HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-754-2019
Submission Date : 09-11-2019 04:59:37 AM
Applicant Type : Company
Project Type: ONGOING




H L RESIDENCY PRIVATE LIMITED
B-12, VISHRANTIKA APPARTMENT, PLOT NO.- 5A, SECTOR-3, DWARKA DELHI SOUTH WEST DELHI DL 110075 IN
01276297888
9958488889 (Number Shared by Promoter in Public)
hlresidency@gmail.com
https://hlcity.in
XXXX294A
U45200DL2010PTC210343
 
 


 
 


 
 


 
 







HL CITY
HL CITY, SECTOR-37
BAHADURGARH
JHAJJAR
01276297888
8813888101 (Number Shared by Promoter in Public)
HLRESIDENCY@GMAIL.COM
ADITYA KUMAR
01276297888
8813888101 (Number Shared by Promoter in Public)
HLRESIDENCY@GMAIL.COM








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
11779731-07-2017730433AXIS BANK BAHADURGARHHRERA Panchkula
2031-07-2017164634AXIS BANK BAHADURGARHHRERA Panchkula







35.38579 (Acre)
18.393
52.622
35.38579 (Acre)
102 OF 2012, 143 OF 2014 (27-09-2012)
Yes







15514 Lakhs
3390 Lakhs
2674 Lakhs
4850 Lakhs
4600 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD13.973
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS4.42
3CONSTRUCTION OF ROADS15.169
4PAVEMENTS0
5PARKS AND PLAYGROUNDS1.66
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.158
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total35.38




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSNO EXTERNAL AGENCIES INVOLVEDNo
WATER SUPPLYNO EXTERNAL AGENCIES INVOLVEDNo
ELECTRICITYNO EXTERNAL AGENCIES INVOLVEDNo
SEWAGE DISPOSALNO EXTERNAL AGENCIES INVOLVEDNo
STORM WATER DRAINAGENO EXTERNAL AGENCIES INVOLVEDNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS880YET TO BE PREPARED
2WATER SUPPLY SYSTEM296YET TO BE PREPARED
3STORM WATER DRAINAGE245YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM0YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL246YET TO BE PREPARED
6STREET LIGHTING135YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS20YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER1108YET TO BE PREPARED
15ADMINISTRATIVE EXPENSES1920YET TO BE PREPARED


17-05-2017 (date)
09-01-2013 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1PLOT Type 127.681100
2PLOT Type 125.691100
3PLOT Type 123.791100
4PLOT Type 121.791100
5PLOT Type 119.81100
6PLOT Type 117.81100
7PLOT Type 115.811100
8PLOT Type 113.811100
9PLOT Type 110.821100
10PLOT Type EWS53.6170170
11PLOT Type EWS50.02510510
12PLOT Type 945.772200
13PLOT Type 848.632200
14PLOT Type 457.681100
15PLOT Type 454.41100
16PLOT Type 403.21100
17PLOT Type 394.751100
18PLOT Type 388.721100
19PLOT Type 386.881100
20PLOT Type 366.021100
21PLOT Type 347.763300
22PLOT Type 345.621100
23PLOT Type 344.831100
24PLOT Type 308.43300
25PLOT Type 304.31100
26PLOT Type 303.122200
27PLOT Type 301.86600
28PLOT Type 298.891100
29PLOT Type 298.281100
30PLOT Type 292.32200
31PLOT Type 288454410
32PLOT Type 279.121100
33PLOT Type 278.321100
34PLOT Type 275.21100
35PLOT Type 273.41100
36PLOT Type 272.661100
37PLOT Type 266.642200
38PLOT Type 260.43300
39PLOT Type 256.661100
40PLOT Type 244.921100
41PLOT Type 227.41100
42PLOT Type 222.111100
43PLOT Type 214.66600
44PLOT Type 211.584400
45PLOT Type 205.872200
46PLOT Type 200232300
47PLOT Type 183.2141310
48PLOT Type 180.811100
49PLOT Type 180131300
50PLOT Type 174.79900
51PLOT Type 145.871100
52PLOT Type 136.661100
53PLOT Type 134.661100
54PLOT Type 132.671100
55PLOT Type 129.681100
56PLOT Type 128.251100






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
5CONSTRUCTED & HANDED OVER 15 FLOOR
77CONSTRUCTED & HANDED OVER 231 FLOOR
6CONSTRUCTED & HANDED OVER 18 FLOOR
5CONSTRUCTED & HANDED OVER 15 FLOOR
2CONSTRUCTED & HANDED OVER 6 FLOOR
77CONSTRUCTED & HANDED OVER 231 FLOOR
6CONSTRUCTED & HANDED OVER 18 FLOOR
5CONSTRUCTED & HANDED OVER 15 FLOOR
77CONSTRUCTED & HANDED OVER 231 FLOOR
6CONSTRUCTED & HANDED OVER 18 FLOOR


N/A
N/A
N/A
05-03-2013
100
01-03-2018
PART COMPLETION CERTIFICATE RECEIVED VIDE MEMO NO. 7646 DATED 01.03.2018


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
05-03-2013
100
01-03-2018
PART COMPLETION CERTIFICATE RECEIVED VIDE MEMO NO. 7646 DATED 01.03.2018


0
0
0
0
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements880
Water Supply System296
Sewerage treatment & garbage disposal245
Electricity Supply System0
Storm Water Drainage246
Parks and Playgrounds20
Clubhouse/community centres0
Shopping area0
Other1108
Administrative Expenses1920
Street Lightning135

