HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-649-2019
Submission Date : 24-07-2019 11:25:11 AM
Applicant Type : Company
Project Type: ONGOING




M/S BPTP LTD.
M-11, MIDDLE CIRCUS, CONNAUGHT CIRCUS, NEW DELHI 110001
01149572787
9871883334 (Number Shared by Promoter in Public)
rera.panchkula@bptp.com
http://bptp.com
XXXX442A
U45201DL2003PLC121733
 
 


 
 


 
 







PARK ELITE PREMIUM
SECTOR 84, FARIDABAD
FARIDABAD
FARIDABAD
9711205530
9711205530 (Number Shared by Promoter in Public)
rera.panchkula@bptp.com
PANKAJ BAGGA
9711205530
9711205530 (Number Shared by Promoter in Public)
rera.panchkula@bptp.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
174826528-07-2017369859RBL BANKHRERA Panchkula
258443505-06-2018253102PUNJAB NATIONAL BANKHRERA Panchkula







5.03 (Acre)
1.75
0.51
11.094 (Acre)
62 of 2010 dated 14-08-2010
No
Address     M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address     M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address     M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address     M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address     M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address     M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address     M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address     M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Annexure-B- AS A PROMOTER. (AS PER THE MASTER DEVELOPMENT AGREEMENT DATED AUGUST 03, 2007 WITH THE LICENSE HOLDERS).
APPLICANT IS APPLYING ON THE BASIS OF MASTER DEVELOPMENT AGREEMENT WHICH WAS ENTERED ON AUGUST 03,2007.
No
AS PER POINT (C) OF PARTY RELATED RECITALS OF THE MASTER DEVELOPMENT AGREEMENT THE LAND OWNERS HAVE ENTERED A COLLABORATION AGREEMENTS WITH THE COUNTRYWIDE PROMOTERS PRIVATE LIMITED (HEREIN REFERRED AS COUNTRYWIDE) AND COUNTRYWIDE IN TURN HAD ALSO ENTERED COLLABORATION AGREEMENT WITH BPTP LIMITED (HEREIN REFERRED AS BPTP) WHICH GIVES EXCLUSIVE RIGHT OF THE DEVELOPMENT TO THE BPTP; ATTACHED HEREWITH FOR YOUR KIND PERUSAL.
No
No
Yes







10768.53 Lakhs
371.03 Lakhs
7036.71 Lakhs
438.31 Lakhs
2922.48 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS35597.80
3CONSTRUCTION OF ROADS0
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total35597.8




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYHSVPNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS66.33SUBMITTED TO HUDA
2WATER SUPPLY SYSTEM32.25SUBMITTED TO HUDA
3STORM WATER DRAINAGE41.23SUBMITTED TO HUDA
4ELECTRICITY SUPPLY SYSTEM165.8SUBMITTED TO HUDA
5SEWAGE TREATMENT & GARBAGE DISPOSAL29SUBMITTED TO HUDA
6STREET LIGHTING0SUBMITTED TO HUDA
7SECURITY AND FIRE FIGHTING13.7SUBMITTED TO HUDA
8PLAYGROUNDS AND PARKS0SUBMITTED TO HUDA
9CLUB HOUSE/COMMUNITY CENTRE90SUBMITTED TO HUDA
10SHOPPING AREA0SUBMITTED TO HUDA
11RENEWABLE ENERGY SYSTEM0SUBMITTED TO HUDA
12SCHOOL0SUBMITTED TO HUDA
13HOSPITAL/DISPENSARY0SUBMITTED TO HUDA
14ANY OTHER0SUBMITTED TO HUDA


06-05-2011 (date)
06-05-2011 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type APARTMENTS70376351347
2APARTMENT/SHOPS/OTHER BUILDINGS Type VILLAS199.839811
3APARTMENT/SHOPS/OTHER BUILDINGS Type EWS16.18646401






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
APARTMENTS351AS ANNEXED.
VILLAS8AS ANNEXED.
EWS64AS ANNEXED.


01-01-2012
30-11-2014
31-12-2012
01-01-2012
55
31-12-2022
AS MENTIONED
APARTMENTS/VILLAS/ EWS: AS WE HAVE SPENT 6219.34 LAKHS OUT OF THE ESTIMATED BUDGET OF 7036.71 SO THE PERCENTAGE COMPLETION OF THE CONSTRUCTION IS 88%. INFRASTRUCTURE: WE HAVE SPENT 241.12 LAKHS OUT OF 438.31 LAKHS SO THE COMPLETION PERCENTAGE IS 55%


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT0NA
01-01-2012
55
31-12-2022
NA
NA


0
0
434
144
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments6219.34
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments70506062
Shops0000
Plots0000

