HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-759-2019
Submission Date : 17-12-2019 11:00:26 AM
Applicant Type : Company
Project Type: ONGOING




SUNRAYS INFRASTRUCTURE PRIVATE LIMITED
MCF-1847/2, GALI NO. 41B SANJAY COLONY, SECTOR-23, NIT FARIDABAD, HR 121005
9899995581 (Number Shared by Promoter in Public)
rera@efawplaza.com
http://www.efawplaza.com/
XXXX668C
U70101HR2011PTC041868
 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 







EFAW PLAZA
SECTOR 79, VILLAGE BADOLI, FARIDABAD, HARYANA
FARIDABAD
FARIDABAD
9899995581 (Number Shared by Promoter in Public)
rera@efawplaza.com
DEEPAK TIWARI
8076605333 (Number Shared by Promoter in Public)
d.tiwari1012@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
175231-07-2017328653HDFC BANKHRERA Panchkula
221002416-11-2019167610IDFC FIRST BANKHRERA Panchkula







2.725 (Acre)
1.5
1.5
2.725 (Acre)
License No. 14 of 2015
Yes







7185 Lakhs
0 Lakhs
4230 Lakhs
150 Lakhs
2805 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD112
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS1.047
3CONSTRUCTION OF ROADS0.95
4PAVEMENTS0.178
5PARKS AND PLAYGROUNDS0
6GREEN BELTS0
7VEHICLE PARKINGS0.52
8ELECTRICITY SUB-STATION0.03
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.037
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total114.762




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHUDAYes
WATER SUPPLYHUDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHUDAYes
STORM WATER DRAINAGEHUDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS15SUBMITTED TO HUDA
2WATER SUPPLY SYSTEM10SUBMITTED TO HUDA
3STORM WATER DRAINAGE10SUBMITTED TO HUDA
4ELECTRICITY SUPPLY SYSTEM60SUBMITTED TO HUDA
5SEWAGE TREATMENT & GARBAGE DISPOSAL15SUBMITTED TO HUDA
6STREET LIGHTING15SUBMITTED TO HUDA
7SECURITY AND FIRE FIGHTING15SUBMITTED TO HUDA
8PLAYGROUNDS AND PARKS10SUBMITTED TO HUDA
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


NA (date)
NA (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-24214.411012
2APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-25265.422022
3APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-26268.81100102
4APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-27257.062022
5APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-1161.431012
6APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-2106.969362
7APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-346.812022
8APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-447.886152
9APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-547.592112
10APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-6194.611012
11APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-7116.111012
12APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-886.679092
13APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-929.742022
14APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-1030.696062
15APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-1118.32022
16APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-1284.841012
17APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-13155.252022
18APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-14110.41183152
19APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-1547.454042
20APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-1648.92121112
21APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-1738.414132
22APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-18108.062022
23APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-19262.571012
24APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-20265.965052
25APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-21244.841012
26APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-22226.621012
27APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-23229.55052






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
TYPE-23EXCAVAION DONE, BASMENT UNDER CONSTRUCTION, WITH 75% OF THE ROOF OF BASEMENT ALREADY CASTED.
TYPE-41EXCAVAION DONE, BASMENT UNDER CONSTRUCTION, WITH 75% OF THE ROOF OF BASEMENT ALREADY CASTED.
TYPE-51EXCAVAION DONE, BASMENT UNDER CONSTRUCTION, WITH 75% OF THE ROOF OF BASEMENT ALREADY CASTED.
TYPE-143EXCAVAION DONE, BASMENT UNDER CONSTRUCTION, WITH 75% OF THE ROOF OF BASEMENT ALREADY CASTED.
TYPE-161EXCAVAION DONE, BASMENT UNDER CONSTRUCTION, WITH 75% OF THE ROOF OF BASEMENT ALREADY CASTED.
TYPE-171EXCAVAION DONE, BASMENT UNDER CONSTRUCTION, WITH 75% OF THE ROOF OF BASEMENT ALREADY CASTED.
TYPE-41EXCAVAION DONE, BASMENT UNDER CONSTRUCTION, WITH 75% OF THE ROOF OF BASEMENT ALREADY CASTED.
TYPE-51EXCAVAION DONE, BASMENT UNDER CONSTRUCTION, WITH 75% OF THE ROOF OF BASEMENT ALREADY CASTED.
TYPE-143EXCAVAION DONE, BASMENT UNDER CONSTRUCTION, WITH 75% OF THE ROOF OF BASEMENT ALREADY CASTED.
TYPE-161EXCAVAION DONE, BASMENT UNDER CONSTRUCTION, WITH 75% OF THE ROOF OF BASEMENT ALREADY CASTED.
TYPE-171EXCAVAION DONE, BASMENT UNDER CONSTRUCTION, WITH 75% OF THE ROOF OF BASEMENT ALREADY CASTED.
TYPE-41EXCAVAION DONE, BASMENT UNDER CONSTRUCTION, WITH 75% OF THE ROOF OF BASEMENT ALREADY CASTED.
TYPE-51EXCAVAION DONE, BASMENT UNDER CONSTRUCTION, WITH 75% OF THE ROOF OF BASEMENT ALREADY CASTED.
TYPE-143EXCAVAION DONE, BASMENT UNDER CONSTRUCTION, WITH 75% OF THE ROOF OF BASEMENT ALREADY CASTED.
TYPE-161EXCAVAION DONE, BASMENT UNDER CONSTRUCTION, WITH 75% OF THE ROOF OF BASEMENT ALREADY CASTED.
TYPE-171EXCAVAION DONE, BASMENT UNDER CONSTRUCTION, WITH 75% OF THE ROOF OF BASEMENT ALREADY CASTED.


