22-Jan-2020 |
PENDING |
1.
As
per record of the authority, it has been observed that in spite of mandatory
provisions under section 11(1) of the Act, rule 14(1)(d) of the Rules and
Regulations dated 21.5.2019 made thereunder, the promoter has failed to submit
the updates on the webpage for the project.
2.
Hence,the
promoter is again directed to submit REP-I (Part A-H) online as well as hard
copy along the requisite documents in the Authority immediately without any
failure.
3.
The
authority has decided to impose a penalty of Rs 25,000/- per day with effect
from 31.12.2019 i.e. the deadline for completing the online filling of REP-I
(Part A-H), on failure to comply with the directions of the Authority. The
penalty shall continue during which default continues which may cumulatively
extend upto five percent of the estimated cost of the real estate project as
determined by the Authority.
4.
The
Authority has decided to issue a show cause notice in which promoteris required to comply with the
directions of the Authority within one month from the date of receipt of this
notice otherwise show cause as to why their registration certificate should not
be revoked under section-7 of the Real Estate (Regulation and Development) Act
2016 and Rule-7 of the Haryana Real Estate (Regulation and Development) Rules,
2017.
5.
The
promoter is given a final opportunity of personal hearing on 24.02.2020 at
3:00 pm in the office of
HARERA, Gurugram at the Conference Room, New PWD Rest House, Civil Lines,
Gurugram, Haryana. |