294/1 VISHWAKARMA COLONY, LAL KUAN, M.B ROAD, NEW DELHI-110044
01126360175
9560066223 (Number Shared by Promoter in Public)
OODLESSKYWALK@GMAIL.COM
http://mascotbuildcon.com
XXXX339N
U70100DL2010PTC209879
OODLES SKYWALK
VILLAGE SIHI
MANESAR
GURUGRAM
9990244570 (Number Shared by Promoter in Public)
oodlesskywalk@gmail.com
VIKRANT
9990244570 (Number Shared by Promoter in Public)
vikrantsngh66@gmail.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
159881
29-07-2017
490900
INDIAN OVERSEAS BANK
HRERA Gurugram
2
160676
31-12-2019
214745
INDIAN OVERSEAS BANK
HRERA Gurugram
3.0326 (Acre)
1.75
1.75
3.0326 (Acre)
08 of 2013(05-03-2013)
No
Address C/O HOMETOWN PROPERTY PVT LTD 8586 MANGLAPURI NEW DELHI
Annexure-B- COLLABORATION AGREEMENT
COLLABORATION AGREEMENT
Yes
OWNER SHARE 22%, DEVELOPER SHARE 78%
No
Yes
No
12452.18 Lakhs
61.71 Lakhs
6607.82 Lakhs
2526.65 Lakhs
3256.00 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
4901.41
3
CONSTRUCTION OF ROADS
2155.6
4
PAVEMENTS
983.265
5
PARKS AND PLAYGROUNDS
0
6
GREEN BELTS
950.22
7
VEHICLE PARKINGS
1965.66
8
ELECTRICITY SUB-STATION
150.48
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
105.68
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
1060.16
Total
12272.475
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HUDA
Yes
WATER SUPPLY
MCG
Yes
ELECTRICITY
DAKSHIN HARYANA BIJLI VITRAN NIGAM
Yes
SEWAGE DISPOSAL
STP
Yes
STORM WATER DRAINAGE
HUDA
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
82.77
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
209.75
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
30.75
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
900.93
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
46.60
AS PER PROJECT REPORT
6
STREET LIGHTING
5.82
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
402.80
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
0
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
20
AS PER PROJECT REPORT
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
15
ELEVATOR AND ESCALATORS
320
AS PER PROJECT REPORT
16
AIR CONDITIONING AND VENTELATION
198.91
AS PER PROJECT REPORT
17-05-2014 (date)
17-01-2014 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type A1
13576.12
470
199
271
8
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
SHOPS AND COMMERCIAL SPACES
199
CIVIL CONSTRUCTION COMPLETED FINISHING AND SERVICES WORK UNDER PROGRESS
17-03-2014
31-12-2019
31-12-2020
17-03-2014
85
31-12-2020
PROVIDED
ALREADY EXPLAINED
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0 COMMERCIAL
17-03-2014
80
31-12-2020
PROVIDED
SUBMITTED
451
0
0
64
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
9373
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
605
614.25
363.82
Plots
0
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
31.67
Water Supply System
46.00
Sewerage treatment & garbage disposal
1.00
Electricity Supply System
133.79
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
55.44
Air Conditioning and Ventilation
53.98
Escalator and Elevators
1.06
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
15
20
15.1
Water Supply System
40
40
40
Sewerage treatment & garbage disposal
0
20
25.6
Electricity Supply System
160
170
225
Storm Water Drainage
0
15
15.75
Parks and Playgrounds
0
0
0
Clubhouse/community centres
0
0
0
Shopping area
75
150
122.8
Other
0
0
0
Air conditioning
40
50
50
Escalators
0
140
120
Pending work of civil construction
50
0
0
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
470
ii. No. of Flats/ Apartments booked
199
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
9351 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
7500 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
300 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
1551 Lakhs
vii. Amount invested in the project upto the date of application
0 Lakhs
Land cost (If any)
0 Lakhs
Apartments
0 Lakhs
Infrastructure
0 Lakhs
EDC/ Taxes Etc.