03-12-2015
02-12-2020
02-12-2020
03-12-2015
16.67
02-12-2020
ATTACHED


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
01-12-2016
0
02-12-2020
NOT APPLICABLE
NOT APPLICABLE


0
0
183
169
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops525
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other25

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar












Particulars Remarks, if any
i. No. of Flats/Apartments constructed0Project under construction. Excavaion done, basment under construction, with 75% of the roof of basement already casted.
ii. No. of Flats/ Apartments booked10(collaboation agreements)
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter140 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter140 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter0 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter0 Lakhs
vii. Amount invested in the project upto the date of application0 Lakhs
Land cost (If any)697.425 Lakhs
Apartments525 Lakhs
Infrastructure25 Lakhs
EDC/ Taxes Etc.1048 Lakhs(Incudes EDC, IDC paid and other charge including license fees, building plan fee etc.)
viii. Balance cost to be incurred for completion of the project and delivery of possession5587 Lakhs(Balance Cost includes cost of construction, cost of infrastructure and Balance EDC/IDC on estimated basis)
(a) In respect of existing allottees498.84 Lakhs
(b) In respect of rest of the project5088.16 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS150
II. WATER SUPPLY SYSTEM100
III. STORM WATER DRAINAGE100
IV. ELECTRICITY SUPPLY SYSTEM600
V. SEWAGE TREATMENT & GARBAGE DISPOSAL150
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER1525
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.100
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM150
XVII. OTHER FACILITIES AS PER PROJECT REPORT00









Yes
Yes
HDFC BANK-SCO, F 44, SECTOR 29,DEL FARIDABAD-121008, HARYANA
50200019285945
HDFC0000707
110240108
000707
Mr. Kapil Singhal
Attached











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENCE ALREADY BEEN OBTAINED03-12-2015
II. REVENUE RASTA APPROVALALREADY BEEN OBTAINED03-08-2017
III. FOREST CLEARANCEALREADY BEEN OBTAINED30-09-2016
IV. HARYANA STATE POLLUTION CONTROL BOARDALREADY BEEN OBTAINED02-02-2018
V. BUILDING PLANS APPROVALALREADY BEEN OBTAINED27-12-2016
VI. ENVIRONMENTAL CLEARANCEALREADY BEEN OBTAINED09-11-2017
VII. DAKSHIN HARYANA BIJLI VITRAN NIGAM ALREADY BEEN OBTAINED21-10-2016
VIII. SUPPLY OF FRESH WATER APPROVAL FROM HUDAALREADY BEEN OBTAINED26-09-2016
IX. SUPPLY OF TREATED WATER APPROVAL FROM HUDAALREADY BEEN OBTAINED26-09-2016
X. SITE PLAN APPROVALALREADY BEEN OBTAINED01-04-2014








