total Estimated/ Revised cost of project. (In Lakhs)
Land95.0095.00
Building3570.004490.00
Infrastructure facilities, etc.00
Other costs including EDC, IDC, etc.1204.001204.00
Total4869.005789.00



Name of the approvalStatusDate
Demarcation PlanObtained Approval on10-06-2013
Zoning PlanObtained Approval on10-06-2013
Service PlansHave not applied till dateN/A
Electricity PlansObtained Approval on20-01-2018
Site PlansObtained Approval on25-07-2014
Building PlansRevised approval obtained on25-07-2014
FIre NOCObtained Approval on20-11-2014
Total Expenditure on the project1216.00
Expenditure made upto the date of Registration3570.00



EDC due as on the date of Registration0

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance4827.00
2Amount collected from allottees against booked plots and/or apartments92.00
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates645.00
5Any other receipt0
Total5564.00



S.No.Cash OutflowAmount
(In Lakhs)
1Land95.00
2Cost of construction of apartments4265.00
3Cost of infrastructure & other structure0
4Other costs including EDC, taxes, etc1204.00
Total5564.00
Balance2043.00



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter4827.00
2Amount deposited in Escrow Account92.00
3Amount withdrawn during the quarter0
4Balance at the end of the quarter4919.00
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1RESIDENTIAL0



Total Apartments in the colony253
Apartments sold upto the date of Registration237



S.No.Type/SizeApartments Sold in the Quarter
1RESIDENTIAL0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NA0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure319.00
2Apartments3251.00
3EDC, IDC, etc1144.00
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date1204.00
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 10-12-2019  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 10-12-2019  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 10-12-2019  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 10-12-2019  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 10-12-2019  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance5564.00
2Amount collected from allottees against booked plots and/or apartments14.00
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates189.00
5Any other receipt0
Total5767.00



S.No.Cash OutflowAmount
(In Lakhs)
1Land95.00
2Cost of construction of apartments4468.00
3Cost of infrastructure & other structure0
4Other costs including EDC, taxes, etc1204.00
Total5767.00
Balance1840.00



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter4919.00
2Amount deposited in Escrow Account14.00
3Amount withdrawn during the quarter203.00
4Balance at the end of the quarter4730.00
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NA0



Total Apartments in the colony253
Apartments sold upto the date of Registration237



S.No.Type/SizeApartments Sold in the Quarter
1ONE BR (TYPE 1)64
2ONE BR (TYPE 2)11
3TWO BR (TYPE 3)65
4TWO BR (TYPE 4)19
5TWO BR (TYPE 5)22
6THREE BR (TYPE 6)17
7THREE BR (TYPE 7)43
8ONE BR (TYPE 2)11
9TWO BR (TYPE 3)65
10TWO BR (TYPE 4)19
11TWO BR (TYPE 5)22
12THREE BR (TYPE 6)17
13THREE BR (TYPE 7)43



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NA0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments0
3EDC, IDC, etc1144.00
4Others Expenditure60.00



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date1144.00
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 16-12-2019  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 16-12-2019  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 16-12-2019  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 16-12-2019  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 16-12-2019  View