HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-595-2019
Submission Date : 25-10-2019 02:41:24 AM
Applicant Type : Company
Project Type: ONGOING




MAPSKO BUILDERS PVT LTD
52, NORTH AVENUE, ROAD, PUNJABI BAGH WEST, NEW DELHI -110026
01142467410
9911573797 (Number Shared by Promoter in Public)
info@mapskogroup.com
https://mapskogroup.com
XXXX296L
U45203DL2003PTC118590
 
 


 
 


 
 







MAPSKO GALLERIA (PROJECT AREA 1.82 ACRES COMMERCIAL, PART OF RESIDENTIAL PLOTTED COLONY)
SECTOR - 27
SONIPAT
SONIPAT
9990613737 (Number Shared by Promoter in Public)
salescrm@mapskogroup.com
SANDEEP KUMAR
9990613737 (Number Shared by Promoter in Public)
salescrm@mapskogroup.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
115137416-10-2017221000PUNJAB NATIONAL BANKHRERA Panchkula







1.82 (Acre)
1.497
1.497
134.205 (Acre)
43 to 55 of 2007(21-01-2019)
No
Address     52, NORTH AVENUE ROAD, PUNJABI BAGH WEST, NEW DELHI - 110026
Annexure-B- COLLABORATION AGREEMENT
YES
No
COLLABORATION AGREEMENT
No
No
No







3500 Lakhs
101 Lakhs
1870 Lakhs
679 Lakhs
850 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS3155.350
3CONSTRUCTION OF ROADS0
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0
6GREEN BELTS0
7VEHICLE PARKINGS1548.12
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER2661.752
Total7365.222




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSALREADY OBTAINED PART OCCUPATION CERTIFICATE FOR THE ENTIRE LAND MEASURING 134.205 ACRES OF WHICH THIS COMMERCIAL POCKET IS A PARTYes
WATER SUPPLYALREADY OBTAINED PART OCCUPATION CERTIFICATE FOR THE ENTIRE LAND MEASURING 134.205 ACRES OF WHICH THIS COMMERCIAL POCKET IS A PARTYes
ELECTRICITYALREADY OBTAINED PART OCCUPATION CERTIFICATE FOR THE ENTIRE LAND MEASURING 134.205 ACRES OF WHICH THIS COMMERCIAL POCKET IS A PARTYes
SEWAGE DISPOSALALREADY OBTAINED PART OCCUPATION CERTIFICATE FOR THE ENTIRE LAND MEASURING 134.205 ACRES OF WHICH THIS COMMERCIAL POCKET IS A PARTYes
STORM WATER DRAINAGEALREADY OBTAINED PART OCCUPATION CERTIFICATE FOR THE ENTIRE LAND MEASURING 134.205 ACRES OF WHICH THIS COMMERCIAL POCKET IS A PARTYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS170AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM115AS PER PROJECT REPORT
3STORM WATER DRAINAGE0YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM175AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL138AS PER PROJECT REPORT
6STREET LIGHTING0YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING81AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS0YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA1870AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


NA (date)
NA (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE 1/GROUND FLOOR2183.0117217200
2APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE 2/FIRST FLOOR1710.5315415310
3APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE 3/SECOND FLOOR1787.76129101280
4APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE 4/THIRD FLOOR1441.4210739680






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
00


01-02-2014
30-06-2019
30-06-2019
01-02-2014
80
30-06-2019


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
01-02-2014
0
30-06-2019


178
0
0
44
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops900
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments00
Shops200250
Plots00

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments00
Shops260260
Plots00




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements150
Water Supply System100
Sewerage treatment & garbage disposal125
Electricity Supply System125
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other69

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements55
Water Supply System55
Sewerage treatment & garbage disposal33
Electricity Supply System1010
Storm Water Drainage00
Parks and Playgrounds00
Clubhouse/community centres00
Shopping area00
Other33

