HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-58-2018
Submission Date : 30-10-2018 06:19:42 AM
Applicant Type : Company
Project Type: ONGOING




VATIKA LIMITED
VATIKA TRIANGLE, 4TH FLOOR, SUSHANT LOK, PHASE-I, BLOCK-A, M. G. ROAD, GURUGRAM - 122002
01244177777
9810566938 (Number Shared by Promoter in Public)
vatika.rera@vatikagroup.com
https://www.vatikagroup.com
XXXX647G
U74899HR1998PLC054821
 
 


 
 


 
 


 
 


 
 







VATIKA CITY CENTRAL
SECTOR- 21, 22, 23, AND 25
AMBALA
AMBALA
1714090700
1714090700 (Number Shared by Promoter in Public)
vatika.rera@vatikagroup.com
GHANSHYAM CHAUHAN
1714090700
1714090700 (Number Shared by Promoter in Public)
vatika.rera@vatikagroup.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
15899712-07-20183455000HDFC BANK LIMITEDHRERA Panchkula







170.703 (Acre)
123.43
123.43
174.373 (Acre)
256 of 2007 dated 07.11.2007 & 100 of 2014 dated 13.08.2014.
No
Address     FLAT NO. 621-A, 6TH FLOOR, DEVIKA TOWERS, 6 , NEHRU PLACE, NEW DELHI - 110019
Annexure-B- THROUGH THE DEVELOPMENT AGREEMENT DATED 16-08-2009 ALONG WITH RELEVANT DOCUMENTS SALE DEEDS ETC.
AFTER GRANT OF LICENSES.
No
NOT APPLICABLE
Yes
Yes
Yes







36034.44 Lakhs
2842.44 Lakhs
0 Lakhs
6000.00 Lakhs
27192.00 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 82.92
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0
3CONSTRUCTION OF ROADS 17.340
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 8.89
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 61.553
Total170.703




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHARYANA URBAN DEVELOPMENT AUTHORITY (HUDA)Yes
WATER SUPPLYHARYANA URBAN DEVELOPMENT AUTHORITY (HUDA)Yes
ELECTRICITYUHBVNNo
SEWAGE DISPOSALHARYANA URBAN DEVELOPMENT AUTHORITY (HUDA)Yes
STORM WATER DRAINAGEHARYANA URBAN DEVELOPMENT AUTHORITY (HUDA)Yes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS4400.00AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM280.16AS PER PROJECT REPORT
3STORM WATER DRAINAGE700.23AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM200.12AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL500.25YET TO BE PREPARED
6STREET LIGHTING850.02AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS448.08AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


21-01-2015 (date)
NA (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartments Total number of plots/apartments in the project Total size of the plots/carpet area of the apartments Plots/apartments booked/ sold upto the date of application Yet to be sold/ booked No. of towers to be/ being constructed for booked apartments
1 PLOT Type ANNEXURE 9 0 0 0 0 0 0
Total00000






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
NOT APPLICABLE0NOT APPLICABLE


24-10-2018
24-10-2018
24-10-2018
24-10-2018
0
24-10-2018
NOT APPLICABLE
NOT APPLICABLE


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT0REFER ANNEXURE 9
30-11-2008
55.68
30-06-2024
PROVIDED
ANNEXURE-10


0
0
0
0
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2017
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0
Shops0
Plots0

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments000
Shops000
Plots0025.75
Plots (Annexure-11)25.75

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots25.7525.7525.7525.75

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots25.7525.7525.7525.75

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots25.7525.7525.7525.75

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots25.7525.7525.7525.75

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots25.7525.75128.77128.77

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments00
Shops00
Plots128.77128.77




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2017
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0016.8416.84
Water Supply System001.071.07
Sewerage treatment & garbage disposal002.682.68
Electricity Supply System000.770.77
Storm Water Drainage002.682.68
Parks and Playgrounds001.711.71
Clubhouse/community centres0000
Shopping area0000
Other0000
Solid Waste Disposal00

