S-5 DDA SHOPPING COMPLEX (LSC), NEAR JEEWAN ANMOL HOSPITAL, MAYUR VIHAR PH-1, NEW DELHI-110091
01244993701
9871597440 (Number Shared by Promoter in Public)
ankurseth@elitestock.com
XXXX538F
U55101DL2002PTC114333
PICASSO CENTRE
VILLAGE GHATA, SECTOR-61
SOHNA
GURUGRAM
01244993701
9871597440 (Number Shared by Promoter in Public)
ankurseth@elitestock.com
ANKUR SETH
01244993701
9871597440 (Number Shared by Promoter in Public)
ankurseth@elitestock.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
8027
27-07-2017
385000
HDFC BANK
HRERA Gurugram
2
35501
13-04-2018
45156
HDFC BANK
HRERA Gurugram
2.362 (Acre)
150
150
2.362 (Acre)
278 of 2007 (17-12-2007)
Yes
8457 Lakhs
305 Lakhs
4469.61 Lakhs
782.39 Lakhs
2900 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
2334.41
3
CONSTRUCTION OF ROADS
750
4
PAVEMENTS
300
5
PARKS AND PLAYGROUNDS
0
6
GREEN BELTS
526.03
7
VEHICLE PARKINGS
497
8
ELECTRICITY SUB-STATION
201.53
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
4949.70
12
ANY OTHER
0
Total
9558.67
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP/MCG
No
WATER SUPPLY
HSVP/MCG
No
ELECTRICITY
DHBVN
No
SEWAGE DISPOSAL
HSVP/MCG
No
STORM WATER DRAINAGE
HSVP/MCG
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
40
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
84.12
YET TO BE PREPARED
3
STORM WATER DRAINAGE
20
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
200
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
30
YET TO BE PREPARED
6
STREET LIGHTING
4
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
150
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
20
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
34.27
YET TO BE PREPARED
15
PARKING
200
AS PER PROJECT REPORT
27-12-2012 (date)
27-12-2012 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type COMMERCIAL TYPE A
38.46
86
15
71
0
2
APARTMENT/SHOPS/OTHER BUILDINGS Type COMMERCIAL TYPE B
48.12
10
6
4
0
3
APARTMENT/SHOPS/OTHER BUILDINGS Type COMMERCIAL TYPE C
46.18
5
0
5
0
4
APARTMENT/SHOPS/OTHER BUILDINGS Type COMMERCIAL TYPE D
68.75
5
0
5
0
5
APARTMENT/SHOPS/OTHER BUILDINGS Type COMMERCIAL TYPE E
64.78
4
0
4
0
6
APARTMENT/SHOPS/OTHER BUILDINGS Type RETAIL SPACE TYPE- A
159.82
1
1
0
0
7
APARTMENT/SHOPS/OTHER BUILDINGS Type RETAIL SPACE TYPE- B
152.99
1
1
0
0
8
APARTMENT/SHOPS/OTHER BUILDINGS Type RETAIL SPACE TYPE- C
191.21
3
0
3
0
9
APARTMENT/SHOPS/OTHER BUILDINGS Type RETAIL SPACE TYPE- D
60.56
6
0
6
0
10
APARTMENT/SHOPS/OTHER BUILDINGS Type RETAIL SPACE TYPE- E
50.25
2
0
2
0
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
COMMERCIAL SPACE
21
STRUCTURE READY
RETAIL SPACE
2
STRUCTURE READY
01-01-2014
31-12-2019
31-12-2019
15-01-2018
1.27
31-12-2019
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
01-03-2018
1.27
31-12-2019
200
0
0
31
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
3433.05
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2018
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
Shops
300
300
300
Plots
0
0
0
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
Shops
135.93
Plots
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
10
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2018
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
Water Supply System
5
10
Sewerage treatment & garbage disposal
5
10
Electricity Supply System
5
20
Storm Water Drainage
0
0
Parks and Playgrounds
0
0
Clubhouse/community centres
0
0
Shopping area
0
0
Other
15
0
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
40
0
0
Water Supply System
40
9.12
0
0
Sewerage treatment & garbage disposal
10
0
0
0
Electricity Supply System
20
50
50
10
Storm Water Drainage
0
0
20
0
Parks and Playgrounds
0
0
0
20
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
40
125.88
137.39
35
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
123
(Commercial Project)
ii. No. of Flats/ Apartments booked
23
(Commercial Project)
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
2631.91 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
1917.56 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
714.35 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
0 Lakhs
vii. Amount invested in the project upto the date of application
6036.5 Lakhs
Land cost (If any)
256.06 Lakhs
Apartments
0 Lakhs
Infrastructure
0 Lakhs
EDC/ Taxes Etc.
0 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
2420.50 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
40
0
II. WATER SUPPLY SYSTEM
84.12
0
III. STORM WATER DRAINAGE
20
0
IV. ELECTRICITY SUPPLY SYSTEM
200
10
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
30
0
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
20
0
XIII. COVERED PARKING
190
0
XIV. OPEN PARKING
10
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
150
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
38.27
0
Yes
Yes
HDFC BANK, 209-214 KAILASH BUILDING, 26 KG MARG, NEW DELHI-110001
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT