HRERA GurugramTemp Project Id : RERA-GRG-PROJ-301-2019
Submission Date : 28-11-2019 03:19:15 AM
Applicant Type : Company
Project Type: ONGOING




MONIKA INFRASTRUCTURE PRIVATE LIMITED
H-334, GROUND FLOOR, NEW RAJINDER NAGAR, NEW DELHI-60
01128744111
8743991222 (Number Shared by Promoter in Public)
monikaproperty@rediffmail.com
XXXX074F
U70101DL1997PTC088463
 
 


 
 


 
 


 
 







TAPASYA ONE
SECTOR 53 WAZIRABAD GURUGRAM
WAZIRABAD ST
GURUGRAM
01242577988
9971798255 (Number Shared by Promoter in Public)
monikaproperty@rediffmail.com
JAY SHANKAR PRASAD
01242577988
9971798255 (Number Shared by Promoter in Public)
jay.shankar@tapasyagroup.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
15755926-07-2017226100KOTAK MAHINDRA BAK LTDHRERA Gurugram
27489831-07-2017226010KOTAK MAHINDRA BANK LTD.HRERA Gurugram
39973614-02-2020339070KOTAK MAHINDRA BANK LTD.HRERA Gurugram







3.1918 (Acre)
1.75
1.749
3.1918 (Acre)
5 OF 2001(31.08.2001) AND 115 OF 2004(27.07.2004)
Yes







17700 Lakhs
106.10 Lakhs
12743.53 Lakhs
256.47 Lakhs
4593.90 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS5163.535
3CONSTRUCTION OF ROADS2718.00
4PAVEMENTS1030.135
5PARKS AND PLAYGROUNDS2311.82
6GREEN BELTS943.17
7VEHICLE PARKINGS750.00
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total12916.66




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHUDAYes
WATER SUPPLYHUDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHPCB/HUDAYes
STORM WATER DRAINAGEPUBLIC HEALTHYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS44.85SUBMITTED TO HUDA
2WATER SUPPLY SYSTEM89.64SUBMITTED TO HUDA
3STORM WATER DRAINAGE19.28SUBMITTED TO HUDA
4ELECTRICITY SUPPLY SYSTEM0YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL21.90SUBMITTED TO HUDA
6STREET LIGHTING5.88SUBMITTED TO HUDA
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS0YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15HORTICULTURE2.07SUBMITTED TO HUDA
16MTC OF SERVICES AND RESURFACING OF ROADS72.85SUBMITTED TO HUDA


16-08-2016 (date)
16-08-2016 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER A1335176201
2APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER B51896001






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
TOWER A20
TOWER B00


10-04-2008
30-06-2023
30-06-2023
14-04-2018
80
30-06-2023
FURTHER DETAILS IS PROVIDED IN REP-1 PART-C-X
TOWER - B COMPLETED. APPROX 80 % OF CIVIL WORK HAS BEEN COMPLETED AND REMAINING 20% OF CIVIL WORK TO BE COMPLETED AFTER THE MECHANICAL, ELECTRICAL, PLUMBING (MEP) SERVICES, FIRE FIGHTING SYSTEM AND INFRASTRUCTURE LIKE GENERATOR, LIFTS, ESCALATORS ARE INSTALLED IN TOWER - A. PARTIALLY OC OF TOWER B AND TOWER A RECEIVED.


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT0NOT APPLICABLE
10-04-2008
0
30-06-2023
NOT APPLICABLE
NOT APPLICABLE


0
0
724
60
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0
Construction Cost6653.61
EDC IDC321.87
Infrastructure Cost133.90
Land Cost106.10
Others Cost including taxes levies etc3063.95

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0
Shops0
Plots0
Others Cost including taxes levies etc48.32
Construction Cost243.60

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000
Construction Cost334.9560.9091.35213.15
Others Cost including taxes levies etc66.4412.0818.1242.28

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000
Others Cost including taxes levies etc181.2166.4460.40120.81
Construction Cost913.49334.95304.50608.99

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000
Construction Cost304.50913.49913.49548.09
Others Cost including taxes levies etc60.40181.21181.21108.73

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0
Shops0
Plots0
Others Cost including taxes levies etc60.40
Construction Cost304.50




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements23.42
Water Supply System46.80
Sewerage treatment & garbage disposal11.43
Electricity Supply System0
Storm Water Drainage10.07
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Horticulture and Road side Plantation1.08
MTC of Services and Resurfacing of Roads38.03
Street Lighting3.07

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0.32
Water Supply System0.64
Sewerage treatment & garbage disposal0.16
Electricity Supply System0
Storm Water Drainage0.14
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Street Lighting0.05
MTC of Services and Resurfacing of Roads0.52
Horticulture and Road side Plantation0.01

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0.960.210.320.86
Water Supply System1.930.430.641.71
Sewerage treatment & garbage disposal0.470.100.160.42
Electricity Supply System0000
Storm Water Drainage0.410.090.140.37
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Horticulture and Road side Plantation0.040.010.010.04
MTC of Services and Resurfacing of Roads1.570.350.521.39
Street Lighting0.130.050.050.11

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements2.571.181.073.21
Water Supply System5.142.362.146.43
Sewerage treatment & garbage disposal1.260.580.521.57
Electricity Supply System0000
Storm Water Drainage1.110.510.461.38
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Street Lighting0.340.150.150.42
MTC of Services and Resurfacing of Roads4.181.911.745.22
Horticulture and Road side Plantation0.120.050.050.15

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.073.213.212.14
Water Supply System2.146.436.434.28
Sewerage treatment & garbage disposal0.521.571.571.05
Electricity Supply System0000
Storm Water Drainage0.461.381.380.92
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
MTC of Services and Resurfacing of Roads1.745.225.223.48
Horticulture and Road side Plantation0.050.150.150.10
Street Lighting0.150.420.420.28

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.07
Water Supply System2.14
Sewerage treatment & garbage disposal0.52
Electricity Supply System0
Storm Water Drainage0.46
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Horticulture and Road side Plantation0.05
Street Lighting0.15
MTC of Services and Resurfacing of Roads1.74












Particulars Remarks, if any
i. No. of Flats/Apartments constructed82As on 31.12.2019
ii. No. of Flats/ Apartments booked2As on 31.12.2019
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter2900 LakhsAs on 31.12.2019
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter2650 LakhsAs on 31.12.2019
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter250 LakhsAs on 31.12.2019
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter250 LakhsAs on 31.12.2019
vii. Amount invested in the project upto the date of application10279.43 LakhsAs on 31.12.2019
Land cost (If any)106.10 LakhsAs on 31.12.2019
Apartments6653.61 LakhsAs on 31.12.2019
Infrastructure133.90 LakhsAs on 31.12.2019
EDC/ Taxes Etc.3385.82 LakhsAs on 31.12.2019
viii. Balance cost to be incurred for completion of the project and delivery of possession7420.57 LakhsAs on 31.12.2019
(a) In respect of existing allottees250 LakhsAs on 31.12.2019
(b) In respect of rest of the project7670.57 LakhsAs on 31.12.2019
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
3835.00 LakhsAs on 31.12.2019
x. Total liabilities against the project up-to-date. (Annex details in folder C) 2682.67 LakhsAs on 31.12.2019



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS44.8523.42
II. WATER SUPPLY SYSTEM89.6446.80
III. STORM WATER DRAINAGE19.2810.07
IV. ELECTRICITY SUPPLY SYSTEM00
V. SEWAGE TREATMENT & GARBAGE DISPOSAL21.9011.43
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER80.842.18
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.00
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM00
XVII. OTHER FACILITIES AS PER PROJECT REPORT00









Yes
Yes
KOTAK MAHINDRA BANK, 79, OLD RAJINDER NAGAR MARKET, NEW DELHI-60
01792560000013
KKBK0000179
110485010
000179
Som Arora, Address: 50-51, Shivaji Marg, Westend Green Farm Society, Rajokari, New Delhi-110038
UPLOADED











