Quarterly Schedules

HRERA Panchkula
Project Registration Number : 326 OF 2017 DATED 17-10-2017
Project Name : ARIHANT SOUTH WINDS AREA OF 1.62 ACERS
Project Number : RERA-PKL-570-2019
Project Type : ONGOING
Report Online Submission Date : 25-Sep-2019



ParticularsExpenditure already incurred up to the date of registration.
(In Lakhs)
Total Estimated/ Revised cost of project. (In Lakhs)
Land2768.595845
Building2553.493775
Infrastructure facilities, etc.175.65587
Other costs including EDC, IDC, etc.1206.451593
Total6704.1811800



Name of the approvalStatusDate
Layout PlanHave not applied till dateN/A
Demarcation PlanHave not applied till dateN/A
Zoning PlanHave not applied till dateN/A
Service PlansHave not applied till dateN/A
Electricity PlansHave not applied till dateN/A



Name of the approvalStatusDate
Demarcation PlanObtained Approval on10-05-2013
Zoning PlanObtained Approval on14-01-2013
Service PlansObtained Approval on03-04-2019
Electricity PlansObtained Approval on25-09-2020
Site PlansObtained Approval on02-10-2016
Building PlansObtained Approval on25-10-2013
FIre NOCObtained Approval on03-01-2014
Total Expenditure on the project587
Expenditure made upto the date of Registration6704.18



EDC due as on the date of Registration0

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance50.11
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions-305.85
4Amount contributed by the promoters/his associates571.82
5Any other receipt0
Total265.97



S.No.Cash OutflowAmount
(In Lakhs)
1Land0
2Cost of construction of apartments168.33
3Cost of infrastructure & other structure19.43
4Other costs including EDC, taxes, etc75.87
Total263.63
Balance52.45



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
1APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK0
2APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK+SERVANT0
3APARTMENT/SHOPS/OTHER BUILDINGS TYPE 4BHK+SERVANT0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure146.82
2Apartments2097.59
3EDC, IDC, etc1148.73
4Others Expenditure2768.59



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 25-09-2019  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 25-09-2019  View 
3 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 25-09-2019  View 
4 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 25-09-2019  View 
5 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 25-09-2019  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance52.45
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions124.58
4Amount contributed by the promoters/his associates239.62
5Any other receipt0
Total364.2



S.No.Cash OutflowAmount
(In Lakhs)
1Land0
2Cost of construction of apartments244.68
3Cost of infrastructure & other structure30.71
4Other costs including EDC, taxes, etc37.68
Total313.07
Balance103.58



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
1APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK0
2APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK+SERVANT0
3APARTMENT/SHOPS/OTHER BUILDINGS TYPE 4BHK+SERVANT0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure177.53
2Apartments2342.27
3EDC, IDC, etc1186.41
4Others Expenditure2768.59



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 25-09-2019  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 25-09-2019  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 25-09-2019  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 25-09-2019  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 25-09-2019  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance103.58
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions-321.87
4Amount contributed by the promoters/his associates632.72
5Any other receipt0
Total310.85



S.No.Cash OutflowAmount
(In Lakhs)
1Land0
2Cost of construction of apartments325.59
3Cost of infrastructure & other structure25.65
4Other costs including EDC, taxes, etc56.38
Total407.62
Balance6.81



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
1APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK0
2APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK+SERVANT0
3APARTMENT/SHOPS/OTHER BUILDINGS TYPE 4BHK+SERVANT0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure203.18
2Apartments2667.86
3EDC, IDC, etc1242.79
4Others Expenditure2768.59



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 25-09-2019  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 25-09-2019  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 25-09-2019  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 25-09-2019  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 25-09-2019  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance6.81
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions-128.12
4Amount contributed by the promoters/his associates502.17
5Any other receipt0
Total380.86



S.No.Cash OutflowAmount
(In Lakhs)
1Land0
2Cost of construction of apartments308.51
3Cost of infrastructure & other structure22.28
4Other costs including EDC, taxes, etc40.91
Total371.70
Balance9.16



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
1APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK0
2APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK+SERVANT0
3APARTMENT/SHOPS/OTHER BUILDINGS TYPE 4BHK+SERVANT0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure225.46
2Apartments2976.37
3EDC, IDC, etc1283.70
4Others Expenditure2768.59



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 08-11-2019  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 08-11-2019  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 08-11-2019  View 
4 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 08-11-2019  View 
5 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 08-11-2019  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance9.16
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions-224.18
4Amount contributed by the promoters/his associates514.87
5Any other receipt0
Total299.85