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar












Particulars Remarks, if any
i. No. of Flats/Apartments constructed270
ii. No. of Flats/ Apartments booked270
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter0 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter19820 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter0 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter0 Lakhs
vii. Amount invested in the project upto the date of application0 Lakhs
Land cost (If any)3390 Lakhs
Apartments2674 Lakhs
Infrastructure4850 Lakhs
EDC/ Taxes Etc.4600 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession0 Lakhs
(a) In respect of existing allottees0 Lakhs
(b) In respect of rest of the project0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS00
II. WATER SUPPLY SYSTEM00
III. STORM WATER DRAINAGE00
IV. ELECTRICITY SUPPLY SYSTEM00
V. SEWAGE TREATMENT & GARBAGE DISPOSAL00
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.00
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM00
XVII. OTHER FACILITIES AS PER PROJECT REPORT00









Yes
Yes
AXIS BANK BAHADURGARH
913020011675582
UTIB0000627
110211056
000627
RAKESH KUMAR JOON, H L CITY, HOUSE NO. 2, SECTOR 37, BAHADURGARH, HARYANA-124 507
ATTACHED











Yes
Yes
Yes
Yes
No
Yes
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO. 102 OF 2012 & 143 OF 2014ALREADY BEEN OBTAINEDNA
II. MAP APPROVALALREADY BEEN OBTAINEDNA
III. HUDA WATER CONNECTIONALREADY BEEN OBTAINED20-01-2017
IV. FOREST AUTHORITYALREADY BEEN OBTAINED10-10-2017
V. NATIONAL HIGHWAY AUTHORITYALREADY BEEN OBTAINED25-08-2009
VI. POLLUTION CONTROL BOARDALREADY BEEN OBTAINED11-05-2018








Yes


No


Buyer Builder Agreement













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILES
2WALL FINISHING DETAILSPOP + PUTTY + ASIAN ROYAL
3KITCHEN DETAILSMODULAR KITCHEN WITH CHIMNEY
4BATHROOM FITTINGSONE WASH BASIN, ONE ENGLISH SEAT, WITH CP FITTING + ALL ACCESSORIES
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESWOOD FRAME
7GLASS WORKON EXTERNAL WINDOW
8ELECTRIC FITTINGSISI MARK SWITCH SOCKET
9CONDUCTING AND WIRING DETAILSIN PVC CONDUITS WITH COPPER WIRING
10CUPBOARD DETAILSIN ALL ROOM CUPBOARD
11WATER STORAGEA COMMON TANK PVC HALF DAY CAPACITY PROVIDED
12LIFT DETAILSNA
13EXTERNAL GLAZINGSSS RAILING
13.1WINDOWS/GLAZINGS4MM GLASS
14DOORSFLUSH DOOR SHUTTER
14.1MAIN DOORSSAFETY DOOR
14.2INTERNAL DOORSFLUSH DOOR SHUTTER
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYYES
19EXTERNAL FINISHING/COLOUR SCHEMETEXTURE PAINT
20INTERNAL FINISHINGASIAN ROYAL
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSWALL POP + PUTTY + ASIAN ROYAL
1 . 3 CEILINGPOP + PUTTY + ASIAN ROYAL
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILES
2 . 2 WALLSWALL POP + PUTTY + ASIAN ROYAL
2 . 3 CEILINGPOP + PUTTY + ASIAN ROYAL
2 . 4 MODULAR WARDROBESYES/ MODULAR
3 . MASTER TOILET
3 . 1 FLOORNON SKID TILES
3 . 2 WALLSGLAZED TILES
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSONE WASH BASIN, ONE ENGLISH SEAT WITH CP FITTING
3 . 6 FITTING/FIXTURESALL
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES
4 . 2 WALLSWALL POP + PUTTY + ASIAN ROYAL
4 . 3 CEILINGPOP + PUTTY + ASIAN ROYAL
4 . 4 WARDROBESMODULAR WARDROBES
5 . TOILET
5 . 1 FLOORNON SKID CERAMIC TILES
5 . 2 WALLSGLAZED TILES
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSONE WASH BASIN, ONE ENGLISH SEAT WITH CP FITTING
5 . 6 FIXTURESALL
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILES
6 . 2 WALLSGLAZED TILES 2 FEET ABOVE COUNTER
6 . 3 CEILINGPOP + PUTTY + ASIAN ROYAL
6 . 4 COUNTERSGRANITE STONE ON MODULAR KITCHEN
6 . 5 FIXTURESSTAINLESS STEEL SINK DRAIN BOARD
6 . 6 KITCHEN APPLIANCESCHIMNEY
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNON SKID TILES
7 . 2 WALLS & CEILINGPUTTY + ASIAN ROYAL
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNON SKID TILES
8 . 2 WALLS & CEILINGPOP + PUTTY + ASIAN ROAL
8 . 3 RAILINGSSS RAILING
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT08-11-2019 View Document
2IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN09-11-2019 View Document
3IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN09-11-2019 View Document
4COPY OF LICENSE ALONG WITH SCHEDULE OF LAND08-11-2019 View Document
5CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT09-11-2019 View Document
6A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS09-11-2019 View Document
7DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.09-11-2019 View Document
8CASH FLOW STATEMENT OF THE PROPOSED PROJECT09-11-2019 View Document
9DEMARCATION PLAN09-11-2019 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 Part Completion Certificate dated-01-03-2018 and Occupation Certificate dated-28-01-2020 granted 30-01-2024 View Document