8826141246 (Number Shared by Promoter in Public)
indiabulls_el_plot@indiabulls.com
http://www.indiabulls.com
XXXX010Q
U45201DL2005PLC139676
IB CITY
SECTOR - 26,26 A,33 & 34, VILLAGE RATHDHANA, SONIPAT, HARYANA
SONIPAT
SONIPAT
01306682892
8826141246 (Number Shared by Promoter in Public)
indiabulls_el_plot@indiabulls.com
ASHISH KAUSHIK
01306682892
9466522838 (Number Shared by Promoter in Public)
ashish.kaushik@indiabulls.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
661246
22-08-2017
281661
HDFC
HRERA Panchkula
2
661245
22-08-2017
1382003
HDFC
HRERA Panchkula
3
88342
26-10-2018
267000
HDFC
HRERA Panchkula
4
19352
03-12-2018
189000
AXIS
HRERA Panchkula
37.63 (Acre)
NA
0
99.309 (Acre)
70 OF 2009 DATED 24.11.2009
Yes
7124 Lakhs
1550 Lakhs
955 Lakhs
2232.5 Lakhs
2386 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
5.5
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
5.4918
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0.2677
6
GREEN BELTS
1.48
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
13
SHOPPING
3.49
14
AREA
20.92
15
EWS
0.50
Total
37.6495
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HUDA/ HSVP
No
WATER SUPPLY
HUDA/ HSVP
No
ELECTRICITY
UHBVN
Yes
SEWAGE DISPOSAL
HUDA/ HSVP
No
STORM WATER DRAINAGE
HUDA/ HSVP
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
250
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
205
YET TO BE PREPARED
3
STORM WATER DRAINAGE
225
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
575
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
75
YET TO BE PREPARED
6
STREET LIGHTING
0
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
235
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
311
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
15
MAINTENANCE
40
YET TO BE PREPARED
NA (date)
NA (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
PLOT Type PLOT
149.17
22
2
20
0
2
PLOT Type PLOT
149.58
21
0
21
0
3
PLOT Type PLOT
151.94
1
1
0
0
4
PLOT Type PLOT
153.39
82
24
58
0
5
PLOT Type PLOT
155.32
2
2
0
0
6
PLOT Type PLOT
161.46
4
1
3
0
7
PLOT Type PLOT
179.76
20
6
14
0
8
PLOT Type PLOT
241.71
1
1
0
0
9
PLOT Type PLOT
260.44
1
0
1
0
10
PLOT Type PLOT
481.15
5
0
5
0
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
0
0
N/A
N/A
N/A
01-12-2012
55
31-10-2019
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
01-12-2012
55
31-10-2019
ALL PLOT ARE DEMARCATED AND WILL BE HANDED OVER AFTER RECEIVING COMPLETION CERTIFICATE WITH IN THE PROJECTED TIMELINE
2
0
0
76
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
151
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2017
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
Shops
257
318
199
Plots
0
0
0
Particulars
Year-2018
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
Shops
50
142
150
Plots
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
235
Water Supply System
159
Sewerage treatment & garbage disposal
63
Electricity Supply System
565
Storm Water Drainage
219
Parks and Playgrounds
193
Clubhouse/community centres
0
Shopping area
0
Other
0
Gate Civil Mep Fencing
195
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2017
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
Water Supply System
0
0
0
Sewerage treatment & garbage disposal
0
0
0
Electricity Supply System
0
0
17.40
Storm Water Drainage
0
0
0
Parks and Playgrounds
0
0
0
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
0
0
0
Maintenance
6.40
6.40
6.40
Particulars
Year-2018
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
Water Supply System
0
0
85
Sewerage treatment & garbage disposal
0
0
0
Electricity Supply System
15
100
3
Storm Water Drainage
0
5
0
Parks and Playgrounds
0
0
0
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
0
0
0
Maintenance
6.4
7
7
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
159
ii. No. of Flats/ Apartments booked
39
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
670.17 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
260.22 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
394.97 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
14.98 Lakhs
vii. Amount invested in the project upto the date of application
0 Lakhs
Land cost (If any)
1550.25 Lakhs
Apartments
0 Lakhs
Infrastructure
1780.51 Lakhs
EDC/ Taxes Etc.