S.No.Cash OutflowAmount
(In Lakhs)
1Land0
2Cost of construction of apartments194.08
3Cost of infrastructure & other structure39.12
4Other costs including EDC, taxes, etc36.10
Total269.30
Balance30.55



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
1APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK0
2APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK+SERVANT0
3APARTMENT/SHOPS/OTHER BUILDINGS TYPE 4BHK+SERVANT0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure264.58
2Apartments3170.45
3EDC, IDC, etc1319.80
4Others Expenditure2768.59



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 11-02-2020  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 11-02-2020  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 11-02-2020  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 11-02-2020  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 11-02-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance30.55
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions-46.36
4Amount contributed by the promoters/his associates200.08
5Any other receipt0
Total184.27



S.No.Cash OutflowAmount
(In Lakhs)
1Land0
2Cost of construction of apartments128.12
3Cost of infrastructure & other structure23.66
4Other costs including EDC, taxes, etc28.96
Total180.74
Balance3.53



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
1APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK0
2APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK+SERVANT0
3APARTMENT/SHOPS/OTHER BUILDINGS TYPE 4BHK+SERVANT0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure288.24
2Apartments3298.57
3EDC, IDC, etc1348.76
4Others Expenditure2768.59



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 02-07-2020  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 02-07-2020  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 02-07-2020  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 02-07-2020  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 02-07-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3.53
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions-0.52
4Amount contributed by the promoters/his associates8.02
5Any other receipt0
Total11.03



S.No.Cash OutflowAmount
(In Lakhs)
1Land0
2Cost of construction of apartments9.64
3Cost of infrastructure & other structure0
4Other costs including EDC, taxes, etc0
Total9.64
Balance1.39



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
1APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK0
2APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK+SERVANT0
3APARTMENT/SHOPS/OTHER BUILDINGS TYPE 4BHK+SERVANT0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure288.24
2Apartments3308.21
3EDC, IDC, etc1348.76
4Others Expenditure2768.59



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-07-2020  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-07-2020  View 
3 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-07-2020  View 
4 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-07-2020  View 
5 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-07-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance1.39
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions-16.18
4Amount contributed by the promoters/his associates153.61
5Any other receipt0
Total138.82



S.No.Cash OutflowAmount
(In Lakhs)
1Land0
2Cost of construction of apartments137.76
3Cost of infrastructure & other structure0
4Other costs including EDC, taxes, etc0
Total137.76
Balance1.06



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
1APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK0
2APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK+SERVANT0
3APARTMENT/SHOPS/OTHER BUILDINGS TYPE 4BHK+SERVANT0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure328.73
2Apartments3405.48
3EDC, IDC, etc1348.76
4Others Expenditure2768.59



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 20-10-2020  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 20-10-2020  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 20-10-2020  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 20-10-2020  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 20-10-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance1.06
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions-3.14
4Amount contributed by the promoters/his associates242.21
5Any other receipt0
Total240.13



S.No.Cash OutflowAmount
(In Lakhs)
1Land0
2Cost of construction of apartments114.86
3Cost of infrastructure & other structure93.71
4Other costs including EDC, taxes, etc28.64
Total237.21
Balance2.92



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
1APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK0
2APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK+SERVANT0
3APARTMENT/SHOPS/OTHER BUILDINGS TYPE 4BHK+SERVANT0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure93.71
2Apartments114.86
3EDC, IDC, etc28.64
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 21-01-2021  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 21-01-2021  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 21-01-2021  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 21-01-2021  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 21-01-2021  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance2.92
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions145
4Amount contributed by the promoters/his associates123.76
5Any other receipt0
Total271.68



S.No.Cash OutflowAmount
(In Lakhs)
1Land0
2Cost of construction of apartments137.08
3Cost of infrastructure & other structure92.80
4Other costs including EDC, taxes, etc38.48
Total268.36
Balance3.32



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
1APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK0
2APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK+SERVANT0
3APARTMENT/SHOPS/OTHER BUILDINGS TYPE 4BHK+SERVANT0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure92.80
2Apartments137.08
3EDC, IDC, etc38.48
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 14-05-2021  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 14-05-2021  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 14-05-2021  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 14-05-2021  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 14-05-2021  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3.32
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates92.50
5Any other receipt0
Total95.82



S.No.Cash OutflowAmount
(In Lakhs)
1Land0
2Cost of construction of apartments49.05
3Cost of infrastructure & other structure33.35
4Other costs including EDC, taxes, etc10.82
Total93.22
Balance2.60