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments60655555
Shops0000
Plots0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments52555845
Shops0000
Plots0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments404050
Shops000
Plots000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements43.43
Water Supply System25
Sewerage treatment & garbage disposal19
Electricity Supply System110
Storm Water Drainage29
Parks and Playgrounds0
Clubhouse/community centres9
Shopping area0
Other5.7

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.751.61.61.7
Water Supply System0.250.20.250.35
Sewerage treatment & garbage disposal1.250.550.751.15
Electricity Supply System3.5452.5
Storm Water Drainage0.750.810.950.9
Parks and Playgrounds0000
Clubhouse/community centres76.58.57.5
Shopping area0000
Other0.250.50.550.25

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.351.351.251.8
Water Supply System0.750.50.750.4
Sewerage treatment & garbage disposal3.750.650.30.35
Electricity Supply System0.653.62.752.25
Storm Water Drainage0.850.80.90.75
Parks and Playgrounds0000
Clubhouse/community centres6.58.54.55.5
Shopping area0000
Other0.450.550.450.35

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.851.451.91.9
Water Supply System0.950.550.650.75
Sewerage treatment & garbage disposal0.650.750.350.45
Electricity Supply System53.653.853.95
Storm Water Drainage0.550.650.750.85
Parks and Playgrounds0000
Clubhouse/community centres27.53.52.5
Shopping area0000
Other0.350.550.950.65












Particulars Remarks, if any
i. No. of Flats/Apartments constructed449
ii. No. of Flats/ Apartments booked423
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter10203.34 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter9271.88 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter931.46 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter931.46 Lakhs
vii. Amount invested in the project upto the date of application9753.98 Lakhs
Land cost (If any)371.03 Lakhs
Apartments6219.34 Lakhs
Infrastructure241.13 Lakhs
EDC/ Taxes Etc.2922.48 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession1014.54 Lakhs
(a) In respect of existing allottees0 Lakhs
(b) In respect of rest of the project0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
3500.00 LakhsThe Loan is against the whole township.
x. Total liabilities against the project up-to-date. (Annex details in folder C) 2653.43 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS66.3343.43
II. WATER SUPPLY SYSTEM32.2525
III. STORM WATER DRAINAGE41.2329
IV. ELECTRICITY SUPPLY SYSTEM165.8110
V. SEWAGE TREATMENT & GARBAGE DISPOSAL2919
VI. CLUB HOUSE/COMMUNITY CENTRE909
VII. SCHOOL00
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.00
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM13.75.7
XVII. OTHER FACILITIES AS PER PROJECT REPORT00









Yes
Yes
INDUSIND BANK, GOPALDAS BHAWAN, 28, BARAKHAMBA ROAD, NEW DELHI-110001
201002429183
INDB0000005
110234002
000005
Rakesh Kumar Aggarwal and Inderbir Singh Bhatia. Add: ECE House , Connaught Place, New Delhi-110001
As Annexed.











No
No
Yes
Yes
Yes
No
No
No
Yes
Yes


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE 62 OF 2010ALREADY BEEN OBTAINED14-08-2010
II. BUILDING PLANALREADY BEEN OBTAINED06-05-2011
III. ZONNING PLANALREADY BEEN OBTAINED06-12-2010
IV. SITE PLANALREADY BEEN OBTAINED06-05-2011
V. ENVIRONMENTAL CLEARANCEALREADY BEEN OBTAINED31-12-2012
VI. APPROVAL FROM DHBVNALREADY BEEN OBTAINED10-10-2011








Yes


Yes


As per the provided draft.







PARK TERRA, SEC 37D GURUGRAM
840305
456
0
373
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
35269.38020987.44
Cost of the apartments000
Cost of the infrastructure000
Others costs000


30900 Lakhs
9500 Lakhs
6500 Lakhs
4500 Lakhs
Yes
31-12-2012
31-10-2020




PARK SENTOSA, SECTOR 77 FARIDABAD
743720
420
0
159
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
22701.6505630.20
Cost of the apartments000
Cost of the infrastructure000
Others costs000


3600 Lakhs
10100 Lakhs
0 Lakhs
0 Lakhs
Yes
30-04-2013
31-07-2022




VISSIONAIRE VILLAS, SECTOR 70 GURUGRAM
56233
10
10
5
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
932.830493.28
Cost of the apartments000
Cost of the infrastructure000
Others costs000


1300 Lakhs
1000 Lakhs
0 Lakhs
0 Lakhs
Yes
30-04-2015
31-07-2020




PEDESTAL FLOORS SECTOR 70A GURUGRAM
303304
174
58
143
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
5550.8702718.42
Cost of the apartments000
Cost of the infrastructure000
Others costs000


