BPTP NEST 85 A
VILLAGE-BUDENA, SECTOR-85, FARIDABAD
FARIDABAD
FARIDABAD
01149572787
8800414400 (Number Shared by Promoter in Public)
rera.panchkula@bptp.com
VINOD KUMAR
01149572787
8800414400 (Number Shared by Promoter in Public)
rera.panchkula@bptp.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
941622
08-08-2019
216588
RBL BANK
HRERA Panchkula
5.3520 (Acre)
1
1
5.5750 (Acre)
80 of 2019
Yes
2436.47 Lakhs
859.00 Lakhs
0 Lakhs
877.00 Lakhs
700.47 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
2.863
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
0.877
4
PAVEMENTS
0.542
5
PARKS AND PLAYGROUNDS
0.418
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0.019
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0.044
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.558
12
ANY OTHER
0.032
Total
5.353
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
HSVP
No
ELECTRICITY
DHBVN
No
SEWAGE DISPOSAL
HSVP
No
STORM WATER DRAINAGE
HSVP
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
152
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
143
YET TO BE PREPARED
3
STORM WATER DRAINAGE
47
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
164
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
131
YET TO BE PREPARED
6
STREET LIGHTING
15
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
2
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
88
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
9
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
126
YET TO BE PREPARED
30-07-2019 (date)
NA (date)
01-08-2019
29-07-2024
Plot Area(In Square Meter)
Number of plots in the project
91.00
50
78.09
1
80.26
1
82.43
1
84.60
1
86.77
1
88.94
1
91.11
1
93.28
1
95.45
1
97.65
1
99.86
1
102.03
1
104.20
1
127.89
1
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
5
9
6
Water Supply System
4
10
9
Sewerage treatment & garbage disposal
14
12
11
Electricity Supply System
3
6
5
Storm Water Drainage
2
2
1
Parks and Playgrounds
4
4
3
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
8
5
4
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
5
6
3
4
Water Supply System
8
5
6
9
Sewerage treatment & garbage disposal
4
5
6
4
Electricity Supply System
5
2
3
5
Storm Water Drainage
2
2
1
2
Parks and Playgrounds
5
3
4
2
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
7
10
8
9
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
2
9
7
4
Water Supply System
6
6
8
5
Sewerage treatment & garbage disposal
6
3
2
5
Electricity Supply System
8
3
4
6
Storm Water Drainage
2
3
2
3
Parks and Playgrounds
7
3
5
3
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
8
9
8
5
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
5
3
6
8
Water Supply System
4
3
4
2
Sewerage treatment & garbage disposal
5
3
2
6
Electricity Supply System
7
4
8
6
Storm Water Drainage
2
1
1
1
Parks and Playgrounds
1
2
1
5
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
3
2
3
4
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
7
8
7
3
Water Supply System
5
5
6
3
Sewerage treatment & garbage disposal
4
2
3
2
Electricity Supply System
11
17
12
10
Storm Water Drainage
1
2
2
2
Parks and Playgrounds
2
5
4
3
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
2
2
4
3
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
8
6
Water Supply System
4
3
Sewerage treatment & garbage disposal
12
4
Electricity Supply System
2
6
Storm Water Drainage
3
2
Parks and Playgrounds
0
2
Clubhouse/community centres
0
0
Shopping area
0
0
Other
2
3
Yes
Yes
RBL BANK GROUND FLOOR, M-6, HAUZ KHAS, NEW DELHI - 110016
400011110048
RATN0000141
110176006
000141
Rakesh Aggarwal, Inderbir
Singh Bhatia, Manik Malik and
Sanjeev Aggarwal- Either of
two jointly.
Address: ECE house, Connaught Place, New Delhi-110001
As Annexed
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE NO 80 OF 2019
ALREADY BEEN OBTAINED
30-07-2019
II. APPROVED LAYOUT
ALREADY BEEN OBTAINED
30-07-2019
Yes
Yes
As per the provided format.
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following: