M-11, MIDDLE CIRCUS, CONNAUGHT CIRCUS, NEW DELHI-110001
01149572787
9871883334 (Number Shared by Promoter in Public)
rera.panchkula@bptp.com
http://bptp.com
XXXX442A
U45201DL2003PLC121733
PARKLAND VILLAS
SECTOR 75 AND 84
FARIDABAD
FARIDABAD
01149572787
9810163594 (Number Shared by Promoter in Public)
rera.panchkula@bptp.com
VINOD KUMAR
8800414400
8800414400 (Number Shared by Promoter in Public)
vinod2.kumar@bptp.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
685726
17-07-2018
134000
INDUSIND BANK
HRERA Panchkula
4.70 (Acre)
1.5
1.5
106.89 (Acre)
License No 60 of 2010
License No 38 of 2011
License no 47 of 2011 for Block L
License No. 1210-1261of 2005 for block P, Q and S
No
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Address M 11 MIDDLE CIRCLE CONNAUGHT CIRCUS NEW DELHI 110001
Annexure-B- AS A PROMOTER. (AS PER THE MASTER DEVELOPMENT AGREEMENT DATED AUGUST 03, 2007 WITH THE LICENSE HOLDERS).
APPLICANT IS APPLYING ON THE BASIS OF MASTER DEVELOPMENT AGREEMENT WHICH WAS ENTERED ON AUGUST 03,2007.
No
AS PER POINT (C) OF PARTY RELATED RECITALS OF THE MASTER DEVELOPMENT AGREEMENT THE LAND OWNERS HAVE ENTERED A COLLABORATION AGREEMENTS WITH THE COUNTRYWIDE PROMOTERS PRIVATE LIMITED (HEREIN REFERRED AS COUNTRYWIDE) AND COUNTRYWIDE IN TURN HAD ALSO ENTERED COLLABORATION AGREEMENT WITH BPTP LIMITED (HEREIN REFERRED AS BPTP) WHICH GIVES EXCLUSIVE RIGHT OF THE DEVELOPMENT TO THE BPTP; ATTACHED HEREWITH FOR YOUR KIND PERUSAL.
No
No
Yes
2121.61 Lakhs
419.40 Lakhs
1053.16 Lakhs
188.33 Lakhs
460.72 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
8690.04
3
CONSTRUCTION OF ROADS
6062.69
4
PAVEMENTS
1741.56
5
PARKS AND PLAYGROUNDS
0
6
GREEN BELTS
2533
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
Total
19027.29
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
Yes
WATER SUPPLY
HSVP
Yes
ELECTRICITY
HSVP
Yes
SEWAGE DISPOSAL
HSVP
Yes
STORM WATER DRAINAGE
HSVP
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
36
SUBMITTED TO HUDA
2
WATER SUPPLY SYSTEM
29.50
SUBMITTED TO HUDA
3
STORM WATER DRAINAGE
16
SUBMITTED TO HUDA
4
ELECTRICITY SUPPLY SYSTEM
67.76
SUBMITTED TO HUDA
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
34
SUBMITTED TO HUDA
6
STREET LIGHTING
5.07
SUBMITTED TO HUDA
7
SECURITY AND FIRE FIGHTING
0
SUBMITTED TO HUDA
8
PLAYGROUNDS AND PARKS
0
SUBMITTED TO HUDA
9
CLUB HOUSE/COMMUNITY CENTRE
0
SUBMITTED TO HUDA
10
SHOPPING AREA
0
SUBMITTED TO HUDA
11
RENEWABLE ENERGY SYSTEM
0
SUBMITTED TO HUDA
12
SCHOOL
0
SUBMITTED TO HUDA
13
HOSPITAL/DISPENSARY
0
SUBMITTED TO HUDA
14
ANY OTHER
0
SUBMITTED TO HUDA
10-05-2011 (date)
10-05-2011 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Total size of the plots/carpet area of the apartments
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type VILLAS BLOCK L
125.41
17
2131.97
12
5
1
2
APARTMENT/SHOPS/OTHER BUILDINGS Type VILLAS BLOCK P
137.961
15
2069.415
15
0
0
3
APARTMENT/SHOPS/OTHER BUILDINGS Type VILLAS BLOCK Q
275.922
10
2759.22
6
4
0
4
APARTMENT/SHOPS/OTHER BUILDINGS Type VILLAS BLOCK S
346.993
9
3122.937
6
3
0
Total
51
10083.542
39
12
1
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
VILLAS
39
AS ANNEXED.
01-05-2011
31-08-2014
31-12-2022
01-05-2011
47
31-12-2022
AS MENTIONED.