10200 Lakhs
8000 Lakhs
0 Lakhs
0 Lakhs
Yes
30-04-2015
31-07-2020










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSE- CERAMIC TILES IN TOILETS # EWS - SELECT IMPORTED MARBLE FOR STAIRS AND UPPER LOBBY AREA # APARTMENTS
2WALL FINISHING DETAILSPLASTER WITH WHITE WASH # EWS - PAINTED IN PLEASING SHADES OF ACRYLIC EMULSION PAINT WITH VELVET FINISH # APARTMENTS
3KITCHEN DETAILSKITCHEN COUNTER – IPS, KITCHEN SINK – BOWL ONLY # EWS - DADO- GRANITE ABOVE THE WORKING PLATFORM AND REST PAINTED IN ACRYLIC EMULSION PAINT. COUNTER- WORKING PLATFORM/COUNTER EQUIPPED WITH DOUBLE BOWL/STAINLESS STEEL SINK AND DRAIN BOARD, CHIMNEY HOB AND DISH WASHER # APARTMENTS
4BATHROOM FITTINGSGI PIPING AND CPVC AND UPVC, ENGLISH WC, SIMPLE TAPS # EWS - IMPORTED MARBLE/GRANITE. GRANITE MARBLE COUNTER, WHITE SANITARY FEATURES, CONTEMPORARY CHROME PLATTED FITTINGS. STEAM & SHOWER IN THE MASTER BATHROOM # APARTMENTS
5WOOD WORK ETCFLUSH DOOR WITH MS FRAME # EWS - N.A. # APARTMENTS
6DOORS AND WINDOS FRAMESGLASS WINDOW WITH MS FRAME # EWS - MAIN DOOR: SEASONED HARDWOOD FRAMES WITH DESIGNER SHUTTER AND HIGH & LARGE. SEASONED HARDWOOD FRAMES WITH PAINTED SKIN DOOR SHUTTER (TALL). INTERNAL: (DOORS WITH TEAK FRAMES) UPVC FRAMES AND GLAZING, FLOOR TO CEILING DOOR WINDOWS GLASS IN DOUBLE HEIGHT # APARTMENTS
7GLASS WORKROOMS, KITCHEN AND TOILET # EWS - AS PER ABOVE # APARTMENTS
8ELECTRIC FITTINGSCU WIRING AND ORDINARY SWITCHES WITH BAKELITE SHEET # EWS - CU WIRING # APARTMENTS
9CONDUCTING AND WIRING DETAILSAS ABOVE # EWS - AS ABOVE # APARTMENTS
10CUPBOARD DETAILSAS ABOVE # EWS - AS ABOVE # APARTMENTS
11WATER STORAGERCC TANK # EWS - RCC TANKS # APARTMENTS
12LIFT DETAILSNOT APPLICABLE # EWS -- # APARTMENTS
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSGLASS WINDOW WITH MS FRAME # EWS - RAILING- GLASS
14DOORSAS PER 14.1 AND 14.2
14.1MAIN DOORS- L. DROP # EWS - SEASONED HARDWOOD FRAMES WITH DESIGNER SHUTTER AND HIGH & LARGE # APARTMENT
14.2INTERNAL DOORS- TOWER BOLT # EWS - SEASONED HARDWOOD FRAMES WITH PAINTED SKIN DOOR SHUTTER (TALL) # APARTMENT
15AIR CONDITIONING- NOT PROVIDED # EWS - NOT PROVIDED # APARTMENTS
16ELECTRICAL FITTINGSCU WIRING # EWS - CU WIRING # APARTMENTS
17CNG PIPE LINENOT PROVIDED # EWS - NOT PROVIDED # APARTMENTS
18PROVISION OF WIFI AND BROADBAND FACILITYNOT PROVIDED # EWS - NOT PROVIDED # APARTMENTS
19EXTERNAL FINISHING/COLOUR SCHEMEPLASTER WITH WHITE WASH # EWS - PLASTER WITH WHITE WASH # APARTMENTS
20INTERNAL FINISHINGFLOORING-IPS # EWS - FLOORING-IPS # APARTMENTS
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOOR- IPS & CERAMIC TILES # EWS - VITRIFIED TILES # APARTMENTS
1 . 2 WALLS- PLASTER WITH WHICH WASH # EWS - PAINTED IN PLEASING SHADES OF OIL BOUND DISTEMPER # APARTMENTS
1 . 3 CEILINGPLASTER WITH WHICH WASH # EWS - PLASTER WITH WHITE WASH # APARTMENTS
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORIPS # EWS - LAMINATED WOODEN FLOORING # APARTMENTS
2 . 2 WALLSPLASTER WITH WHICH WASH # EWS - PAINTED IN PLEASING SHADES OF OILD BOUND DISTEMPER # APARTMENTS
2 . 3 CEILINGPLASTER WITH WHICH WASH # EWS - PLASTER WITH WHITE WASH OF GOOD QUALITY # APARTMENTS