Yes


Yes


The draft agreement is on lines of standard draft prescribed by HRERA













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSESTAIRCASE WELL AREA - GRANITE/LOCAL STONE/KOTA STONE BASEMENT - VDF /TRIMIX UNITS - RAW FLOOR ( UNFINISHED) CORRIDORS - GRANITE/LOCAL STONE/KOTA STONE PLAZA - COMMERCIAL TILE/PAVER TILES/LOCAL STONE
2WALL FINISHING DETAILSBASEMENT - PAINTED ( OBD) INTERNAL WALL - UNFINISHED BLOCK WORK OUTER WALL - PAINTED ( ACRYLIC EMULSION /TEXTURE PAINT) STAIRCASE /CORRIDORS - PAINTED ( PLASTIC EMULSION /ACRYLIC EMULSION/TEXTURE PAINT)
3KITCHEN DETAILSN.A
4BATHROOM FITTINGSN.A
5WOOD WORK ETCN.A
6DOORS AND WINDOS FRAMESDOORS- HARDWOOD/WPC FRAMES WINDOWS - ALUMINUM ANODIZED/POWER COATED
7GLASS WORK12 MM THICK TOUGHENED GLASS
8ELECTRIC FITTINGSMODULAR SWITCHED - ANCHOR ROMA /LEGRAND /HAVELLS COMMON AREA / CORRIDOR LED LIGHTS
9CONDUCTING AND WIRING DETAILSPVC CONDUCTING AND COPPER WIRING - FINOLEX/HAVELLS/POLYCAB/KEI
10CUPBOARD DETAILSN.A
11WATER STORAGERCC OVER HEAD AND UNDER GROUND TANKS
12LIFT DETAILSIN BLOCK-A ( 12 NOS - 4 PASSENGER AND 2 NOS - 13 PASSENGER MRL LIFT) IN BLOCK-B ( 7 NOS - 4 PASSENGER AND 1 NOS - 13 PASSENGER MRL LIFT)
13EXTERNAL GLAZINGSALUMINUM ANODIZED/POWER COATED WITH 12 MM THICK TOUGHENED GLASS
13.1WINDOWS/GLAZINGSALUMINUM ANODIZED/POWER COATED WITH 12 MM THICK TOUGHENED GLASS
14DOORSFLUSH /SKIN MOLDED/ TOUGHENED GLASS DOORS
14.1MAIN DOORSFLUSH /SKIN MOLDED/ TOUGHENED GLASS DOORS
14.2INTERNAL DOORSFLUSH /SKIN MOLDED
15AIR CONDITIONINGN.A
16ELECTRICAL FITTINGS COPPER WIRING - FINOLEX/HAVELLS/POLYCAB/KEI MODULAR SWITCHES - ANCHOR ROMA /LEGRAND /HAVELLS
17CNG PIPE LINEN.A
18PROVISION OF WIFI AND BROADBAND FACILITYN.A
19EXTERNAL FINISHING/COLOUR SCHEMEPAINTED- ACRYLIC EMULSION EXTERIOR GRADE /TEXTURE PAINT
20INTERNAL FINISHINGUNITS - UNFINISHED FLOOR AND BLOCK WALLS BASEMENT - VDF / TRIMIX FLOORING AND OBD PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORN.A
1 . 2 WALLSN.A
1 . 3 CEILINGN.A
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORN.A
2 . 2 WALLSN.A
2 . 3 CEILINGN.A
2 . 4 MODULAR WARDROBESN.A
3 . MASTER TOILET
3 . 1 FLOORN.A
3 . 2 WALLSN.A
3 . 3 CEILINGN.A
3 . 4 COUNTERSN.A
3 . 5 SANITARY WARE/CP FITTINGSN.A
3 . 6 FITTING/FIXTURESN.A
4 . BED ROOMS
4 . 1 FLOORN.A
4 . 2 WALLSN.A
4 . 3 CEILINGN.A
4 . 4 WARDROBESN.A
5 . TOILET
5 . 1 FLOORN.A
5 . 2 WALLSN.A
5 . 3 CEILINGN.A
5 . 4 COUNTERSN.A
5 . 5 SANITARY WARE/CP FITTINGSN.A
5 . 6 FIXTURESN.A
6 . KITCHEN
6 . 1 FLOORN.A
6 . 2 WALLSN.A
6 . 3 CEILINGN.A
6 . 4 COUNTERSN.A
6 . 5 FIXTURESN.A
6 . 6 KITCHEN APPLIANCESN.A
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORN.A
7 . 2 WALLS & CEILINGN.A
7 . 3 TOILETN.A
7 . 4 BALCONYN.A
8 . SIT-OUTS
8 . 1 FLOORN.A
8 . 2 WALLS & CEILINGN.A
8 . 3 RAILINGSN.A
8 . 4 FIXTURESN.A












Sr. No.Document DescriptionDate of Document UploadView Document
1A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS09-12-2019 View Document
2NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT10-12-2019 View Document
3SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN09-12-2019 View Document
4ZONING PLAN09-12-2019 View Document
5DRAFT ALLOTMENT LETTER 10-12-2019 ------
6IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN10-12-2019 View Document
7DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.09-12-2019 View Document
8DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD09-12-2019 View Document
9IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN09-12-2019 View Document
10COPY OF LICENSE ALONG WITH SCHEDULE OF LAND09-12-2019 View Document
11DEMARCATION PLAN10-12-2019 View Document
12AGREEMENT FOR SALE10-12-2019 ------
13BALANCESHEETS10-12-2019 ------
14CASH FLOW STATEMENT OF THE PROPOSED PROJECT17-12-2019 View Document
15APPROVALS-ENVIRONMENTAL CLEARANCE17-12-2019 ------
16BUILDING PLAN APPROVAL17-12-2019 ------
17FRESH WATER APPROVAL17-12-2019 ------
18CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT17-12-2019 View Document
19TREATED WATER APPROVAL17-12-2019 ------
20SITE PLAN17-12-2019 ------
21JAMABANDI INTKAL17-12-2019 ------
22STATE POLLUTION CONTROL BOARD17-12-2019 ------
23SERVICES PLAN17-12-2019 ------
24FORST NOC17-12-2019 ------
25REVENUE RASTA17-12-2019 ------












Sr. No.Document DescriptionDate of Document UploadView Document
1 CORRIGENDUM 30-06-2021 View Document