410, 4TH FLOOR, D MALL, NETAJI SUBHASH PLACE, PITAMPURA, NEW DELHI-110034
01147804747
9811013011 (Number Shared by Promoter in Public)
parkervrcinfo@yahoo.com
http://www.parkervrc.com/
XXXX028G
U45201DL2005PTC133483
WHITE LILY
SECTOR-8, VILLAGE KAMASPUR, SONEPAT
SONIPAT
SONIPAT
9811013011 (Number Shared by Promoter in Public)
parkervrcinfo@yahoo.com
RAJEEV GUPTA
9574003201 (Number Shared by Promoter in Public)
parkervrcinfo@yahoo.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
882417
28-07-2017
374820
CORPORATION BANK
HRERA Panchkula
2
882431
09-08-2017
281180
CORPORATION BANK
HRERA Panchkula
3
882446
17-08-2017
2311
CORPORATION BANK
HRERA Panchkula
9.262 (Acre)
1.75
1.75
9.262 (Acre)
182 of 2007 Dated 14.05.2007
Yes
23761 Lakhs
2930 Lakhs
9000 Lakhs
4092 Lakhs
7739 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
6419.10
3
CONSTRUCTION OF ROADS
12116.90
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
8553
6
GREEN BELTS
1500
7
VEHICLE PARKINGS
24560
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
195.80
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
480
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
1668
12
ANY OTHER
0
13
STILT
4297.09
Total
59789.89
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
Yes
WATER SUPPLY
HSVP
Yes
ELECTRICITY
UHBVN
Yes
SEWAGE DISPOSAL
HSVP
Yes
STORM WATER DRAINAGE
HSVP
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
230.75
SUBMITTED TO TOWN & COUNTRY PLANNING
2
WATER SUPPLY SYSTEM
267.22
SUBMITTED TO TOWN & COUNTRY PLANNING
3
STORM WATER DRAINAGE
90.96
SUBMITTED TO TOWN & COUNTRY PLANNING
4
ELECTRICITY SUPPLY SYSTEM
500
SUBMITTED TO TOWN & COUNTRY PLANNING
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
136.94
AS PER PROJECT REPORT
6
STREET LIGHTING
35.52
SUBMITTED TO TOWN & COUNTRY PLANNING
7
SECURITY AND FIRE FIGHTING
0
SUBMITTED TO TOWN & COUNTRY PLANNING
8
PLAYGROUNDS AND PARKS
7.98
SUBMITTED TO TOWN & COUNTRY PLANNING
9
CLUB HOUSE/COMMUNITY CENTRE
50
SUBMITTED TO TOWN & COUNTRY PLANNING
10
SHOPPING AREA
50
SUBMITTED TO TOWN & COUNTRY PLANNING
11
RENEWABLE ENERGY SYSTEM
0
AS PER PROJECT REPORT
12
SCHOOL
200
SUBMITTED TO TOWN & COUNTRY PLANNING
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
21-01-2013 (date)
21-01-2013 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
PLOT Type
0
0
0
0
0
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
2 BHK
124
OCCUPANCY CERTIFICATE RECEIVED
3 BHK
173
OCCUPANCY CERTIFICATE RECEIVED
4 BHK
56
OCCUPANCY CERTIFICATE RECEIVED
PENT HOUSE
3
OCCUPANCY CERTIFICATE RECEIVED
SHOPS
15
OCCUPANCY CERTIFICATE RECEIVED
01-08-2014
31-12-2017
31-12-2018
01-08-2014
100
31-12-2018
ENCLOSED
PROJECT COMPLETED. RECEIVED OCCUPANCY CERTIFICATE
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
NOT APPLICABLE
01-08-2014
0
31-12-2018
PLOTTED COLONY NOT APPLICABLE
NOT APPLICABLE
0
143
601
141
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2018
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
400
500
900
Shops
0
0
0
Plots
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2018
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
4
4
3
Water Supply System
15
20
25
Sewerage treatment & garbage disposal
10
15
0
Electricity Supply System
150
200
100
Storm Water Drainage
7
8
0
Parks and Playgrounds
10
10
10
Clubhouse/community centres
10
5
5
Shopping area
0
0
0
Other
0
0
0
Lifts
75
75
50
Security System
10
10
5
Covered Parking
150
150
215
School
10
20
20
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
578
Project Completed
(OC Received)
ii. No. of Flats/ Apartments booked
366
Project Completed Occupancy Certificate Received
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
167.88 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
146.50 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
21.38 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
21.38 Lakhs
vii. Amount invested in the project upto the date of application
0 Lakhs
Land cost (If any)
2930 Lakhs
Apartments
9000 Lakhs
Infrastructure
4092 Lakhs
EDC/ Taxes Etc.
7739 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
0 Lakhs
Project Completed Occupancy Certificate Received
(a) In respect of existing allottees
0 Lakhs
Project Completed Occupancy Certificate Received
(b) In respect of rest of the project
0 Lakhs
Project Completed Occupancy Certificate Received
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
530 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
230.75
0
II. WATER SUPPLY SYSTEM
267.22
0
III. STORM WATER DRAINAGE
90.96
0
IV. ELECTRICITY SUPPLY SYSTEM
500
0
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
136.94
0
VI. CLUB HOUSE/COMMUNITY CENTRE
50
0
VII. SCHOOL
200
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
50
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
7.98
0
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
0
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
0
0
Yes
Yes
CORPORATION BANK, FAIZ ROAD, JHANDEWALAN, NEW DELHI
510101005726068
CORP0000447
110017012
0447
Mr. Manish Garg and Mr. Chander Shekhar Bansal
Enclosed
Yes
No
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. PERMANENT ELECTRICAL CONNECTIONS
ALREADY BEEN OBTAINED
22-07-2019
II. PUBLIC HEALTH APPROVAL FROM HUDA
ALREADY BEEN OBTAINED
31-10-2012
III. ENVIRONMENT CLEARANCE
ALREADY BEEN OBTAINED
11-07-2014
IV. NOC FROM AIRPORT AUTHORITY
ALREADY BEEN OBTAINED
13-11-2013
V. SERVICE PLAN ESTIMATES
ALREADY BEEN OBTAINED
27-12-2017
VI. CONSENT TO ESTABLISH FROM POLLUTION CONTROL BOARD
ALREADY BEEN OBTAINED
27-04-2015
VII. FIRE NOC
ALREADY BEEN OBTAINED
16-01-2019
VIII. SANCTIONED PLANS
ALREADY BEEN OBTAINED
23-01-2013
IX. LIFT REGISTRATION
ALREADY BEEN OBTAINED
NA
X. CONSENT TO OPERATE
APPLIED FOR BUT YET TO RECEIVE
NA
Yes
Yes
As per enclosed Agreement
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
• VITRIFIED TILES IN DRAWING ROOM, BED ROOMS
• GRANITE FLOORING N COMMON AREA AND STAIR CASES
• WOODEN FLOORING IN MASTER BED ROOM
2
WALL FINISHING DETAILS
• OIL BOUND DISTEMPER ON INTERNAL WALLS
• TEXTURE PAINT ON EXTERNAL WALLS