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
1APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK0
2APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK+SERVANT0
3APARTMENT/SHOPS/OTHER BUILDINGS TYPE 4BHK+SERVANT0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure33.35
2Apartments49.05
3EDC, IDC, etc10.82
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 27-07-2021  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 27-07-2021  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 27-07-2021  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 27-07-2021  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 27-07-2021  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance2.60
2Amount collected from allottees against booked plots and/or apartments5
3Amount availed from the bank/financial institutions-0.45
4Amount contributed by the promoters/his associates200
5Any other receipt0
Total207.15



S.No.Cash OutflowAmount
(In Lakhs)
1Land0
2Cost of construction of apartments113.31
3Cost of infrastructure & other structure44.58
4Other costs including EDC, taxes, etc43.03
Total200.92
Balance6.23



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account3.5
3Amount withdrawn during the quarter0
4Balance at the end of the quarter3.5
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
1APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK0
2APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK+SERVANT1
3APARTMENT/SHOPS/OTHER BUILDINGS TYPE 4BHK+SERVANT0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure44.48
2Apartments113.31
3EDC, IDC, etc43.03
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 19-10-2021  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 19-10-2021  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 19-10-2021  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 19-10-2021  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 19-10-2021  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance6.23
2Amount collected from allottees against booked plots and/or apartments254.00
3Amount availed from the bank/financial institutions-77.34
4Amount contributed by the promoters/his associates55.00
5Any other receipt0.00
Total237.89



S.No.Cash OutflowAmount
(In Lakhs)
1Land0.00
2Cost of construction of apartments148.65
3Cost of infrastructure & other structure45.78
4Other costs including EDC, taxes, etc41.38
Total235.81
Balance2.08



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter3.5
2Amount deposited in Escrow Account177.80
3Amount withdrawn during the quarter181.30
4Balance at the end of the quarter0
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
1APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK0
2APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK+SERVANT2
3APARTMENT/SHOPS/OTHER BUILDINGS TYPE 4BHK+SERVANT0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure45.78
2Apartments148.65
3EDC, IDC, etc41.38
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 21-01-2022  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 21-01-2022  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 21-01-2022  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 21-01-2022  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 21-01-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance2.08
2Amount collected from allottees against booked plots and/or apartments353.12
3Amount availed from the bank/financial institutions-72.78
4Amount contributed by the promoters/his associates52.00
5Any other receipt0.00
Total334.42



S.No.Cash OutflowAmount
(In Lakhs)
1Land0.00
2Cost of construction of apartments124.29
3Cost of infrastructure & other structure43.67
4Other costs including EDC, taxes, etc22.62
Total190.58
Balance143.84



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.00
2Amount deposited in Escrow Account247.19
3Amount withdrawn during the quarter136.65
4Balance at the end of the quarter110.54
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
1APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK0
2APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK+SERVANT2
3APARTMENT/SHOPS/OTHER BUILDINGS TYPE 4BHK+SERVANT1



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure43.67
2Apartments124.29
3EDC, IDC, etc22.62
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 18-04-2022  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 18-04-2022  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 18-04-2022  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 18-04-2022  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 18-04-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance143.84
2Amount collected from allottees against booked plots and/or apartments27.96
3Amount availed from the bank/financial institutions-53.64
4Amount contributed by the promoters/his associates21.20
5Any other receipt0
Total139.36



S.No.Cash OutflowAmount
(In Lakhs)
1Land0
2Cost of construction of apartments83.65
3Cost of infrastructure & other structure29.20
4Other costs including EDC, taxes, etc21.04
Total133.89
Balance5.47



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter110.54
2Amount deposited in Escrow Account19.57
3Amount withdrawn during the quarter130.10
4Balance at the end of the quarter0.01
Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
1APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK0
2APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK+SERVANT1
3APARTMENT/SHOPS/OTHER BUILDINGS TYPE 4BHK+SERVANT0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure29.20
2Apartments83.65
3EDC, IDC, etc21.04
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 14-07-2022  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 14-07-2022  View 
3 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 14-07-2022  View 
4 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 14-07-2022  View 
5 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 14-07-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance5.47
2Amount collected from allottees against booked plots and/or apartments163.23
3Amount availed from the bank/financial institutions-60.54
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total108.16



S.No.Cash OutflowAmount
(In Lakhs)
1Land0
2Cost of construction of apartments35.86
3Cost of infrastructure & other structure53.77
4Other costs including EDC, taxes, etc14.55
Total104.18
Balance3.98



