9813713844 (Number Shared by Promoter in Public)
skrathi09@gmail.com
SUSHIL RATHI
9813713844 (Number Shared by Promoter in Public)
skrathi09@gmail.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
824125
17-09-2019
2170000
VIJAYA BANK
HRERA Panchkula
52.906 (Acre)
3.075
3.075
52.906 (Acre)
263/2007
Yes
12700 Lakhs
4000 Lakhs
5200 Lakhs
1000 Lakhs
2500 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
ANY OTHER
0
2
COMMERCIAL
2.05
3
PLOTS TO BE SOLD
24.49
4
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
5
CONSTRUCTION OF ROADS
20.9814
6
PAVEMENTS
0
7
PARKS AND PLAYGROUNDS
2.70
8
GREEN BELTS
2.20
9
VEHICLE PARKINGS
0
10
ELECTRICITY SUB-STATION
0
11
CLUB HOUSE
0
12
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0.4846
13
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
Total
52.906
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
No
WATER SUPPLY
No
ELECTRICITY
No
SEWAGE DISPOSAL
No
STORM WATER DRAINAGE
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
120000000
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
20000000
YET TO BE PREPARED
3
STORM WATER DRAINAGE
10000000
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
6000000
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
4000000
YET TO BE PREPARED
6
STREET LIGHTING
3000000
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
3000000
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
2000000
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
15000000
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
20000000
YET TO BE PREPARED
03-12-2007 (date)
03-12-2007 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Total size of the plots/carpet area of the apartments
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
PLOT Type A
585
20
11700
0
20
0
2
PLOT Type B
412.5
63
25987.5
0
63
0
3
PLOT Type C
288
63
18144
0
63
0
4
PLOT Type D
220
70
15400
0
70
0
5
PLOT Type E
180
94
16920
0
94
0
6
PLOT Type F
162
12
1944
0
12
0
7
PLOT Type G
128
33
4224
0
33
0
8
PLOT Type H
50
89
4450
0
89
0
Total
444
98769.5
0
444
0
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
0
0
N/A
N/A
N/A
01-12-2009
60
31-12-2024
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
01-12-2009
60
31-12-2024
0
0
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
500
Water Supply System
100
Sewerage treatment & garbage disposal
50
Electricity Supply System
100
Storm Water Drainage
0
Parks and Playgrounds
50
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
0
ii. No. of Flats/ Apartments booked
0
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
0 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
0 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
0 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
0 Lakhs
vii. Amount invested in the project upto the date of application
0 Lakhs
Land cost (If any)
0 Lakhs
Apartments
0 Lakhs
Infrastructure
0 Lakhs
EDC/ Taxes Etc.
0 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
0 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)