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements16.8416.8416.8416.84
Water Supply System1.071.071.071.07
Sewerage treatment & garbage disposal2.682.682.682.68
Electricity Supply System0.770.770.770.77
Storm Water Drainage2.682.682.682.68
Parks and Playgrounds1.711.711.711.71
Clubhouse/community centres0000
Shopping area0000
Other0000
Solid Waste Disposal0000

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements16.8416.8416.8416.84
Water Supply System1.071.071.071.07
Sewerage treatment & garbage disposal2.682.682.682.68
Electricity Supply System0.770.770.770.77
Storm Water Drainage2.682.682.682.68
Parks and Playgrounds1.711.711.711.71
Clubhouse/community centres0000
Shopping area0000
Other0000
Solid Waste Disposal0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements16.8416.8416.8416.84
Water Supply System1.071.071.071.07
Sewerage treatment & garbage disposal2.682.682.682.68
Electricity Supply System0.770.770.770.77
Storm Water Drainage2.682.682.682.68
Parks and Playgrounds1.711.711.711.71
Clubhouse/community centres0000
Shopping area0000
Other0000
Solid Waste Disposal0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements16.8416.8416.8416.84
Water Supply System1.071.071.071.07
Sewerage treatment & garbage disposal2.682.682.682.68
Electricity Supply System0.770.770.770.77
Storm Water Drainage2.682.682.682.68
Parks and Playgrounds1.711.711.711.71
Clubhouse/community centres0000
Shopping area0000
Other0000
Solid Waste Disposal0000

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements16.8416.8484.284.2
Water Supply System1.071.075.365.36
Sewerage treatment & garbage disposal2.682.6813.413.4
Electricity Supply System0.770.773.833.83
Storm Water Drainage2.682.6813.413.4
Parks and Playgrounds1.711.718.578.57
Clubhouse/community centres0000
Shopping area0000
Other0000
Solid Waste Disposal000.010.01

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements84.284.2
Water Supply System5.365.36
Sewerage treatment & garbage disposal13.413.4
Electricity Supply System3.833.83
Storm Water Drainage13.413.4
Parks and Playgrounds8.578.57
Clubhouse/community centres00
Shopping area00
Other00
Solid Waste Disposal0.010.01












Particulars Remarks, if any
i. No. of Flats/Apartments constructed14841451 Nos Plots and 33 Nos Sellable Community & Commercial Sites (Total Approved No) Refer Annexure-5
ii. No. of Flats/ Apartments booked780Plots
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter24421.96 LakhsPlots
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter17748.54 LakhsPlots
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter6673.42 LakhsPlots
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter3318.18 Lakhs Plots
vii. Amount invested in the project upto the date of application30954.04 Lakhs
Land cost (If any)2842.44 Lakhs
Apartments0 LakhsNot Applicable
Infrastructure4969.85 Lakhs
EDC/ Taxes Etc.23141.75 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession5514.25 Lakhs
(a) In respect of existing allottees1102.85 Lakhs
(b) In respect of rest of the project4411.40 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 LakhsNil
x. Total liabilities against the project up-to-date. (Annex details in folder C) 959.06 LakhsAnnexure-13



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS3923.213249.62
II. WATER SUPPLY SYSTEM249.80206.91
III. STORM WATER DRAINAGE624.35517.16
IV. ELECTRICITY SUPPLY SYSTEM178.43147.80
V. SEWAGE TREATMENT & GARBAGE DISPOSAL624.24517.06
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM0.450.37
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.399.52330.93
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM00
XVII. OTHER FACILITIES AS PER PROJECT REPORT00









Yes
Yes
HDFC BANK LIMITED VATIKA ATTRIUM, BLOCK - A, KHASRA NO. 1742/1/2 1743, VILLAGE WAZIRABAD, GURGAON SECTOR - 53
05720350000406
HDFC0000572
110240093
000572
1. Mr. Anil Bhalla 2. Mr. Gautam Bhalla 3. Mr. Gaurav Bhalla 4. Mr. K V George 5. Ms. Veena Bhomia (Vatika Triangle, 4th Floor, Sushant Lok 1, MG Road, Gurugram 122002)
Attached - Annexure-16