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. APPROVED ZOING PLAN ALREADY BEEN OBTAINED26-04-2006
II. ENVIRONMENT CLEARANCE ALREADY BEEN OBTAINED20-08-2018
III. CERTIFICATE OF REGISTRATION ISSUED BY THE LABOUR COMMISSIONER HARYANA & REGISTERING OFFICER, LABOUR DEPARTMENT HARYANA ALREADY BEEN OBTAINED01-01-2016
IV. BOCW REGISTRATION ISSUED BY THE ASSISTANT DIRECTOR (IS& H) GURUGRAM -II, REGISTRATION OFFICER CUM ASSESSING AUTHORITY , GOVERNMENT OF HARYANA ALREADY BEEN OBTAINED18-01-2018
V. NOC FROM POLLUTION BOARD ALREADY BEEN OBTAINED29-08-2017
VI. NOC FROM FOREST DEPT. ALREADY BEEN OBTAINED28-10-2015
VII. ARAVALI NOTIFICATION ALREADY BEEN OBTAINED24-11-2015
VIII. ASSURANCE LETTER FOR ELECTRICITY DEPARTMENT ALREADY BEEN OBTAINED13-02-2017
IX. NOC FROM HUDA FOR CONSTRUCTION ALREADY BEEN OBTAINED06-10-2010
X. NOC FROM AIRPORTS AUTHORITY ALREADY BEEN OBTAINED30-01-2019








Yes


Yes


Possession Date: June, 2023













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEGF CENTRAL PLAZA - PAVERS/ TILES, COMMON TOILETS - VITRIFIED / CERAMIC TILES, CORRIDORS / PASSAGE - VITRIFIED / CERAMIC TILES, RETAIL SHOPS - BARE SHELL, COMMON STAIRCASE - KOTA STONE.
2WALL FINISHING DETAILSPLASTERED WALLS IN SHOP
3KITCHEN DETAILSKOTA IN FLOORING AND SINK
4BATHROOM FITTINGSSINGLE LEVER C.P. FITTINGS, EWC, HEALTH FAUCET, WASH BASIN.
5WOOD WORK ETCN/A
6DOORS AND WINDOS FRAMESN/A
7GLASS WORKN/A
8ELECTRIC FITTINGSBRANDED MODULAR SWITCHES AND SOCKETS.
9CONDUCTING AND WIRING DETAILSCOPPER WIRING
10CUPBOARD DETAILSN/A
11WATER STORAGEWATER TANK UNDERGROUND + OVERHEAD ( 6.5 KLD)
12LIFT DETAILS3 LIFTS IN TOWER B OPERATIONAL. MAKE MITSUBISHI, SPEED 1.5 M/SEC.
13EXTERNAL GLAZINGSDGU IN THE EXTERNAL FACADE IN TOWER B
13.1WINDOWS/GLAZINGSUPVC/ALUMINIUM SLIDING SWING GLASS SHUTTER
14DOORSN/A
14.1MAIN DOORSN/A
14.2INTERNAL DOORSN/A
15AIR CONDITIONINGVRV SYSTEM IN TOWER B. TOWER A YET TO BE PLANNED.
16ELECTRICAL FITTINGSBRANDED MODULAR SWITCHES AND SOCKETS. COPPER WIRING
17CNG PIPE LINEPNG BEING PROVIDED IN TOWER B
18PROVISION OF WIFI AND BROADBAND FACILITYN/A
19EXTERNAL FINISHING/COLOUR SCHEMEEXTERNAL FACADE IS OF DRU IN TOWER B
20INTERNAL FINISHINGPLASTER WITH PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORN/A
1 . 2 WALLSN/A
1 . 3 CEILINGN/A
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORN/A
2 . 2 WALLSN/A
2 . 3 CEILINGN/A
2 . 4 MODULAR WARDROBESN/A
3 . MASTER TOILET
3 . 1 FLOORN/A
3 . 2 WALLSN/A
3 . 3 CEILINGN/A
3 . 4 COUNTERSN/A
3 . 5 SANITARY WARE/CP FITTINGSN/A
3 . 6 FITTING/FIXTURESN/A
4 . BED ROOMS
4 . 1 FLOORN/A
4 . 2 WALLSN/A
4 . 3 CEILINGN/A
4 . 4 WARDROBESN/A
5 . TOILET
5 . 1 FLOORN/A
5 . 2 WALLSN/A
5 . 3 CEILINGN/A
5 . 4 COUNTERSN/A
5 . 5 SANITARY WARE/CP FITTINGSN/A
5 . 6 FIXTURESN/A
6 . KITCHEN
6 . 1 FLOORN/A
6 . 2 WALLSN/A
6 . 3 CEILINGN/A
6 . 4 COUNTERSN/A
6 . 5 FIXTURESN/A
6 . 6 KITCHEN APPLIANCESN/A
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORN/A
7 . 2 WALLS & CEILINGN/A
7 . 3 TOILETN/A
7 . 4 BALCONYN/A
8 . SIT-OUTS
8 . 1 FLOORANTI-SKID CERAMIC TILES/ VITRIFIED
8 . 2 WALLS & CEILINGN/A
8 . 3 RAILINGSN/A
8 . 4 FIXTURESN/A