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements55
Water Supply System32
Sewerage treatment & garbage disposal43
Electricity Supply System2010
Storm Water Drainage00
Parks and Playgrounds00
Clubhouse/community centres00
Shopping area00
Other33












Particulars Remarks, if any
i. No. of Flats/Apartments constructed562
ii. No. of Flats/ Apartments booked465
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter4913 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter3393 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter967 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter553 Lakhs
vii. Amount invested in the project upto the date of application0 Lakhs
Land cost (If any)101 Lakhs
Apartments1469 Lakhs
Infrastructure0 Lakhs
EDC/ Taxes Etc.750 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession1180 Lakhs
(a) In respect of existing allottees0 Lakhs
(b) In respect of rest of the project0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
408 LakhsThis loan amount is the outstanding loan amount as on 31.07.2018 out of loan against entire plotted colony project and not specific to the applied commercial project (CA Certificate is enclosed – Annexure)
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS170150
II. WATER SUPPLY SYSTEM115100
III. STORM WATER DRAINAGE00
IV. ELECTRICITY SUPPLY SYSTEM175125
V. SEWAGE TREATMENT & GARBAGE DISPOSAL138125
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER1870900
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.00
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM8169
XVII. OTHER FACILITIES AS PER PROJECT REPORT00









Yes
Yes
PUNJAB NATIONAL BANK, PUNJABI BAGH WEST, NEW DELHI
3096002900000010
PUNB0150100
110024079
150100
Rishu Garg, 52, North Avenue Road, Punjabi Bagh West, New Delhi - 110026
Annexed











Yes
Yes
Yes
Yes
No
No
No
No
No
No


Yes
Yes
Yes
Yes
Yes
No
No
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENCE NO. 43-55 OF 2007ALREADY BEEN OBTAINEDNA
II. DEMARCATION PLANALREADY BEEN OBTAINEDNA
III. ZONING PLANALREADY BEEN OBTAINEDNA
IV. ENVIRONMENT CLEARANCEALREADY BEEN OBTAINEDNA








Yes


Yes















SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSECERAMIC TILES IN SHOPS AND GRANITE STONE IN COMMON AREA
2WALL FINISHING DETAILSPLASTER WITH PLASTIC PAINT WITH PLEASING SHADES
3KITCHEN DETAILSNA
4BATHROOM FITTINGSWBC, WASH BASIN, LOOKING MIRROR, URINAL,
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESROLLING SHUTTER AND UPVC WINDOWS
7GLASS WORKUPVC REFLECTIVE TOUGHENED/PLAIN GLASS
8ELECTRIC FITTINGSMODULAR SWITCHES POINT
9CONDUCTING AND WIRING DETAILSCOPPER CONCEALED WIRING WITH SWITCHES & SOCKETS
10CUPBOARD DETAILSNA
11WATER STORAGEOVERHEAD TANK
12LIFT DETAILS3 PASSENGERS LIFT
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSUPVC WINDOWS
14DOORSROLLING SHUTTER
14.1MAIN DOORSSHOPS MAIN DOOR ROLLING SHUTTER
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSMODULAR SWITCHES POINT
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMELONG LASTING TEXTURE PAINT
20INTERNAL FINISHINGPLASTER WITH PLASTIC PAINT WITH PLEASING SHADES
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN24-10-2019 View Document
2COPY OF LICENSE ALONG WITH SCHEDULE OF LAND24-10-2019 View Document
3DEMARCATION PLAN24-10-2019 View Document
4ZONING PLAN24-10-2019 View Document
5CASH FLOW STATEMENT OF THE PROPOSED PROJECT24-10-2019 View Document
6DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.24-10-2019 View Document
7SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN24-10-2019 View Document
8NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT24-10-2019 View Document
9CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT24-10-2019 View Document
10A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS24-10-2019 View Document
11DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD24-10-2019 View Document
12IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN24-10-2019 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 EXTENSION RC APPROVED 20-09-2024 View Document