Yes
Yes
Yes
No
No
No
No
No
No
No


Yes
Yes
Yes
Yes
Yes
No
Yes
No
Statutory Approvals Statutory Approvals StatusDate
I. LAYOUT PLANALREADY BEEN OBTAINED21-01-2015
II. DEMARCATION PLANALREADY BEEN OBTAINED10-10-2014
III. ZONING PLANALREADY BEEN OBTAINED17-04-2015
IV. SERVICE COST ESTIMATE ALREADY BEEN OBTAINED04-05-2018
V. NOC FROM FOREST DEPT.ALREADY BEEN OBTAINED03-09-2014
VI. ASSURANCE FOR WATER SUPPLY, SEWERAGE & STORM WATERALREADY BEEN OBTAINED18-11-2014
VII. ISSUE OF CONSENT TO ESTABLISH FROM POLLUTION ANGLE.ALREADY BEEN OBTAINED29-01-2014
VIII. NOC FROM AIRPORT AUTHORITY OF INDIAALREADY BEEN OBTAINED23-01-2009
IX. ENVIRONMENTAL CLEARANCE - 152.302 ACRES.ALREADY BEEN OBTAINED28-05-2009
X. THE APPLICATION FOR THE ENVIRONMENTAL CLEARANCE FOR THE EXPANSION OF THE PROJECT FROM 152.302 ACRES TO 174.371 ACRES WAS SUBMITTED TO SEIAA, HARYANA. THE SAME IS UNDER PROCESS AT STATE EXPERT APPRAISAL COMMITTEE.APPLIED FOR BUT YET TO RECEIVE22-12-2014








Yes


Yes


Annexure 28







SOVEREIGN NEXT (PHASE - 1), LOCATION: SECTOR 82A, VILLAGE SHIKOHPUR, TEHSIL MANESAR, DISTRICT GURUGRAM, STATE HARYANA.
34519.201
146
0
54
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
18175.0018175.0010956.15
Cost of the apartments10350.0010350.006017.40
Cost of the infrastructure1150.001150.00668.00
Others costs6675.006675.004270.75


7731.17 Lakhs
3965.09 Lakhs
15000.00 Lakhs
15000.00 Lakhs
No
31-07-2022
31-07-2022




TRANQUIL HEIGHTS (PHASE - 1), LOCATION: SECTOR 82A, VILLAGE SHIKOHPUR, TEHSIL MANESAR, DISTRICT GURUGRAM, STATE HARYANA.
22646.293
169
0
112
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
13056.0013056.005650.76
Cost of the apartments7200.007200.001062.63
Cost of the infrastructure800.00800.00118.00
Others costs5056.005056.004470.13


5162.97 Lakhs
8361.37 Lakhs
20000.00 Lakhs
20000.00 Lakhs
No
31-01-2022
31-01-2022




TURNING POINT (PHASE - 1), LOCATION: SECTOR 88B, VILLAGE HARSARU, SUB-TEHSIL HARSARU, DISTRICT GURUGRAM, STATE HARYANA
93588.71
703
0
235
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
32145.0032145.005760.80
Cost of the apartments25200.0025200.00789.52
Cost of the infrastructure1530.001530.0087.00
Others costs5415.005415.004884.28


2524.27 Lakhs
16951.11 Lakhs
15000.00 Lakhs
15000.00 Lakhs
No
31-01-2025
31-01-2025




TOWN SQUARE (BLOCK-D), LOCATION: SECTOR 82A, VILLAGE SHIKOHPUR, TEHSIL MANESAR, DISTRICT GURUGRAM, STATE HARYANA
13809.56
187
0
22
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
10586.0010586.0010337.50
Cost of the apartments4500.004500.004098.08
Cost of the infrastructure500.00500.00455.00
Others costs5586.005586.005784.42


635.59 Lakhs
465.61 Lakhs
14600.00 Lakhs
14600.00 Lakhs
No
31-07-2018
31-07-2018




INXT CITY CENTRE, LOCATION: SECTOR 83, VILLAGE SHIKOHPUR, TEHSIL MANESAR, DISTRICT GURUGRAM, STATE HARYANA
67046.04
1425
0
1371
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
743757437565512.51
Cost of the apartments244802448017606.51
Cost of the infrastructure272027201956.28
Others costs471754717545949.72