2 . 4 MODULAR WARDROBESNOT PROVIDED # EWS -- # APARTMENTS
3 . MASTER TOILET
3 . 1 FLOORCEREMIC TILES # EWS - CERAMIC TILES DADO – SELECTED CERAMIC TILES UPTO 7FT. # APARTMENTS
3 . 2 WALLSPLASTER WITH WHICH WASH # EWS - PAINTED IN PLEASING SHADES OF ACRYLIC EMULSION PAINT # APARTMENTS
3 . 3 CEILINGPLASTER WITH WHICH WASH # EWS - PLASTER WITH WHITE WASH # APARTMENTS
3 . 4 COUNTERS- IPS # EWS - IPS # APARTMENTS
3 . 5 SANITARY WARE/CP FITTINGSENGLISH WC # EWS - ENGLISH WC # APARTMENTS
3 . 6 FITTING/FIXTURESGI, CPVC, UPVC PIPING, TAP # EWS - GI, CPVC, UPVC PIPING # APARTMENTS
4 . BED ROOMS
4 . 1 FLOORCERAMIC TILES # EWS - LAMINATED WOODEN FLOORING # APARTMENTS
4 . 2 WALLSPLASTER WITH WHITE WASH # EWS - PAINTED IN PLEASING SHADES OF OIL BOUND DISTEMPER # APARTMENTS
4 . 3 CEILINGPLASTER WITH WHITE WASH # EWS - PLASTER WITH WHITE WASH # APARTMENTS
4 . 4 WARDROBESNOT PROVIDED # EWS - NOT PROVIDED # APARTMENTS # APARTMENTS
5 . TOILET
5 . 1 FLOORCERAMIC TILES # EWS - CERAMIC TILES # APARTMENTS
5 . 2 WALLS- PLASTER WITH WHITE WASH # EWS - PAINTED IN PLEASING SHADES OF ACRYLIC EMULSION PAINT # APARTMENTS
5 . 3 CEILINGPLASTER WITH WHITE WASH # EWS - PLASTER WITH WHITE WASH # APARTMENTS
5 . 4 COUNTERSNOT PROVIDED # EWS - IPS # APARTMENTS
5 . 5 SANITARY WARE/CP FITTINGSGI, CPVC, UPVC PIPING # EWS - GI, CPVC, UPVC PIPING # APARTMENTS
5 . 6 FIXTURES# EWS -- # APARTMENTS
6 . KITCHEN
6 . 1 FLOORCERAMIC TILES # EWS - CERAMIC TILES DADO- CERAMIC TILES TWO FEET ABOVE, THE WORKING PLATFORM # APARTMENTS
6 . 2 WALLS- PLASTER WITH WHITE WASH # EWS - OIL BOUND DISTEMPER # APARTMENTS
6 . 3 CEILING- PLASTER WITH WHITE WASH # EWS - DISTEMPER # APARTMENTS
6 . 4 COUNTERSIPS # EWS - PLATFORM: GRANITE COUNTER WITH SINGLE BOWL STAINLESS STEEL AND DRAIN BOARD # APARTMENTS
6 . 5 FIXTURES- BOWL ONLY # EWS - STAINLESS STEEL SINK AND DRAIN BOARD # APARTMENTS
6 . 6 KITCHEN APPLIANCESNOT PROVIDED # EWS -- # APARTMENTS
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORN.A. # EWS - CERAMIC TILES # APARTMENTS
7 . 2 WALLS & CEILINGN.A. # EWS - PAINTED WITH DISTEMPER # APARTMENTS
7 . 3 TOILETN.A. # EWS - N.A. # APARTMENTS
7 . 4 BALCONYN.A. # EWS - N.A. # APARTMENTS
8 . SIT-OUTS
8 . 1 FLOOR- N.A. # EWS - N.A. # APARTMENTS
8 . 2 WALLS & CEILING- N.A. # EWS - N.A. # APARTMENTS
8 . 3 RAILINGS- N.A. # EWS - N.A. # APARTMENTS
8 . 4 FIXTURES- N.A. # EWS - N.A. # APARTMENTS












Sr. No.Document DescriptionDate of Document UploadView Document
1OC OBTAINED23-07-2019 ------
2ZONING PLAN22-07-2019 View Document
3IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN22-07-2019 View Document
4COPY OF LICENSE ALONG WITH SCHEDULE OF LAND22-07-2019 View Document
5NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT22-07-2019 View Document
6DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.22-07-2019 View Document
7IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN22-07-2019 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 Occupation Certificate Uploaded 27-02-2024 View Document
2 OCCUPATION CERTIFICATE UPLOADE 27-02-2024 View Document