Quarterly Schedules | ||
HRERA Gurugram | ||
Project Registration Number : GGM/375/107/2019/69 DATED 14.11.2019 | ||
Project Name : SIGNATUREGLOBAL ASPIRE | ||
Project Number : RERA-GRG-322-2019 | ||
Project Type : NEW |
S.No. | Particulars | Amount (In Lakhs) |
1 | Cost of the land (if included in the estimated cost) | 4203.85 |
2 | Estimated cost of construction of apartments | 9014.65 |
3 | Estimated cost of infrastructure & other structure | 1137.09 |
4 | Other cost including EDC taxes, levies, etc | 3841.73 |
Total | 18197.32 |
Name of the approval | Status | Date |
Demarcation Plan | Obtained Approval on | 29-05-2019 |
Zoning Plan | Obtained Approval on | 04-07-2019 |
Service Plans | Obtained Approval on | 30-09-2019 |
Electricity Plans | Obtained Approval on | 06-11-2019 |
Site Plans | Obtained Approval on | 30-09-2019 |
Building Plans | Obtained Approval on | 30-09-2019 |
FIre NOC | Obtained Approval on | 05-06-2020 |
Total Expenditure on the project | 1341.27 |
Expenditure made upto the date of Registration | 4692.75 |
EDC due as on the date of Registration | 610.32 |
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 0 |
2 | Amount collected from allottees against booked plots and/or apartments | 0 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | 1595.71 |
5 | Any other receipt | 0 |
Total | 1595.71 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 697.41 |
2 | Expenditure on infrastructure & other structure | 0 |
3 | Other costs including EDC, taxes, etc | 898.3 |
Total | 1595.71 | |
Balance | 0 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 0 |
3 | Amount withdrawn during the quarter | 0 |
4 | Balance at the end of the quarter | 0 |
Total Apartments in the colony | 792 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | 0 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 0 |
2 | Apartments | 719.47 |
3 | EDC, IDC, etc | 93.80 |
4 | Others Expenditure | 528 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 122.06 |
2 | EDC due as on date | 488.26 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 0 |
2 | Amount collected from allottees against booked plots and/or apartments | 0 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | 26.60 |
5 | Any other receipt | 0 |
Total | 26.60 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 26.60 |
2 | Expenditure on infrastructure & other structure | 0 |
3 | Other costs including EDC, taxes, etc | 0 |
Total | 26.60 | |
Balance | 0 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 0 |
3 | Amount withdrawn during the quarter | 0 |
4 | Balance at the end of the quarter | 0 |
Total Plots in the colony | 0 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | 0 |
Total Apartments in the colony | 0 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | 0 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 0 |
2 | Apartments | 563.98 |
3 | EDC, IDC, etc | 0 |
4 | Others Expenditure | 239 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 122.06 |
2 | EDC due as on date | 488.26 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 0 |
2 | Amount collected from allottees against booked plots and/or apartments | 1090.60 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | 0 |
5 | Any other receipt | 0 |
Total | 1090.60 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 800.10 |
2 | Expenditure on infrastructure & other structure | 0 |
3 | Other costs including EDC, taxes, etc | 215.70 |
Total | 1015.80 | |
Balance | 74.80 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 1090.6 |
3 | Amount withdrawn during the quarter | 1090.6 |
4 | Balance at the end of the quarter | 0 |
Total Apartments in the colony | 812 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | TYPE | 229 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | TYPE | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 0 |
2 | Apartments | 800.10 |
3 | EDC, IDC, etc | 0 |
4 | Others Expenditure | 215.70 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 122.06 |
2 | EDC due as on date | 488.26 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 74.80 |
2 | Amount collected from allottees against booked plots and/or apartments | 1098.90 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | 0 |
5 | Any other receipt | 0 |
Total | 1173.7 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 196.20 |
2 | Expenditure on infrastructure & other structure | 0 |
3 | Other costs including EDC, taxes, etc | 62.20 |
Total | 258.40 | |
Balance | 915.30 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 1098.90 |
3 | Amount withdrawn during the quarter | 1098.90 |
4 | Balance at the end of the quarter | 0 |
Total Plots in the colony | 0 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | TYPE | 0 |
Total Apartments in the colony | 812 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | TYPE | 211 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | TYPE | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 0 |
2 | Apartments | 196.20 |
3 | EDC, IDC, etc | 0 |
4 | Others Expenditure | 62.20 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 122.06 |
2 | EDC due as on date | 488.26 |
|