43294.52 Lakhs
1245.14 Lakhs
5900.00 Lakhs
5900.00 Lakhs
No
31-01-2020
31-01-2020










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENOT APPLICABLE
2WALL FINISHING DETAILSNOT APPLICABLE
3KITCHEN DETAILSNOT APPLICABLE
4BATHROOM FITTINGSNOT APPLICABLE
5WOOD WORK ETCNOT APPLICABLE
6DOORS AND WINDOS FRAMESNOT APPLICABLE
7GLASS WORKNOT APPLICABLE
8ELECTRIC FITTINGSNOT APPLICABLE
9CONDUCTING AND WIRING DETAILSNOT APPLICABLE
10CUPBOARD DETAILSNOT APPLICABLE
11WATER STORAGENOT APPLICABLE
12LIFT DETAILSNOT APPLICABLE
13EXTERNAL GLAZINGSNOT APPLICABLE
13.1WINDOWS/GLAZINGSNOT APPLICABLE
14DOORSNOT APPLICABLE
14.1MAIN DOORSNOT APPLICABLE
14.2INTERNAL DOORSNOT APPLICABLE
15AIR CONDITIONINGNOT APPLICABLE
16ELECTRICAL FITTINGSNOT APPLICABLE
17CNG PIPE LINENOT APPLICABLE
18PROVISION OF WIFI AND BROADBAND FACILITYNOT APPLICABLE
19EXTERNAL FINISHING/COLOUR SCHEMENOT APPLICABLE
20INTERNAL FINISHINGNOT APPLICABLE
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNOT APPLICABLE
1 . 2 WALLSNOT APPLICABLE
1 . 3 CEILINGNOT APPLICABLE
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNOT APPLICABLE
2 . 2 WALLSNOT APPLICABLE
2 . 3 CEILINGNOT APPLICABLE
2 . 4 MODULAR WARDROBESNOT APPLICABLE
3 . MASTER TOILET
3 . 1 FLOORNOT APPLICABLE
3 . 2 WALLSNOT APPLICABLE
3 . 3 CEILINGNOT APPLICABLE
3 . 4 COUNTERSNOT APPLICABLE
3 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE
3 . 6 FITTING/FIXTURESNOT APPLICABLE
4 . BED ROOMS
4 . 1 FLOORNOT APPLICABLE
4 . 2 WALLSNOT APPLICABLE
4 . 3 CEILINGNOT APPLICABLE
4 . 4 WARDROBESNOT APPLICABLE
5 . TOILET
5 . 1 FLOORNOT APPLICABLE
5 . 2 WALLSNOT APPLICABLE
5 . 3 CEILINGNOT APPLICABLE
5 . 4 COUNTERSNOT APPLICABLE
5 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE
5 . 6 FIXTURESNOT APPLICABLE
6 . KITCHEN
6 . 1 FLOORNOT APPLICABLE
6 . 2 WALLSNOT APPLICABLE
6 . 3 CEILINGNOT APPLICABLE
6 . 4 COUNTERSNOT APPLICABLE
6 . 5 FIXTURESNOT APPLICABLE
6 . 6 KITCHEN APPLIANCESNOT APPLICABLE
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNOT APPLICABLE
7 . 2 WALLS & CEILINGNOT APPLICABLE
7 . 3 TOILETNOT APPLICABLE
7 . 4 BALCONYNOT APPLICABLE
8 . SIT-OUTS
8 . 1 FLOORNOT APPLICABLE
8 . 2 WALLS & CEILINGNOT APPLICABLE
8 . 3 RAILINGSNOT APPLICABLE
8 . 4 FIXTURESNOT APPLICABLE












