2/3, FIRST FLOOR, WEST PATEL NAGAR, F/SIDE NEW DELHI WEST DELHI DL 110008
01143111111
9654728375 (Number Shared by Promoter in Public)
blossompark40@gmail.com
XXXX343D
U70200DL2018PTC333015
BLOSSOM PARK AT PARADISE GREENS
SECTOR -63, TEHSIL RAI & DISTRICT SONIPAT
RAI ST
SONIPAT
9896440666 (Number Shared by Promoter in Public)
blossompark40@gmail.com
MANISH GARG
9896440666 (Number Shared by Promoter in Public)
blossompark40@gmail.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
823672
27-08-2019
250000
PNB BANK DELHI
HRERA Panchkula
5.6375 (Acre)
0
0
5.6375 (Acre)
47 of 2019 dated 05.03.2019
No
Address UG FLOOR, VANDANA BUILDING, 11 TOLSTOY MARG, CONNAUGHT PLACE, NEW DELHI-110001
Annexure-B- ANNEXURE-B
TOTAL LAND ON SR. NO. 1 OF LICENSE IS 0.40 ACRES, M/S. K B. REALTORS PRIVATE LIMITED IS CO-OWNER OF 1/2 SHARE LAND MEASURING 0.20 ACRES AND COLLABORATION AGREEMENT EXECUTED WITH PUSHPRATTAN DEVELOPERS PRIVATE LIMITED OF ITS LAND 0.20 ACRES ON DATED 06.06.2018 AND OWNERSHIP OF BALANCE LAND 5.438 ACRES OF THE SAID LICENSE IS PUSHPRATTAN DEVELOPERS PRIVATE LIMITED WHO IS PROMOTER OF THE PROJECT.
Yes
AGREEMENT ATTACH
No
Yes
Yes
2097.98 Lakhs
518.80 Lakhs
0 Lakhs
279.75 Lakhs
1299.43 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
12598.93982
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
5554.11
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
1713.45
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
100
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
2286.49
12
ANY OTHER
100
13
COMMERCIAL
461.345
Total
22814.33482
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HUDA
No
WATER SUPPLY
HUDA
No
ELECTRICITY
DHBVN
No
SEWAGE DISPOSAL
HUDA
No
STORM WATER DRAINAGE
HUDA
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
59.38
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
27.11
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
21.80
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
43.84
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
33.32
AS PER PROJECT REPORT
6
STREET LIGHTING
19.72
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
0
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
10.17
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
AS PER PROJECT REPORT
10
SHOPPING AREA
0
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
5.14
AS PER PROJECT REPORT
12
SCHOOL
0
AS PER PROJECT REPORT
13
HOSPITAL/DISPENSARY
0
AS PER PROJECT REPORT
14
ANY OTHER
0
AS PER PROJECT REPORT
15
BOUNDARY WALL GATE AND GUARD ROOM
59.29
AS PER PROJECT REPORT
NA (date)
NA (date)
01-10-2019
31-12-2021
Plot Area(In Square Meter)
Number of plots in the project
130
6
126
77
100.80
21
461.345
1
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
9.90
Water Supply System
4.52
Sewerage treatment & garbage disposal
5.55
Electricity Supply System
10.59
Storm Water Drainage
3.63
Parks and Playgrounds
1.69
Clubhouse/community centres
0
Shopping area
0
Other
0
Boundary Wall Gate and Guard Room
9.88
Renewable Energy System
0.86
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
9.90
9.90
9.90
9.90
Water Supply System
4.52
4.52
4.52
4.52
Sewerage treatment & garbage disposal
5.55
5.55
5.55
5.55
Electricity Supply System
10.59
10.59
10.59
10.59
Storm Water Drainage
3.63
3.63
3.63
3.63
Parks and Playgrounds
1.69
1.69
1.69
1.69
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Boundary Wall Gate and Guard Room
9.88
9.88
9.88
9.88
Renewable Energy System
0.86
0.86
0.86
0.86
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
9.90
Water Supply System
4.52
Sewerage treatment & garbage disposal
5.55
Electricity Supply System
10.59
Storm Water Drainage
3.63
Parks and Playgrounds
1.69
Clubhouse/community centres
0
Shopping area
0
Other
0
Renewable Energy System
0.86
Boundary Wall Gate and Guard Room
9.88
No
No
PNB BANK, BHIKHAJI CAMA PLACE NEW DELHI
1988002100194085
PUNB0198800
110024115
198800
Ratan Chand Taneja R/o 7 South Patel Nagar New Delhi-110008
ATTACHED
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE
ALREADY BEEN OBTAINED
05-03-2019
II. LAYOUT PLAN
ALREADY BEEN OBTAINED
28-02-2019
Yes
Yes
FULL AGREEMENT
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT