TIVOLI HOLIDAY VILLAGE PHASE- 2
DHARUHERA
DHARUHERA ST
REWARI
9891088406 (Number Shared by Promoter in Public)
tc@tivoliholidayvillage.com
PANKAJ CHAUHAN
9891088406 (Number Shared by Promoter in Public)
tc@tivoliholidayvillage.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
313086
24-10-2017
60249
VIJAYA BANK
HRERA Panchkula
12050 (Sqr/mtrs)
1.75
1.75
31488.54 (Sqr/mtrs)
License No. 118 of 2007 dated 14.02007 which is valid upto 13.02.2019.
Yes
3030.59 Lakhs
540.59 Lakhs
1450.00 Lakhs
495.00 Lakhs
545.00 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
2809.69
3
CONSTRUCTION OF ROADS
6507.00
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
723.00
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
1853.476
12
ANY OTHER
0
13
COMMERCIAL
156.834
Total
12050
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
Yes
WATER SUPPLY
HSVP
Yes
ELECTRICITY
DHBVNL
Yes
SEWAGE DISPOSAL
HSVP
Yes
STORM WATER DRAINAGE
HSVP
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
143.55
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
163.35
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
59.40
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
0.00
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
103.95
AS PER PROJECT REPORT
6
STREET LIGHTING
14.85
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
9.90
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
NA (date)
17-07-2008 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type BLOCK-III
9165.66
88
10
78
1
2
APARTMENT/SHOPS/OTHER BUILDINGS Type VILLAS-I
1542.84
2
2
0
0
3
APARTMENT/SHOPS/OTHER BUILDINGS Type VILLAS-II
792.93
3
1
2
0
4
APARTMENT/SHOPS/OTHER BUILDINGS Type COMMUNITY BUILDING
1853.476
1
0
1
0
5
APARTMENT/SHOPS/OTHER BUILDINGS Type SHOPPING AREA
156.834
1
0
1
0
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
VILLAS & UNITS
13
THE VILLAS AND 10 UNITS HAVE BEEN BOOKED IN THE SAID PROJECT. THE CONSTRUCTION WORKS STANDS STARTED AND WE SHALL ADHERE TO THE TIMELINE SUBMITTED TO RERA AUTHORITY.
31-12-2009
28-08-2022
28-08-2022
31-12-2009
10
28-08-2022
THE VILLAS AND 10 UNITS HAVE BEEN BOOKED IN THE SAID PROJECT. THE CONSTRUCTION WORKS STANDS STARTED AND WE SHALL ADHERE TO THE TIMELINE SUBMITTED TO RERA AUTHORITY.
THE VILLAS AND 10 UNITS HAVE BEEN BOOKED IN THE SAID PROJECT. THE CONSTRUCTION WORKS STANDS STARTED AND WE SHALL ADHERE TO THE TIMELINE SUBMITTED TO RERA AUTHORITY.
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
31-12-2009
10
28-08-2022
THE VILLAS AND 10 UNITS HAVE BEEN BOOKED IN THE SAID PROJECT. THE CONSTRUCTION WORKS STANDS STARTED AND WE SHALL ADHERE TO THE TIMELINE SUBMITTED TO RERA AUTHORITY.