Sr. No.Document DescriptionDate of Document UploadView Document
1 APPROVED SEWERAGE DWG-PART-C 26-10-2018 ------
2 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 26-10-2018 View Document
3 DEMARCATION PLAN 26-10-2018 View Document
4 ZONING PLAN 26-10-2018 View Document
5 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 26-10-2018 View Document
6 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 26-10-2018 View Document
7 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 26-10-2018 ------
8 LIST OF DIRECTORS & SHARE HOLDERS 26-10-2018 ------
9 BOARD RESOLUTION 26-10-2018 ------
10 DEVELOPMENT WORK PLAN 26-10-2018 ------
11 CERTIFIED BY ARCHITECT & ENGINEER (ANNEXURE-3C-1) 26-10-2018 ------
12 TIME PERIOD COMMITTED TO THE ALLOTTEES (ANNEXURE-3B) 26-10-2018 ------
13 CERTIFIED BY CHARTERED ACCOUNTANTS 26-10-2018 ------
14 QUARTERLY SCHEDULE OF DEVELOPMENT (PLOTS) 26-10-2018 ------
15 QUARTERLY SCHEDULE OF DEVELOPMENT (INFRASTRUCTURE) 26-10-2018 ------
16 TOTAL LIABILITIES AGAINST THE PROJECT UP-TO- DATE 26-10-2018 ------
17 DETAILS OF THE PLOTS IN THE PROJECT 26-10-2018 ------
18 APPROVED STORMWATER DRAIN DWG-PART-C 26-10-2018 ------
19 APPROVED RISING MAIN DWG 26-10-2018 ------
20 ASSURANCE FOR WATER SUPPLY, SEWERAGE & STORM WATER 26-10-2018 ------
21 RELEVANT DOCUMENTS ETC-10 29-10-2018 ------
22 APPROVED WATER SUPPLY DWG 26-10-2018 ------
23 APPROVED ROADS DWG 26-10-2018 ------
24 CASH FLOW STATEMENT OF THE PROJECT 26-10-2018 ------
25 CERTIFICATE ISSUED BY CA 26-10-2018 ------
26 DEMARCATION PLAN 26-10-2018 ------
27 ZONNING PLAN 26-10-2018 ------
28 ELECTRICAL LAYOUT 26-10-2018 ------
29 STREET LIGHTING LAYOUT 26-10-2018 ------
30 ISSUE OF CONSENT TO ESTABLISH FROM POLLUTION ANGLE 26-10-2018 ------
31 REGISTRATION CERTIFICATE & MOA & AOA (B) 26-10-2018 ------
32 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 26-10-2018 View Document
33 RELEVANT DOCUMENTS ETC-3 26-10-2018 ------
34 FOREST NOC 26-10-2018 ------
35 NOC FROM AIRPORT AUTHORITY OF INDIA 26-10-2018 ------
36 ENVIRONMENTAL CLEARANCE 26-10-2018 ------
37 DRAFT APPLICATION FORM CUM ALLOTMENT LETTER 26-10-2018 ------
38 DRAFT AGREEMENT FOR SALE 26-10-2018 ------
39 GIST OF THE IMPORTANT PROVISIONS OF THE DRAFT AGREEMENT 26-10-2018 ------
40 DRAFT CONVEYANCE DEED 26-10-2018 ------
41 REGISTRATION CERTIFICATE & MOA & AOA (A) 26-10-2018 ------
42 REGISTRATION CERTIFICATE & MOA & AOA (C) 26-10-2018 ------
43 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 26-10-2018 View Document
44 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 26-10-2018 View Document
45 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 26-10-2018 View Document
46 RELEVANT DOCUMENTS ETC-2 26-10-2018 ------
47 RELEVANT DOCUMENTS ETC-4 26-10-2018 ------
48 RELEVANT DOCUMENTS ETC 26-10-2018 ------
49 RELEVANT DOCUMENTS ETC-6 26-10-2018 ------
50 RELEVANT DOCUMENTS ETC-7 26-10-2018 ------
