9560454296 (Number Shared by Promoter in Public)
suneet.puri@experion.net.in
http://www.experion.co
XXXX138L
U70109DL2006FTC151343
WINDCHANTS PHASE-4, NURSERY SCHOOL SITE
SECTOR 112, GURUGAM
GURGAON
GURUGRAM
01244422630
9818559575 (Number Shared by Promoter in Public)
suneet.puri@experion.net.in
VAIBHAV KUMAR SHIVHARE
01244422630
9818559575 (Number Shared by Promoter in Public)
vaibhav.shivhare@experion.net.in
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
42380
24-07-2017
4965060
AXIS BANK
HRERA Gurugram
0.2 (Acre)
100
27.39
23.431 (Acre)
21 of 2008 and 28 of 2012
Yes
148.93 Lakhs
78.73 Lakhs
14.24 Lakhs
0 Lakhs
55.96 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0.2
3
CONSTRUCTION OF ROADS
0
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
Total
0.2
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
G.M.D.A.
No
WATER SUPPLY
G.M.D.A.
Yes
ELECTRICITY
D.H.B.V.N.
Yes
SEWAGE DISPOSAL
H.S.V.P.
Yes
STORM WATER DRAINAGE
H.S.V.P.
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
0
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
0
YET TO BE PREPARED
3
STORM WATER DRAINAGE
0
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
0
SUBMITTED TO HUDA
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
0
SUBMITTED TO HUDA
6
STREET LIGHTING
0
SUBMITTED TO HUDA
7
SECURITY AND FIRE FIGHTING
0
SUBMITTED TO HUDA
8
PLAYGROUNDS AND PARKS
0
SUBMITTED TO HUDA
9
CLUB HOUSE/COMMUNITY CENTRE
0
SUBMITTED TO HUDA
10
SHOPPING AREA
0
SUBMITTED TO HUDA
11
RENEWABLE ENERGY SYSTEM
0
SUBMITTED TO HUDA
12
SCHOOL
0
SUBMITTED TO HUDA
13
HOSPITAL/DISPENSARY
0
SUBMITTED TO HUDA
14
ANY OTHER
0
SUBMITTED TO HUDA
07-06-2012 (date)
07-06-2012 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type 1 NURSERY SCHOOL
809.37
1
0
1
1
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
1 NURSERY SCHOOL
0
0
28-08-2017
27-08-2019
27-08-2020
28-08-2017
100
27-08-2020
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
28-08-2017
100
27-08-2020
NIL
NIL
0
0
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
one Nursery School
139.73
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
Shops
0
Plots
0
One Nursery School
9.2
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
Shops
0
0
0
Plots
0
0
0
One Nursery School
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (2020)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
1
1 Nursery School
ii. No. of Flats/ Apartments booked
0
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
160.84 Lakhs
1 Nursery School
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
0 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
0 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
0 Lakhs
vii. Amount invested in the project upto the date of application
139.73 Lakhs
Land cost (If any)
78.73 Lakhs
Apartments
5.04 Lakhs
Infrastructure
0 Lakhs
EDC/ Taxes Etc.
55.96 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
9.2 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
9.2 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)