AS ANNEXED.
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
31-12-2022
0
31-12-2022
AS PROVIDED.
AS MENTIONED.
0
0
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
657.16
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
12
Water Supply System
27
Sewerage treatment & garbage disposal
33
Electricity Supply System
4.88
Storm Water Drainage
13
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0.85
1.6
2.5
1
Water Supply System
0.25
0.25
0.25
0.1
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
3.25
4.5
5.5
4.95
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
1.75
1
1.85
1.95
Water Supply System
0.15
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
0
5.5
4
3.95
Storm Water Drainage
4.5
0
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
1.85
1.35
1.55
Water Supply System
0.25
0.10
0.2
Sewerage treatment & garbage disposal
0
0
0
Electricity Supply System
5.4
6
7
Storm Water Drainage
0
0
0
Parks and Playgrounds
0
0
0
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
0
0
0
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
1.65
1.75
1.9
Water Supply System
0
0
0.75
Sewerage treatment & garbage disposal
0
0
1
Electricity Supply System
2.75
3
5
Storm Water Drainage
1
1
1
Parks and Playgrounds
0
0
0
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
0
0
0
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
51
ii. No. of Flats/ Apartments booked
39
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
1913 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
1431.8 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
481.2 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
481.2 Lakhs
vii. Amount invested in the project upto the date of application
1627.16 Lakhs
Land cost (If any)
419.40 Lakhs
Apartments
657.16 Lakhs
Infrastructure
89.88 Lakhs
EDC/ Taxes Etc.
460.72 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
494.45 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
249.85 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
36
12
II. WATER SUPPLY SYSTEM
29.50
27
III. STORM WATER DRAINAGE
16
13
IV. ELECTRICITY SUPPLY SYSTEM
67.76
3.19
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
34
33
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
5.07
1.69
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
0
0
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
0
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
0
0
Yes
Yes
IDBI BANK FIRST FLOOR, VIDEOCON TOWER, E-1 JHANDEWALAN EXTENSION NEW DELHI-110055
413102000007573
IBKL0000413
110259037
000413
Rakesh Kumar Agarwal and Inder Singh Bhatia 28, KG Marg, New Delhi
No such defaults
Yes
No
Yes
Yes
Yes
No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE NO 60 OF 2010- BLOCK L
ALREADY BEEN OBTAINED
07-08-2010
II. LICENSE NO 38 OF 2011-BLOCK L
ALREADY BEEN OBTAINED
28-04-2011
III. LICENSE NO 47 OF 2011 FOR BLOCK L
ALREADY BEEN OBTAINED
27-05-2011
IV. LICENSE NO. 1210-1261 OF 2005 FOR BLOCK P, Q AND S
ALREADY BEEN OBTAINED
25-10-2006
V. RENEWAL APPLIED-LICENSE NO 60 OF 2010
APPLIED FOR BUT YET TO RECEIVE
26-11-2018
VI. RENEWAL APPLIED LICENSE NO 38 OF 2011-BLOCK L
APPLIED FOR BUT YET TO RECEIVE
23-05-2017
VII. RENEWAL APPLIED- LICENSE NO 47 OF 2011 FOR BLOCK L
APPLIED FOR BUT YET TO RECEIVE
10-01-2019
VIII. RENEWAL APPLIED-LICENSE NO. 1210-1261 OF 2005 FOR BLOCK P, Q AND S
APPLIED FOR BUT YET TO RECEIVE
05-12-2017
Yes
Yes
PARK TERRA, SEC 37D GURUGRAM
840305
456
0
373
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
35269.38
0
20987.44
Cost of the apartments
0
0
0
Cost of the infrastructure
0
0
0
Others costs
0
0
0
30900 Lakhs
9500 Lakhs
6500.00 Lakhs
4500.00 Lakhs
Yes
31-12-2012
31-10-2020
PARK SENTOSA, SECTOR 77 FARIDABAD
743720
420
0
159
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
22701.65
0
5630.20
Cost of the apartments
0
0
0
Cost of the infrastructure
0
0
0
Others costs
0
0
0
3600 Lakhs
10100 Lakhs
0 Lakhs
0 Lakhs
Yes
30-04-2013
30-04-2022
VISSIONAIRE VILLAS, SECTOR 70 GURUGRAM
56233
10
10
5
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
932.83
0
493.28
Cost of the apartments
0
0
0
Cost of the infrastructure
0
0
0
Others costs
0
0
0
1300 Lakhs
1000 Lakhs
0 Lakhs
0 Lakhs
Yes
30-04-2015
31-07-2020
PEDESTAL FLOORS SECTOR 70A GURUGRAM
303304
174
58
143
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
5550.87
0
2718.42
Cost of the apartments
0
0
0
Cost of the infrastructure
0
0
0
Others costs
0
0
0
10200 Lakhs
8000 Lakhs
0 Lakhs
0 Lakhs
Yes
30-04-2015
31-07-2020
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
LAMINATED WOODEN FLOORING
2
WALL FINISHING DETAILS
OBD, TEXTURE AND EXTERIOR GRADE EMULSION SUPERFINE.