51 RELEVANT DOCUMENTS ETC-8 26-10-2018 ------
52 RELEVANT DOCUMENTS ETC-9 29-10-2018 ------
53 RELEVANT DOCUMENTS ETC-11 29-10-2018 ------
54 RELEVANT DOCUMENTS ETC-12 29-10-2018 ------
55 RELEVANT DOCUMENTS ETC-13 29-10-2018 ------
56 RELEVANT DOCUMENTS ETC-14 29-10-2018 ------
57 RELEVANT DOCUMENTS ETC-15 29-10-2018 ------
58 RELEVANT DOCUMENTS ETC-16 29-10-2018 ------
59 RELEVANT DOCUMENTS ETC-17 29-10-2018 ------
60 RELEVANT DOCUMENTS ETC-18 29-10-2018 ------
61 RELEVANT DOCUMENTS ETC-19 29-10-2018 ------
62 RELEVANT DOCUMENTS ETC-20 29-10-2018 ------
63 RELEVANT DOCUMENTS ETC-21 29-10-2018 ------
64 RELEVANT DOCUMENTS ETC-22 29-10-2018 ------
65 RELEVANT DOCUMENTS ETC-23 29-10-2018 ------
66 RELEVANT DOCUMENTS ETC-24 29-10-2018 ------
67 RELEVANT DOCUMENTS ETC-25 29-10-2018 ------
68 RELEVANT DOCUMENTS ETC-26 29-10-2018 ------
69 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 29-10-2018 View Document
70 RELEVANT DOCUMENTS ETC-27 29-10-2018 ------
71 RELEVANT DOCUMENTS ETC-27 29-10-2018 ------
72 RELEVANT DOCUMENTS ETC-29 29-10-2018 ------
73 RELEVANT DOCUMENTS ETC-30 29-10-2018 ------
74 RELEVANT DOCUMENTS ETC-31 29-10-2018 ------
75 RELEVANT DOCUMENTS ETC-32 29-10-2018 ------
76 RELEVANT DOCUMENTS ETC-33 29-10-2018 ------
77 ANNEXURE 8 - 1 APPROVAL OF SERVICE PLAN OR ESTIMATES WITH REPORT-(A) 29-10-2018 ------
78 ANNEXURE 8 - 1 APPROVAL OF SERVICE PLAN OR ESTIMATES WITH REPORT-(B) 29-10-2018 ------
79 ANNEXURE 8 - 1 APPROVAL OF SERVICE PLAN OR ESTIMATES WITH REPORT-(C) 29-10-2018 ------
80 ANNEXURE 8 - 1 APPROVAL OF SERVICE PLAN OR ESTIMATES WITH REPORT-(D) 29-10-2018 ------
81 ANNEXURE 14 - 1 DIRECTOR'S REPORT & BALANCE SHEET - FINANCIAL YEAR 2016-2017 (A) 29-10-2018 ------
82 ANNEXURE 14 - 1 DIRECTOR'S REPORT & BALANCE SHEET - FINANCIAL YEAR 2016-2017 (B) 29-10-2018 ------
83 ANNEXURE 14 - 1 DIRECTOR'S REPORT & BALANCE SHEET - FINANCIAL YEAR 2016-2017 (C) 29-10-2018 ------
84 ANNEXURE 14 - 1 DIRECTOR'S REPORT & BALANCE SHEET - FINANCIAL YEAR 2016-2017 (D) 29-10-2018 ------
85 ANNEXURE 14 - 3 DIRECTOR'S REPORT & BALANCE SHEET - FINANCIAL YEAR 2014-2015 (A) 29-10-2018 ------
86 ANNEXURE 14 - 3 DIRECTOR'S REPORT & BALANCE SHEET - FINANCIAL YEAR 2014-2015 (B) 29-10-2018 ------
87 ANNEXURE 14 - 3 DIRECTOR'S REPORT & BALANCE SHEET - FINANCIAL YEAR 2014-2015 (C) 29-10-2018 ------
88 REP-II 30-10-2018 ------
89 ANNEXURE-A 30-10-2018 ------
90 REP-I 30-10-2018 ------
91 ANNEXURE 14 - 2 DIRECTOR'S REPORT & BALANCE SHEET - FINANCIAL YEAR 2015-2016 (A) 30-10-2018 ------
92 ANNEXURE 14 - 2 DIRECTOR'S REPORT & BALANCE SHEET - FINANCIAL YEAR 2015-2016 (B) 30-10-2018 ------
93 ANNEXURE 14 - 2 DIRECTOR'S REPORT & BALANCE SHEET - FINANCIAL YEAR 2015-2016 (C) 30-10-2018 ------
94 ANNEXURE 14 - 2 DIRECTOR'S REPORT & BALANCE SHEET - FINANCIAL YEAR 2015-2016 (D) 30-10-2018 ------
95 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 30-10-2018 View Document