HRERA GurugramTemp Project Id : RERA-GRG-PROJ-359-2019
Submission Date : 30-11-2019 07:59:58 AM
Applicant Type : Firm
Project Type: NEW


GODREJ HIGHVIEW LLP
3RD FLOOR, UM HOUSE, TOWER A, PLOT 35, SECTOR-44, GURUGRAM
01244956150
9212315299 (Number Shared by Promoter in Public)
natureplus1rera@godrejproperties.com
AAH5060
AAQFG1519A













GODREJ NATURE PLUS PHASE-1
SECTOR-33, SOHNA
SOHNA
GURUGRAM
9212315299 (Number Shared by Promoter in Public)
natureplus1rera@godrejproperties.com
DEEPENDRA SINGH
1244956150
9212315299 (Number Shared by Promoter in Public)
deependra.singh@godrejproperties.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
154954820-01-2018552219HDFC BANKHRERA Gurugram
254954920-01-2018552220HDFC BANKHRERA Gurugram







15.595 (Acre)
175
174.93
18.744 (Acre)
01 of 2014(03.01.2014),01 of 2014(11.01.2018)
No
Address     902A, 9TH FLOOR D-MALL, NETAJI SUBHASH PLACE PITAMPURA NEW DELHI NEW DELHI DL 110034
Annexure-B- DEVELOPMENT AGREEMENT AND POWER OF ATTORNEY
AFTER THE GRANT OF LICENSE
Yes
GENERAL POWER OF ATTORNEY DATED 22.09.2017 BEARING DOCUMENT NO.71 REGISTERED AT TEHSIL SOHNA DEVELOPMENT AGREEMENT DATED 22.09.2017 BEARING NO. 2224 REGISTERED WITH TEHSIL SOHNA
No
No
Yes







32529.76 Lakhs
7852.11 Lakhs
28810.65 Lakhs
3719.11 Lakhs
13850.19 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS4280.55
3CONSTRUCTION OF ROADS5264.2
4PAVEMENTS2507.62
5PARKS AND PLAYGROUNDS10693.34
6GREEN BELTS0
7VEHICLE PARKINGS4102.77
8ELECTRICITY SUB-STATION194.24
9CLUB HOUSE877.5
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER35190.56
Total63110.78




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHUDA/GMDAYes
WATER SUPPLYHUDA/GMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHUDA/GMDAYes
STORM WATER DRAINAGEHUDA/GMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS547.54SUBMITTED TO TOWN & COUNTRY PLANNING
2WATER SUPPLY SYSTEM33.05SUBMITTED TO TOWN & COUNTRY PLANNING
3STORM WATER DRAINAGE79.86SUBMITTED TO TOWN & COUNTRY PLANNING
4ELECTRICITY SUPPLY SYSTEM313.61SUBMITTED TO TOWN & COUNTRY PLANNING
5SEWAGE TREATMENT & GARBAGE DISPOSAL79.86SUBMITTED TO TOWN & COUNTRY PLANNING
6STREET LIGHTING84.35SUBMITTED TO TOWN & COUNTRY PLANNING
7SECURITY AND FIRE FIGHTING31.43SUBMITTED TO TOWN & COUNTRY PLANNING
8PLAYGROUNDS AND PARKS276.73SUBMITTED TO TOWN & COUNTRY PLANNING
9CLUB HOUSE/COMMUNITY CENTRE966.29SUBMITTED TO TOWN & COUNTRY PLANNING
10SHOPPING AREA0.84SUBMITTED TO TOWN & COUNTRY PLANNING
11RENEWABLE ENERGY SYSTEM27.27SUBMITTED TO TOWN & COUNTRY PLANNING
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER134.44SUBMITTED TO TOWN & COUNTRY PLANNING


11-11-2014 (date)
11-11-2014 (date)
01-03-2018
30-01-2028
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings76.443085
Apartment/Shops/Other Buildings77.53765
Apartment/Shops/Other Buildings91.6582
Apartment/Shops/Other Buildings862245
Apartment/Shops/Other Buildings107.7962
Apartment/Shops/Other Buildings107422





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments13767.25
Shops0
Plots0
Finance3478.97

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments457
Shops0
Plots0

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1430174817651697
Shops0000
Plots0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1702228226962474
Shops0000
Plots0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments303917101005796
Shops0000
Plots0000

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments967400119336
Shops0000
Plots0000

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments710
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres15.20
Shopping area0
Other174.05

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres48
Shopping area0
Other0

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements00055
Water Supply System0003
Sewerage treatment & garbage disposal0008
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds00028
Clubhouse/community centres9748145145
Shopping area0000
Other0626262

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements11011010110
Water Supply System3333
Sewerage treatment & garbage disposal16161616
Electricity Supply System00063
Storm Water Drainage00016
Parks and Playgrounds28282828
Clubhouse/community centres97979797
Shopping area0000
Other62123123123