3
KITCHEN DETAILS
BLACK GRANITE FOR FLOORING, CERAMIC 300*300
4
BATHROOM FITTINGS
CERAMIC 200*300, BLACK GRANITE, EWC WITH FLOOR MOUNTED- CALIBRE, WASHBASIN WITH WASTE COUPLING - CIRCLE
5
WOOD WORK ETC
NA
6
DOORS AND WINDOS FRAMES
MS HOLLOW SECTION AS/ DESIGN
7
GLASS WORK
NA
8
ELECTRIC FITTINGS
32 MM , 25 MM AND 20 MM DIA HEAVY CONDUIT, MODULAR SWITCHES , JUNCTION BOX, DISTRIBUTION BOARD.
9
CONDUCTING AND WIRING DETAILS
32 MM , 25 MM AND 20 MM DIA HEAVY CONDUIT
10
CUPBOARD DETAILS
NA
11
WATER STORAGE
NA
12
LIFT DETAILS
NA
13
EXTERNAL GLAZINGS
MS HOLLOW SECTION AS/ DESIGN
13.1
WINDOWS/GLAZINGS
UPVC DOORS AND WINDOWS WITH 5 MM CLEAR TOUGHED FLOAT GLASS.
14
DOORS
35 MM THE FLUSH DOOR BOTH SIDE COMMERCIAL WITH ENAMEL PAINTED FINISH.
14.1
MAIN DOORS
MOULDED WITH MESOMINE SKIN WITH HARD WOOD LEAPING.
14.2
INTERNAL DOORS
STAINLESS STEEL / SS FINISH(BRUSH FINISH) MORTICE LOCK FOR BEDROOM & BABY LOCK FOR TOILETS.
15
AIR CONDITIONING
NA
16
ELECTRICAL FITTINGS
32 MM , 25 MM AND 20 MM DIA HEAVY CONDUIT, MODULAR SWITCHES , JUNCTION BOX, DISTRIBUTION BOARD.
17
CNG PIPE LINE
NA
18
PROVISION OF WIFI AND BROADBAND FACILITY
NA
19
EXTERNAL FINISHING/COLOUR SCHEME
NA
20
INTERNAL FINISHING
NA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
NA
1 . 2
WALLS
NA
1 . 3
CEILING
NA
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
LAMINATED WOODEN FLOORING
2 . 2
WALLS
NA
2 . 3
CEILING
NA
2 . 4
MODULAR WARDROBES
NA
3 . MASTER TOILET
3 . 1
FLOOR
CERAMIC 200*300
3 . 2
WALLS
NA
3 . 3
CEILING
NA
3 . 4
COUNTERS
NA
3 . 5
SANITARY WARE/CP FITTINGS
NA
3 . 6
FITTING/FIXTURES
NA
4 . BED ROOMS
4 . 1
FLOOR
LAMINATED WOODEN FLOORING
4 . 2
WALLS
NA
4 . 3
CEILING
NA
4 . 4
WARDROBES
NA
5 . TOILET
5 . 1
FLOOR
CERAMIC 200*300
5 . 2
WALLS
NA
5 . 3
CEILING
NA
5 . 4
COUNTERS
NA
5 . 5
SANITARY WARE/CP FITTINGS
NA
5 . 6
FIXTURES
NA
6 . KITCHEN
6 . 1
FLOOR
BLACK GRANITE FOR FLOORING, CERAMIC 300*300- KAJARIA
6 . 2
WALLS
NA
6 . 3
CEILING
NA
6 . 4
COUNTERS
NA
6 . 5
FIXTURES
KITCHEN SINK DOUBLE BOWEL WITH DRAIN BOARD
6 . 6
KITCHEN APPLIANCES
KITCHEN SINK MIXER
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
NA
7 . 2
WALLS & CEILING
NA
7 . 3
TOILET
NA
7 . 4
BALCONY
NA
8 . SIT-OUTS
8 . 1
FLOOR
NA
8 . 2
WALLS & CEILING
NA
8 . 3
RAILINGS
NA
8 . 4
FIXTURES
NA
Sr. No.
Document Description
Date of Document Upload
View Document
1