Sr. No.Document DescriptionDate of Document UploadView Document
1DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD22-11-2019 View Document
2NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT22-11-2019 View Document
3BR-III APPROVAL OF REVISED BUILDING PLAN.22-11-2019 ------
4ENVIRONMENT CLEARANCE22-11-2019 ------
5OC BUILDING PLAN22-11-2019 ------
6COPY OF LICENSE ALONG WITH SCHEDULE OF LAND22-11-2019 View Document
7WATER ASSURANCE LETTER22-11-2019 ------
8BALANCE SHEET FY 2016-1722-11-2019 ------
9DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.22-11-2019 View Document
10NOC FROM AIRPORT AUTHORITY22-11-2019 ------
11ROADS PLANS22-11-2019 ------
12CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT22-11-2019 View Document
13ESTIMATED COST OF THE PROJECT22-11-2019 ------
14NOC FROM FOREST DEPT22-11-2019 ------
15SEWERAGE SCHEME22-11-2019 ------
16A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS TOWER B22-11-2019 ------
17DEMARCATION PLAN22-11-2019 View Document
18RERA CERTIFICATE 22-11-2019 ------
19A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS22-11-2019 View Document
20APPROVAL LETTER OC22-11-2019 ------
21APPROVAL LETER SLD22-11-2019 ------
22STORM WATER DRAINAGE SCHEME22-11-2019 ------
23BALANCE SHEET FY 2015-1622-11-2019 ------
24CERTIFICATE OF REGISTRATION ISSUED BY THE LABOUR COMMISSIONER HARYANA & REGISTERING OFFICER, LABOUR DEPARTMENT22-11-2019 ------
25DRAFT ALLOTMENT LETTER22-11-2019 ------
26BOCW REGISTRATION ISSUED BY THE ASSISTANT DIRECTOR (IS& H) GURUGRAM -II, REGISTRATION OFFICER CUM ASSESSING AUTHORITY , GOVERNMENT OF HARYANA22-11-2019 ------
27BALANCE SHEET FY 2017-1822-11-2019 ------
28ZONING PLAN22-11-2019 View Document
29IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN22-11-2019 View Document
30FIRE FIGHTING SCHEME22-11-2019 ------
31IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN22-11-2019 View Document
32APPROVAL DRAWING SLD22-11-2019 ------
33NOC FROM HUDA FOR CONSTRUCTION22-11-2019 ------
34ARAVALI NOTIFICATION22-11-2019 ------
35DRAFT AGREEMENT22-11-2019 ------
36ELECTRICAL LOAD SANCTION 1500KW22-11-2019 ------
37NOC FROM POLLUTION BOARD22-11-2019 ------
38WATER SUPPLY SCHEME22-11-2019 ------
39CASH FLOW STATEMENT OF THE PROPOSED PROJECT28-11-2019 View Document
40MIPL BS FY 2018-1928-11-2019 ------
41SITE PLAN28-11-2019 ------
42SERVICE ESTIMATE07-02-2020 ------
43SERVICE PLAN APPROVAL LETTER07-02-2020 ------
44LOI07-02-2020 ------
45BR-III07-02-2020 ------
46DEMARCATION PLAN AND LETTER07-02-2020 ------
47REP-II07-02-2020 ------
48ENVIRONMENT CLEARANCE07-02-2020 ------
49FIRE SCHEME APPROVAL07-02-2020 ------
50FOREST NOC07-02-2020 ------
51LC-IV07-02-2020 ------
52ARAVALI NOTIFICATION07-02-2020 ------
53COMPANY NAME CHANGE CERTIFICATE07-02-2020 ------
54NON ENCUMBRANCE CERTIFICATE07-02-2020 ------
55LAND TITTLE DOCUMEMTS07-02-2020 ------