0
0
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
630.75
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
68.24
68.24
Shops
0
0
Plots
0
0
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
68.24
68.24
68.24
68.24
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
68.24
68.24
68.24
68.24
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
68.24
68.57
Shops
0
0
Plots
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
21.53
Water Supply System
19.60
Sewerage treatment & garbage disposal
10.40
Electricity Supply System
0
Storm Water Drainage
5.94
Parks and Playgrounds
2.97
Clubhouse/community centres
0
Shopping area
0
Other
2.97
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
10.16
10.16
Water Supply System
11.97
11.97
Sewerage treatment & garbage disposal
7.79
7.79
Electricity Supply System
0
0
Storm Water Drainage
4.45
4.45
Parks and Playgrounds
0.58
0.58
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0.99
0.99
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
10.16
10.16
10.16
10.16
Water Supply System
11.97
11.97
11.97
11.97
Sewerage treatment & garbage disposal
7.79
7.79
7.79
7.79
Electricity Supply System
0
0.00
0
0
Storm Water Drainage
4.45
4.45
4.45
4.45
Parks and Playgrounds
0.58
0.58
0.58
0.58
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0.99
0.99
0.99
0.99
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
10.16
10.16
10.16
10.16
Water Supply System
11.97
11.97
11.97
11.97
Sewerage treatment & garbage disposal
7.79
7.79
7.79
7.79
Electricity Supply System
0
0.00
0
0
Storm Water Drainage
4.45
0.45
4.45
4.45
Parks and Playgrounds
0.58
0.58
0.58
0.58
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0.99
0.99
0.99
0.99
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
10.16
10.21
Water Supply System
11.97
12.03
Sewerage treatment & garbage disposal
7.79
7.83
Electricity Supply System
0
0
Storm Water Drainage
4.45
4.47
Parks and Playgrounds
0.58
0.58
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0.99
0.99
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
84
ii. No. of Flats/ Apartments booked
13
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
4785.00 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
2439.87 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
2345.13 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
2345.13 Lakhs
vii. Amount invested in the project upto the date of application
2260.15 Lakhs
Land cost (If any)
540.00 Lakhs
Apartments
630.75 Lakhs
Infrastructure
63.41 Lakhs
EDC/ Taxes Etc.
1026.00 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
1750.84 Lakhs
(a) In respect of existing allottees
0 Lakhs
as above
(b) In respect of rest of the project
0 Lakhs
as above
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
Nil
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
Nil
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
143.55
21.53
II. WATER SUPPLY SYSTEM
163.35
19.60
III. STORM WATER DRAINAGE
59.40
5.94
IV. ELECTRICITY SUPPLY SYSTEM
0
0
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
103.95
10.40
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
14.85
2.97
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
9.90
2.97
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
0
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
0
0
No
No
VIJAYA BANK, M-53, G.K. -2 MARKET, NEW DELHI 110048
603100301000213
VIJB0006031
110029027
6031
Sh. Sandeep Garg
Uploaded in upload Section.
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE NO. 118 OF 2007
ALREADY BEEN OBTAINED
14-02-2007
II. NOC FOR HEIGHT CLEARANCE FROM THE AIRPORT AUTHORITY OF INDIA
APPLIED FOR BUT YET TO RECEIVE
NA
Yes
Yes
The provisions as per RERA Rules notified in the State of Haryana have been added into agreements.
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
VITRIFIED TILES OF APPROVED DESIGN INTENT,
2
WALL FINISHING DETAILS
AS PER STANDARD DESIGN.
3
KITCHEN DETAILS
TILES ABOVE 2FT OF THE COUNTER, REST AS PER DESIGN.
4
BATHROOM FITTINGS
URINAL, WASHBASIN, W.C., TAPS, ABLUTION TAPS AND ALL FIXTURES OF MEDIUM RANGE TO BE FIXED AND PROVIDED BY THE CONTRACTOR. GRANITE PARTITION IN URINAL, WASH BASIN COUNTER OF GRANITE
5
WOOD WORK ETC
AS PER STANDARD DESIGN.
6
DOORS AND WINDOS FRAMES
MAIN DOOR WILL BE OF M.S. SECTION (F4, F7) INCLUDING ALL FITTING AND FIXTURE. VENTILATORS SHALL BE OF M.S. SECTION (F4, F7). ALL W.C. DOORS WILL BE OF WPC(ALSTONE )OR EQUIVALENT PVC MAKE. RAW SECTION OF DOORS AND WINDOWS WILL BE OF JINDAL/HINDALCO
7
GLASS WORK
AS PER STANDARD DESIGN.
8
ELECTRIC FITTINGS
AS PER STANDARD DESIGN.
9
CONDUCTING AND WIRING DETAILS
PVC CONDUITS AND OTHER FITTING LIKE FAN BOXES, JUNCTION BOXES, M.S. BOXES SHALL BE PROVIDED AS PER DRAWINGS. PVC CONDUITS SHALL BE OF POLY PACK OR SETIA OR EQUIVALENT MAKE.