0 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
0 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
82.77
31.67
II. WATER SUPPLY SYSTEM
209.75
6.00
III. STORM WATER DRAINAGE
30.75
0
IV. ELECTRICITY SUPPLY SYSTEM
900.93
62.79
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
46.60
1.00
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
198.91
53.97
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
0
0
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
402.80
55.44
XVII. OTHER FACILITIES AS PER PROJECT REPORT
227.00
1.06
Yes
Yes
INDIAN OVERSEAS BANK
107002000037350
IOBA0001070
110020027
1070
PROMOTERS
Attached
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. LICENCE NO 08 OF 2013
ALREADY BEEN OBTAINED
05-03-2013
II. BUILDING PLAN
ALREADY BEEN OBTAINED
17-01-2014
III. ENVIRONMENTAL CLEARANCE
ALREADY BEEN OBTAINED
23-10-2013
IV. AIR PORT HEIGHT CLEARANCE
ALREADY BEEN OBTAINED
03-01-2019
V. SERVICES ESTIMATE AND PLAN
ALREADY BEEN OBTAINED
26-07-2018
Yes
Yes
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
YES
2
WALL FINISHING DETAILS
YES
3
KITCHEN DETAILS
NA
4
BATHROOM FITTINGS
YES
5
WOOD WORK ETC
NA
6
DOORS AND WINDOS FRAMES
NA
7
GLASS WORK
YES
8
ELECTRIC FITTINGS
YES
9
CONDUCTING AND WIRING DETAILS
YES
10
CUPBOARD DETAILS
NA
11
WATER STORAGE
YES
12
LIFT DETAILS
YES
13
EXTERNAL GLAZINGS
YES
13.1
WINDOWS/GLAZINGS
YES
14
DOORS
YES
14.1
MAIN DOORS
YES
14.2
INTERNAL DOORS
YES
15
AIR CONDITIONING
YES
16
ELECTRICAL FITTINGS
YES
17
CNG PIPE LINE
NA
18
PROVISION OF WIFI AND BROADBAND FACILITY
NA
19
EXTERNAL FINISHING/COLOUR SCHEME
YES
20
INTERNAL FINISHING
YES
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
NA
1 . 2
WALLS
NA
1 . 3
CEILING
NA
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
NA
2 . 2
WALLS
NA
2 . 3
CEILING
NA
2 . 4
MODULAR WARDROBES
NA
3 . MASTER TOILET
3 . 1
FLOOR
NA
3 . 2
WALLS
NA
3 . 3
CEILING
NA
3 . 4
COUNTERS
NA
3 . 5
SANITARY WARE/CP FITTINGS
NA
3 . 6
FITTING/FIXTURES
NA
4 . BED ROOMS
4 . 1
FLOOR
NA
4 . 2
WALLS
NA
4 . 3
CEILING
NA
4 . 4
WARDROBES
NA
5 . TOILET
5 . 1
FLOOR
YES
5 . 2
WALLS
YES
5 . 3
CEILING
YES
5 . 4
COUNTERS
YES
5 . 5
SANITARY WARE/CP FITTINGS
YES
5 . 6
FIXTURES
YES
6 . KITCHEN
6 . 1
FLOOR
NA
6 . 2
WALLS
NA
6 . 3
CEILING
NA
6 . 4
COUNTERS
NA
6 . 5
FIXTURES
NA
6 . 6
KITCHEN APPLIANCES
NA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
NA
7 . 2
WALLS & CEILING
NA
7 . 3
TOILET
NA
7 . 4
BALCONY
NA
8 . SIT-OUTS
8 . 1
FLOOR
NA
8 . 2
WALLS & CEILING
NA
8 . 3
RAILINGS
NA
8 . 4
FIXTURES
NA
Sr. No.
Document Description
Date of Document Upload
View Document
1
04 OF 32- (04- 3RD TO 7TH FLOOR PLANS (BLOCK-1 TO 7 )
16-03-2020
------
2
2 SITE PLAN
16-03-2020
------
3
04 OF 32- (04- 3RD TO 7TH FLOOR PLANS (BLOCK-1 TO 7 )
16-03-2020
------
4
7 APPROVAL OF BUILDING PLAN
16-03-2020
------
5
5 LC-IV
16-03-2020
------
6
07 OF 32- (07- LOWER BASEMENT (BLOCK-1 TO 7 )
16-03-2020
------
7
12 ENVIRONMENT CLEARANCE...
16-03-2020
------
8
07 OF 32- (07- LOWER BASEMENT (BLOCK-1 TO 7 )
16-03-2020
------
9
14 FIRE FIGHTING SCHEME
16-03-2020
------
10
BALANCE SHEET 2016-17
16-03-2020
------
11
HOME TOWN (ANNUAL REPORT-18-19
16-03-2020
------
12
15 FOREST-CLEARANCE
16-03-2020
------
13
16 NON ENCUMBERANCE CERTIFICATE
16-03-2020
------
14
6 LOI
16-03-2020
------
15
06 OF 32- (06- UPPER BASEMENT (BLOCK-1 TO 7 )
16-03-2020
------
16
02 OF 32- (02- GROUND FLOOR PLAN (BLOCK- 1 TO 7)
16-03-2020
------
17
9 SERVICE PLAN ESTIMATES
16-03-2020
------
18
18 OF 32- (01- SITE PLAN- MEP CO-ORDINATION LAYPUT )
16-03-2020
------
19
03 OF 32- (03- FIRST & SECOND FLOOR PLANS (BLOCK-1 TO 7 )
16-03-2020
------
20
4 LICENSE
16-03-2020
------
21
03 OF 32- (03- FIRST & SECOND FLOOR PLANS (BLOCK-1 TO 7 )