9971091904 (Number Shared by Promoter in Public)
compliances@raheja.com
AJAY MOHANTI
9971091904 (Number Shared by Promoter in Public)
compliances@raheja.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
52019092100352367
21-09-2019
682906.00
AXIS BANK
HRERA Gurugram
2.8125 (Acre)
0
0
2.8125 (Acre)
119 of 2019
No
Address H.NO. 2865, SECTOR-46, GURUGRAM, HARYANA
Address H.NO. 802, SECTOR-10A, GURUGRAM, HARYANA
Address H. NO. 1188, SECTOR-6, PART-II, DHARUHERA, REWARI, HARYANA
Address H.NO. 1438, SECTOR-10A, GURUGRAM, HARYANA
Address VILLAGE AND P.O. RAJOKARI, NEW DELHI
Annexure-B- COLLABORATOR
COLLABORATION AGREEMENT AND GENERAL POWER OF ATTORNEY
Yes
YES
No
Yes
Yes
5098 Lakhs
1324 Lakhs
0.000 Lakhs
309 Lakhs
3465 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0.984
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0.000
3
CONSTRUCTION OF ROADS
1.6879
4
PAVEMENTS
0.000
5
PARKS AND PLAYGROUNDS
0.1406
6
GREEN BELTS
0.000
7
VEHICLE PARKINGS
0.000
8
ELECTRICITY SUB-STATION
0.000
9
CLUB HOUSE
0.000
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0.000
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.000
12
ANY OTHER
0.000
Total
2.8125
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HUDA/GMDA
No
WATER SUPPLY
GMDA
No
ELECTRICITY
DHBVN
No
SEWAGE DISPOSAL
GMDA
No
STORM WATER DRAINAGE
GMDA
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
100.13
SUBMITTED TO HUDA
2
WATER SUPPLY SYSTEM
52.43
SUBMITTED TO HUDA
3
STORM WATER DRAINAGE
31
SUBMITTED TO HUDA
4
ELECTRICITY SUPPLY SYSTEM
94
SUBMITTED TO HUDA
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
28.12
SUBMITTED TO HUDA
6
STREET LIGHTING
4.32
SUBMITTED TO HUDA
7
SECURITY AND FIRE FIGHTING
3.05
SUBMITTED TO HUDA
8
PLAYGROUNDS AND PARKS
0
SUBMITTED TO HUDA
9
CLUB HOUSE/COMMUNITY CENTRE
0
SUBMITTED TO HUDA
10
SHOPPING AREA
0
SUBMITTED TO HUDA
11
RENEWABLE ENERGY SYSTEM
1
SUBMITTED TO HUDA
12
SCHOOL
0
SUBMITTED TO HUDA
13
HOSPITAL/DISPENSARY
0
SUBMITTED TO HUDA
14
ANY OTHER
0
SUBMITTED TO HUDA
15
ROAD SIDE PLANTING AND TREES
0.92
SUBMITTED TO HUDA
16
ELECTRICITY SUBSTATION
94
SUBMITTED TO HUDA
26-08-2019 (date)
26-08-2019 (date)
26-08-2019
13-09-2024
Plot Area(In Square Meter)
Number of plots in the project
78.299
8
74.930
1
84.138
1
116.838
6
74.503
6
54.92
14
94.973
5
101.003
5
71.374
2
81.953
1
66.124
1
51.915
1
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
1926
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
Shops
0
Plots
235
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
235
311
317
251
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
244
239
239
239
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
222
220
199
74
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
Shops
0
0
0
Plots
74
37
37
Expenditure incurred till the date of application (In Lakhs)
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT