K-108, ATRIUM, SHOOTING RANGE ROAD, SURAJ KUND, FARIDABAD (HARYANA)-121009
01294196600
9873676990 (Number Shared by Promoter in Public)
kaushal@zionpromoter.com
http://zionpromoter.com
XXXX271K
U45201DL2004PTC129512
STONECROP
SECTOR-78, FARIDABAD
FARIDABAD
FARIDABAD
9582587506 (Number Shared by Promoter in Public)
info@zionpromoter.com
MUNNA LAL
9582587506 (Number Shared by Promoter in Public)
info@zionpromoter.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
514886
22-07-2019
296003
ICICI BANK LTD.
HRERA Panchkula
2
515389
22-08-2019
222007
ICICI BANK LTD
HRERA Panchkula
16912.544 (Sqr/mtrs)
264516.56
175
151152.32 (Sqr/mtrs)
37 of 2007, 38 of 2007, 39 of 2007 dt. 23.01.2007
No
Address R-13, 2ND FLOOR, GREATER KAILASH-I, NEW DELHI-110048
Annexure-B- GPA AND AGREEMENT
AFTER GRANT OF LICENSE
Yes
FSI PURCHASE
No
No
Yes
7464 Lakhs
2230 Lakhs
4160 Lakhs
501 Lakhs
573 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
2339.303
3
CONSTRUCTION OF ROADS
4799.27
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
1896
6
GREEN BELTS
2396.14
7
VEHICLE PARKINGS
9243.70
8
ELECTRICITY SUB-STATION
80
9
CLUB HOUSE
455
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
126
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
Total
21335.413
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
WITH THE LICENSEE COMPANY
Yes
WATER SUPPLY
WITH THE LICENSEE COMPANY
Yes
ELECTRICITY
WITH THE LICENSEE COMPANY
Yes
SEWAGE DISPOSAL
WITH THE LICENSEE COMPANY
Yes
STORM WATER DRAINAGE
WITH THE LICENSEE COMPANY
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
85.78
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
49.85
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
15.67
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
300
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
125
AS PER PROJECT REPORT
6
STREET LIGHTING
15
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
101
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
22.88
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
65.88
AS PER PROJECT REPORT
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
22-11-2007 (date)
22-11-2007 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Total size of the plots/carpet area of the apartments
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type 2 BHK
62.282
84
5231.688
66
18
4
2
APARTMENT/SHOPS/OTHER BUILDINGS Type 2 BHK
66.821
104
6949.384
86
18
4
3
APARTMENT/SHOPS/OTHER BUILDINGS Type 2+1 BHK
76.519
54
4132.026
46
8
4
4
APARTMENT/SHOPS/OTHER BUILDINGS Type 3 BHK
84.70
28
2371.6
28
0
4
5
APARTMENT/SHOPS/OTHER BUILDINGS Type 3 BHK
90.617
28
2537.276
22
6
4
6
APARTMENT/SHOPS/OTHER BUILDINGS Type 3 BHK
85.895
4
343.58
0
4
4
Total
302
21565.554
248
54
24
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
2 BHK
152
TOWER FINISHING WORK IS COMPLETED AND FINISHING WORK OF NON TOWER AREA IS GOING ON
2+1 BHK
46
TOWER FINISHING WORK IS COMPLETED AND FINISHING WORK OF NON TOWER AREA IS GOING ON
3 BHK
50
TOWER FINISHING WORK IS COMPLETED AND FINISHING WORK OF NON TOWER AREA IS GOING ON
01-06-2008
31-05-2011
31-12-2019
01-06-2008
95
31-12-2019
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
01-06-2008
95
31-12-2019
331
53
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
6597.03
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
25
75
Shops
0
0
Plots
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
85.78
Water Supply System
49.85
Sewerage treatment & garbage disposal
125.00
Electricity Supply System
210.00
Storm Water Drainage
15.67
Parks and Playgrounds
22.88
Clubhouse/community centres
65.88
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
100
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
302
ii. No. of Flats/ Apartments booked
230
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
6325.80 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
5891.00 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
434.60 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
434.60 Lakhs
vii. Amount invested in the project upto the date of application
0 Lakhs
Land cost (If any)
22.29 Lakhs
Apartments
4283.94 Lakhs
Infrastructure
575.06 Lakhs
EDC/ Taxes Etc.