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.01
2Amount deposited in Escrow Account114.26
3Amount withdrawn during the quarter114.25
4Balance at the end of the quarter0.02
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
1APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK0
2APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK+SERVANT0
3APARTMENT/SHOPS/OTHER BUILDINGS TYPE 4BHK+SERVANT0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure53.77
2Apartments35.86
3EDC, IDC, etc14.55
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 31-10-2022  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 31-10-2022  View 
3 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 31-10-2022  View 
4 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 31-10-2022  View 
5 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 31-10-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3.98
2Amount collected from allottees against booked plots and/or apartments135.82
3Amount availed from the bank/financial institutions-359.00
4Amount contributed by the promoters/his associates288.00
5Any other receipt0.00
Total68.80



S.No.Cash OutflowAmount
(In Lakhs)
1Land0.00
2Cost of construction of apartments29.17
3Cost of infrastructure & other structure17.08
4Other costs including EDC, taxes, etc20.25
Total66.50
Balance2.30



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.02
2Amount deposited in Escrow Account95.08
3Amount withdrawn during the quarter95.10
4Balance at the end of the quarter0.00
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
10



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
10



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure17.08
2Apartments29.17
3EDC, IDC, etc20.25
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 25-01-2023  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 25-01-2023  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 25-01-2023  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 25-01-2023  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 25-01-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance2.30
2Amount collected from allottees against booked plots and/or apartments387.71
3Amount availed from the bank/financial institutions-225.28
4Amount contributed by the promoters/his associates0.00
5Any other receipt0.00
Total164.73



S.No.Cash OutflowAmount
(In Lakhs)
1Land0.00
2Cost of construction of apartments26.68
3Cost of infrastructure & other structure36.96
4Other costs including EDC, taxes, etc9.02
Total72.66
Balance92.07



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.00
2Amount deposited in Escrow Account271.39
3Amount withdrawn during the quarter215.70
4Balance at the end of the quarter55.69
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
111



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure36.96
2Apartments26.68
3EDC, IDC, etc9.02
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 20-04-2023  View 
2 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 20-04-2023  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 20-04-2023  View 
4 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 20-04-2023  View 
5 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 20-04-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance92.07
2Amount collected from allottees against booked plots and/or apartments553.53
3Amount availed from the bank/financial institutions-48.89
4Amount contributed by the promoters/his associates-312.76
5Any other receipt0
Total283.95



S.No.Cash OutflowAmount
(In Lakhs)
1Land0
2Cost of construction of apartments127.38
3Cost of infrastructure & other structure49.4
4Other costs including EDC, taxes, etc0.24
Total177.02
Balance106.93



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter55.69
2Amount deposited in Escrow Account387.47
3Amount withdrawn during the quarter443.15
4Balance at the end of the quarter0.01
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
113



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure49.40
2Apartments127.38
3EDC, IDC, etc0.24
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 17-07-2023  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 17-07-2023  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 17-07-2023  View 
4 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 17-07-2023  View 
5 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 17-07-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance106.93
2Amount collected from allottees against booked plots and/or apartments679.29
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates-627.24
5Any other receipt0
Total158.98



S.No.Cash OutflowAmount
(In Lakhs)
1Land0
2Cost of construction of apartments107.48
3Cost of infrastructure & other structure29.16
4Other costs including EDC, taxes, etc0
Total136.64
Balance22.34



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.01
2Amount deposited in Escrow Account496.51
3Amount withdrawn during the quarter476.95
4Balance at the end of the quarter19.57
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
110



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure29.16
2Apartments107.48
3EDC, IDC, etc0.00
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 13-10-2023  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 13-10-2023  View 
3 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 13-10-2023  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 13-10-2023  View 
5 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 13-10-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance22.34
2Amount collected from allottees against booked plots and/or apartments464.42
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates-165
5Any other receipt0
Total319.76



S.No.Cash OutflowAmount
(In Lakhs)
1Land0
2Cost of construction of apartments131.59
3Cost of infrastructure & other structure23.67
4Other costs including EDC, taxes, etc0
Total155.26
Balance164.5



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter19.57
2Amount deposited in Escrow Account323.69
3Amount withdrawn during the quarter341.65
4Balance at the end of the quarter1.61
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



Total Apartments in the colony70
Apartments sold upto the date of Registration1



S.No.Type/SizeApartments Sold in the Quarter
1APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK2
2APARTMENT/SHOPS/OTHER BUILDINGS TYPE 3BHK+SERVANT0
3APARTMENT/SHOPS/OTHER BUILDINGS TYPE 4BHK+SERVANT0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure23.67
2Apartments131.59
3EDC, IDC, etc0
4Others Expenditure0



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-01-2024  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-01-2024  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-01-2024  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-01-2024  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-01-2024  View