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements55000
Water Supply System3333
Sewerage treatment & garbage disposal8000
Electricity Supply System63636363
Storm Water Drainage1616168
Parks and Playgrounds28282828
Clubhouse/community centres484800
Shopping area001230
Other1231230123

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage8
Parks and Playgrounds28
Clubhouse/community centres0
Shopping area0
Other123












No
No
ICICI BANK DLF QUTUB PLAZA, DLF CITY PHASE1
017705010059
ICIC0000177
110229030
0177
Sushil Sharma 3rd Floor, Plot No.35, Sector 44 Gurugram











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENSEALREADY BEEN OBTAINED03-01-2014
II. LICENSE RENEWALALREADY BEEN OBTAINED07-02-2020
III. ZONING PLANALREADY BEEN OBTAINED06-01-2014
IV. BUILDING PLANALREADY BEEN OBTAINED11-11-2014
V. ENVIRONMENT CLEARANCE ALREADY BEEN OBTAINED29-12-2017
VI. FIRE SCHEME APPROVALALREADY BEEN OBTAINED17-10-2017








No


No


Agreement for Sale will be executed between the Promoter and the Alottee













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSELIVING ROOM & DINING ROOM-VITRIFIED TILES BED ROOMS-LAMINATED WOODEN FLOOR TOILETS WITH BEDROOMS-ANTI SKID CERAMIC TILE KITCHEN-ANTI SKID TILES BALCONY-ANTI SKID TILES UTILITY ROOM-CERAMIC TILES
2WALL FINISHING DETAILSLIVING ROOM & DINING ROOM-ACRYLIC EMULSION BEDROOMS-ACRYLIC EMULSION TOILETS WITH BEDROOMS-TILL 7'-0" ON ALL SIDES KITCHEN-CERAMIC TILES 2'-0" ABOVE COUNTER. UTILITY ROOM-ACRYLIC EMULSION
3KITCHEN DETAILSFLOORS-ANTI SKID TILES EXTERNAL DOORS & WINDOWS-ANODIZED/POWDER COATED ALUMINUM INTERNAL WALLS-CERAMIC TILES 2'-0" ABOVE COUNTER. FIXTURES AND FITTINGS-MARBLE / GRANITE TOP WITH STAINLESS STEEL SINK WITH DRAIN BOARD
4BATHROOM FITTINGSALL PROVIDED OF STANDARD COMPANY MAKE
5WOOD WORK ETCN/A
6DOORS AND WINDOS FRAMESPOWDER COATED ALUMINUM
7GLASS WORKYES
8ELECTRIC FITTINGSMEP
9CONDUCTING AND WIRING DETAILSMEP
10CUPBOARD DETAILSN/A
11WATER STORAGEMEP
12LIFT DETAILSYES
13EXTERNAL GLAZINGSYES
13.1WINDOWS/GLAZINGSPOWDER COATED ALUMINUM
14DOORSPOWDER COATED ALUMINUM
14.1MAIN DOORSVENEER FINISH FLUSH DOORS/MOULDED SHUTTER WITH HARDWOOD FRAME
14.2INTERNAL DOORSLAMINATED FLUSH DOORS/MOULDED SHUTTERS WITH HARDWOOD FRAMES
15AIR CONDITIONINGMEP
16ELECTRICAL FITTINGSMEP
17CNG PIPE LINEMEP
18PROVISION OF WIFI AND BROADBAND FACILITYMEP
19EXTERNAL FINISHING/COLOUR SCHEMEEXTERIOR GRADE PAINT
20INTERNAL FINISHINGACRYLIC EMULSION
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSACRYLIC EMULSION
1 . 3 CEILINGOIL BOUND DISTEMPER
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN FLOOR
2 . 2 WALLSACRYLIC EMULSION
2 . 3 CEILINGOIL BOUND DISTEMPER
2 . 4 MODULAR WARDROBESN/A
3 . MASTER TOILET
3 . 1 FLOORANTI SKID CERAMIC TILE
3 . 2 WALLSTILL 7'-0" ON ALL SIDES & ACRYLIC EMULSION
3 . 3 CEILINGGRID CEILING
3 . 4 COUNTERSYES
3 . 5 SANITARY WARE/CP FITTINGSALL PROVIDED OF STANDARD COMPANY MAKE
3 . 6 FITTING/FIXTURESALL PROVIDED OF STANDARD COMPANY MAKE
4 . BED ROOMS
4 . 1 FLOORLAMINATED WOODEN FLOOR
4 . 2 WALLSACRYLIC EMULSION
4 . 3 CEILINGOIL BOUND DISTEMPER
4 . 4 WARDROBESN/A
5 . TOILET
5 . 1 FLOORANTI SKID CERAMIC TILE
5 . 2 WALLSTILL 7'-0" ON ALL SIDES & ACRYLIC EMULSION
5 . 3 CEILINGOIL BOUND DISTEMPER
5 . 4 COUNTERSYES
5 . 5 SANITARY WARE/CP FITTINGSALL PROVIDED OF STANDARD COMPANY MAKE
5 . 6 FIXTURESALL PROVIDED OF STANDARD COMPANY MAKE
6 . KITCHEN
6 . 1 FLOORANTI SKID TILES
6 . 2 WALLSCERAMIC TILES 2'-0" ABOVE COUNTER & ACRYLIC EMULSION
6 . 3 CEILINGOIL BOUND DISTEMPER
6 . 4 COUNTERSMARBLE / GRANITE TOP
6 . 5 FIXTURESALL PROVIDED OF STANDARD COMPANY MAKE
6 . 6 KITCHEN APPLIANCESSTAINLESS STEEL SINK WITH DRAIN BOARD
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORCERAMIC TILES
7 . 2 WALLS & CEILINGACRYLIC EMULSION & OIL BOUND DISTEMPER
7 . 3 TOILETANTI SKID CERAMIC TILE
7 . 4 BALCONYANTI SKID TILES
8 . SIT-OUTS
8 . 1 FLOORANTI SKID TILES
8 . 2 WALLS & CEILINGOIL BOUND DISTEMPER
8 . 3 RAILINGSMS RAILING AS PER DESIGN
8 . 4 FIXTURESALL PROVIDED OF STANDARD COMPANY MAKE