0 Lakhs
INCLUDED IN LAND COST
viii. Balance cost to be incurred for completion of the project and delivery of possession
225.00 Lakhs
(a) In respect of existing allottees
225.00 Lakhs
(b) In respect of rest of the project
0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
0
0
II. WATER SUPPLY SYSTEM
0
0
III. STORM WATER DRAINAGE
0
0
IV. ELECTRICITY SUPPLY SYSTEM
0
0
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
0
0
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
0
0
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
0
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
0
0
Yes
No
ICICI BANK LTD., CHARMWOOD BRANCH, SURAJ KUND ROAD, FARIDABAD (HARYANA)-121009
184205000427
ICIC0001842
110229212
001842
BASANT KUMAR GANDHI HOUSE NO. 1475, SECTOR-16, FARIDABAD
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. WITH THE LICENSEE COMPANY
ALREADY BEEN OBTAINED
NA
Yes
Yes
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
VERTIFIED/CERAMIC TILES
2
WALL FINISHING DETAILS
OBD OVER CEMENT PLASTER
3
KITCHEN DETAILS
CERAMIC TILES OVER GRANITE STONE WORKING COUNTER (MODULAR KITCHEN)
4
BATHROOM FITTINGS
WASH BASIN, EWC, DIVERTER MIXER AND OVER HEAD SHOWER
5
WOOD WORK ETC
N.A.
6
DOORS AND WINDOS FRAMES
HARDWOOD FRAMES
7
GLASS WORK
WINDOWS PANEL
8
ELECTRIC FITTINGS
SWITCHES AND FAN REGULATOR
9
CONDUCTING AND WIRING DETAILS
STANDARD
10
CUPBOARD DETAILS
N.A.
11
WATER STORAGE
OVER HEAD & U.G. TANKS
12
LIFT DETAILS
8 PASSENGERS & 13 PASSENGERS LIFTS
13
EXTERNAL GLAZINGS
N.A.
13.1
WINDOWS/GLAZINGS
HARDWOOD AND GLASS PANEL
14
DOORS
N.A.
14.1
MAIN DOORS
FLUSH DOORS
14.2
INTERNAL DOORS
FLUSH DOORS
15
AIR CONDITIONING
N.A.
16
ELECTRICAL FITTINGS
N.A.
17
CNG PIPE LINE
N.A.
18
PROVISION OF WIFI AND BROADBAND FACILITY
N.A.
19
EXTERNAL FINISHING/COLOUR SCHEME
EXTERIOR WHETHER COAT OVER SAND PLASTER
20
INTERNAL FINISHING
OBD OVER CEMENT PLASTER
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
VERTIFIED/CERAMIC TILES
1 . 2
WALLS
CEMENT PLASTERS WITH OBD
1 . 3
CEILING
CEMENT PLASTERS WITH OBD
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
WOODEN FLOORING
2 . 2
WALLS
CEMENT PLASTERS WITH OBD
2 . 3
CEILING
CEMENT PLASTERS WITH OBD
2 . 4
MODULAR WARDROBES
N.A.
3 . MASTER TOILET
3 . 1
FLOOR
CERAMIC TILES
3 . 2
WALLS
CERAMIC TILES UPTO LINTER LEVEL
3 . 3
CEILING
FALSE CELING
3 . 4
COUNTERS
N.A.
3 . 5
SANITARY WARE/CP FITTINGS
EWC, WASH BASIN, DIVERTER, OVERHEAD SHOWER WITH MIXER
3 . 6
FITTING/FIXTURES
N.A.
4 . BED ROOMS
4 . 1
FLOOR
CERAMIC TILES
4 . 2
WALLS
CERAMIC PLASTERS WITH OBD
4 . 3
CEILING
CEMENT PLASTERS WITH OBD
4 . 4
WARDROBES
MOF CUB BOARD
5 . TOILET
5 . 1
FLOOR
CERAMIC TILES
5 . 2
WALLS
CERAMIC TILES UPTO LINTER LEVER
5 . 3
CEILING
FALSE CELING
5 . 4
COUNTERS
N.A.
5 . 5
SANITARY WARE/CP FITTINGS
EWC, WASH BASIN, DIVERTER, OVERHEAD SHOWER WITH MIXER
5 . 6
FIXTURES
N.A.
6 . KITCHEN
6 . 1
FLOOR
CERAMIC TILES
6 . 2
WALLS
2' CERAMIC TILES OVER WORKING COUNTER
6 . 3
CEILING
OBD
6 . 4
COUNTERS
GRANITE STONE
6 . 5
FIXTURES
STEEL SINK WITH WATER MIXER
6 . 6
KITCHEN APPLIANCES
CHIMNEY
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
N.A.
7 . 2
WALLS & CEILING
N.A.
7 . 3
TOILET
N.A.
7 . 4
BALCONY
N.A.
8 . SIT-OUTS
8 . 1
FLOOR
N.A.
8 . 2
WALLS & CEILING
N.A.
8 . 3
RAILINGS
M.S. STEEL PIPE & BAR
8 . 4
FIXTURES
N.A.
Sr. No.
Document Description
Date of Document Upload
View Document
1
DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.