9711802285 (Number Shared by Promoter in Public)
PROPEXREALTY@GMAIL.COM
XXXX684C
U70109HR2018PTC075968
PROPEX CITY FARIDABAD
SECTOR-70, FARIDABAD
FARIDABAD
FARIDABAD
9711802285 (Number Shared by Promoter in Public)
PROPEXREALTY@GMAIL.COM
MANISH GOEL
9711802285 (Number Shared by Promoter in Public)
MANISH.GOEL@AOL.IN
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
0
02-08-2019
348400
ONLINE PAYMENT THROUGH HARYANA RERA PORTAL
HRERA Panchkula
7.55 (Acre)
2
2
7.55 (Acre)
85 of 2019 (01-08-2019)
Yes
2665.84 Lakhs
1247.35 Lakhs
0 Lakhs
493.49 Lakhs
925 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
3.716
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
2.408
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0.605
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0.002
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0.038
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.755
12
ANY OTHER
0.026
Total
7.55
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP/HUDA
No
WATER SUPPLY
HSVP/HUDA
No
ELECTRICITY
DHVBN
No
SEWAGE DISPOSAL
HSVP/HUDA
No
STORM WATER DRAINAGE
HSVP/HUDA
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
136.65
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
98.75
YET TO BE PREPARED
3
STORM WATER DRAINAGE
103.42
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
50.26
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
100.75
YET TO BE PREPARED
6
STREET LIGHTING
0
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
3.66
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
NA (date)
NA (date)
14-08-2019
31-07-2022
Plot Area(In Square Meter)
Number of plots in the project
140.42
9
142.90
1
66.43
4
67.32
8
69.08
1
76.08
10
81.66
5
81.72
5
81.97
1
89.67
4
90.11
1
95.18
6
96.82
2
96.88
1
97.29
16
97.35
8
99.6
1
110.31
28
118.78
5
119.55
1
126.02
1
127.25
1
127.95
4
132.51
11
134.16
1
139.23
1
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
1221.96
1
1
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
Shops
0
0
Plots
90.21
53.01
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
37.38
61.23
116.38
87.56
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
Shops
0
Plots
47.72
Expenditure incurred till the date of application (In Lakhs)