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN27-11-2019 View Document
2NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT29-11-2019 View Document
3EWS SECTION_COMPRESSED29-11-2019 ------
4ZONING PLAN26-11-2019 View Document
5TOWER B PLAN_COMPRESSED29-11-2019 ------
6DRAFT ALLOTMENT LETTER28-11-2019 ------
7TOWER B SEC & ELE_COMPRESSED29-11-2019 ------
8TOWER C SEC & ELE 2_COMPRESSED29-11-2019 ------
9PRIMARY SCHOOL BLD_COMPRESSED29-11-2019 ------
10SECTION TOWER_COMPRESSED29-11-2019 ------
11COPY OF LICENSE ALONG WITH SCHEDULE OF LAND26-11-2019 View Document
12DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD27-11-2019 View Document
13NUSERY SCHOOL_COMPRESSED29-11-2019 ------
14DRAFT AGREEMENT TO SELL27-11-2019 ------
15GENERAL POWER OF ATTORNEY IN FAVOUR OF THE APPLICANT27-11-2019 ------
16NURSERY SEC_COMPRESSED29-11-2019 ------
17TOWER A PLAN & AREA_COMPRESSED29-11-2019 ------
18DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.27-11-2019 View Document
19PRIMARY SCHOOL ELE_COMPRESSED29-11-2019 ------
20TOWER B SEC & ELE_COMPRESSED29-11-2019 ------
21IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN29-11-2019 View Document
22COMMUNITY CENTER29-11-2019 ------
23TOWER C SEC & ELE_COMPRESSED29-11-2019 ------
24RENEWAL OF LICENCE NO. 01 OF 2014 (VALID UPTO 02.01.25)13-03-2020 ------
25DEMARCATION PLAN02-03-2020 View Document
26A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS29-11-2019 View Document
27SEWERAGE SCHEME102-03-2020 ------
28DRAINAGE SCHEME02-03-2020 ------
29WATER SUPPLY02-03-2020 ------
30ELEVATION TOWER_COMPRESSED (1)29-11-2019 ------
31EWS_COMPRESSED29-11-2019 ------
32SHOPPING_COMPRESSED29-11-2019 ------
33SITE PLAN_COMPRESSED29-11-2019 ------
34EARLIER APPROVED SITE PLAN12-03-2020 ------
35TOWER B SEC & ELE_COMPRESSED29-11-2019 ------
36APPROVAL OF FIRE SCHEME SOHNA12-03-2020 ------
37E__SITE PLAN (EXTERNAL LIGTING LAYOUT) 27-08-2019 MODEL (1)02-03-2020 ------
38E__SITE PL (SUBSTATION & METER ROOM LAY) 28-08-19 MODEL (1)02-03-2020 ------
39BUILDING PLAN APPROVAL SOHNA (2)12-03-2020 ------
40LANDSCAPE LIGHTING LAYOUT02-03-2020 ------
41REVISED SERVICE ESTIMATES12-03-2020 ------
42ROAD SCHEME102-03-2020 ------
43SEWERAGE ASSURANCE- SOHNA12-03-2020 ------
44E__SITE PLAN (EXTERNAL LIGTING LAYOUT) 27-08-2019 MODEL (1)12-03-2020 ------
45LOAD ASSURANCE12-03-2020 ------
46WATER ASSURANCE- SOHNA12-03-2020 ------
47BUILDING PLAN APPROVAL SOHNA12-03-2020 ------
48AUM SHRI ENVIRONMENTAL CLEARANCE12-03-2020 ------
49DEMARCATION PLAN12-03-2020 ------
50E__SITE PL (SUBSTATION & METER ROOM LAY) 28-08-19 MODEL (1)12-03-2020 ------
51LANDSCAPE LIGHTING LAYOUT12-03-2020 ------
52DTCP GH LICENSE SOHNA12-03-2020 ------