2386.30 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
1406.60 Lakhs
(a) In respect of existing allottees
252.799 Lakhs
(b) In respect of rest of the project
1153.80 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
216.57 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
250
235
II. WATER SUPPLY SYSTEM
205
159
III. STORM WATER DRAINAGE
225
219
IV. ELECTRICITY SUPPLY SYSTEM
575
565
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
75
63
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
311
151
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
235
193
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
0
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
40
0
Yes
Yes
STATE BANK OF INDIA, MITRADHAM CHS, PAREL T.T., BESIDE BMC BUILDING ,ELPHINSTONE ROAD, A.D. MARG, PAREL, MUMBAI- 400012
3705911834
SBIN0001884
400002064
001884
Vinay Dave
Yes
Yes
Yes
Yes
No
Yes
Yes
No
Yes
No
No
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. LICENCE
ALREADY BEEN OBTAINED
25-11-2009
II. ZONING PLAN
ALREADY BEEN OBTAINED
08-11-2011
III. ENVIRONMENT CLEARANCE
ALREADY BEEN OBTAINED
30-08-2012
IV. CTE
ALREADY BEEN OBTAINED
28-12-2012
V. HRERA RC
ALREADY BEEN OBTAINED
24-10-2017
Yes
Yes
TO FOLLOW HRERA PROVISIONS
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
N.A.
2
WALL FINISHING DETAILS
N.A.
3
KITCHEN DETAILS
N.A.
4
BATHROOM FITTINGS
N.A.
5
WOOD WORK ETC
N.A.
6
DOORS AND WINDOS FRAMES
N.A.
7
GLASS WORK
N.A.
8
ELECTRIC FITTINGS
N.A.
9
CONDUCTING AND WIRING DETAILS
N.A.
10
CUPBOARD DETAILS
N.A.
11
WATER STORAGE
N.A.
12
LIFT DETAILS
N.A.
13
EXTERNAL GLAZINGS
N.A.
13.1
WINDOWS/GLAZINGS
N.A.
14
DOORS
N.A.
14.1
MAIN DOORS
N.A.
14.2
INTERNAL DOORS
N.A.
15
AIR CONDITIONING
N.A.
16
ELECTRICAL FITTINGS
N.A.
17
CNG PIPE LINE
N.A.
18
PROVISION OF WIFI AND BROADBAND FACILITY
N.A.
19
EXTERNAL FINISHING/COLOUR SCHEME
N.A.
20
INTERNAL FINISHING
N.A.
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
N.A.
1 . 2
WALLS
N.A.
1 . 3
CEILING
N.A.
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
N.A.
2 . 2
WALLS
N.A.
2 . 3
CEILING
N.A.
2 . 4
MODULAR WARDROBES
N.A.
3 . MASTER TOILET
3 . 1
FLOOR
N.A.
3 . 2
WALLS
N.A.
3 . 3
CEILING
N.A.
3 . 4
COUNTERS
N.A.
3 . 5
SANITARY WARE/CP FITTINGS
N.A.
3 . 6
FITTING/FIXTURES
N.A.
4 . BED ROOMS
4 . 1
FLOOR
N.A.
4 . 2
WALLS
N.A.
4 . 3
CEILING
N.A.
4 . 4
WARDROBES
N.A.
5 . TOILET
5 . 1
FLOOR
N.A.
5 . 2
WALLS
N.A.
5 . 3
CEILING
N.A.
5 . 4
COUNTERS
N.A.
5 . 5
SANITARY WARE/CP FITTINGS
N.A.
5 . 6
FIXTURES
N.A.
6 . KITCHEN
6 . 1
FLOOR
N.A.
6 . 2
WALLS
N.A.
6 . 3
CEILING
N.A.
6 . 4
COUNTERS
N.A.
6 . 5
FIXTURES
N.A.
6 . 6
KITCHEN APPLIANCES
N.A.
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
N.A.
7 . 2
WALLS & CEILING
N.A.
7 . 3
TOILET
N.A.
7 . 4
BALCONY
N.A.
8 . SIT-OUTS
8 . 1
FLOOR
N.A.
8 . 2
WALLS & CEILING
N.A.
8 . 3
RAILINGS
N.A.
8 . 4
FIXTURES
N.A.
Sr. No.
Document Description
Date of Document Upload
View Document
1
NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT