A-71, FIEE COMPLEX, INDUSTRIAL AREA, PHASE-II, NEW DELHI - 110020
01294160401
9810855773 (Number Shared by Promoter in Public)
edeninfra@gmail.com
257
AAAAE2689J
MANSHA INDRAPRASTHA GREENS
VILLAGE - DODWA, SECTOR-1, TARAORI
NILOKHERI
KARNAL
8950017700 (Number Shared by Promoter in Public)
edeninfra@gmail.com
RAJ KAPOOR MALIK
8950017700 (Number Shared by Promoter in Public)
edenslf95@gmail.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
822211
12-09-2017
178425
PUNJAB AND SIND BANK
HRERA Panchkula
8.818 (Acre)
NA
0
8.818 (Acre)
74 of 2017 dated 08/09/2017 (Valid up to 07/09/2022)
Yes
1602.49 Lakhs
324.73 Lakhs
0 Lakhs
616.49 Lakhs
661.27 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
4.61
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
2.441
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0.665
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.882
12
ANY OTHER
0.220
Total
8.818
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HUDA
No
WATER SUPPLY
HUDA
No
ELECTRICITY
UHBVN
Yes
SEWAGE DISPOSAL
STATE POLLUTION CONTROL BOARD OF HARYANA
Yes
STORM WATER DRAINAGE
HUDA
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
162.15
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
134.24
YET TO BE PREPARED
3
STORM WATER DRAINAGE
69.06
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
39.01
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
86.52
YET TO BE PREPARED
6
STREET LIGHTING
33.85
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
4.16
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
87.50
YET TO BE PREPARED
08-09-2017 (date)
NA (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
PLOT Type A
109.80
11
3
8
0
2
PLOT Type B
118.75
48
0
48
0
3
PLOT Type C
125.31
54
18
36
0
4
PLOT Type D
108.31
46
14
32
0
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
0
0
N/A
N/A
N/A
05-10-2017
23
31-12-2020
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
35
31/12/2020
05-10-2017
23
31-12-2020
PROJECT SHALL BE COMPLETED BY 31/12/2020
0
0
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
159
Plots
ii. No. of Flats/ Apartments booked
35
Plots
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
476.31 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
231.29 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
245.02 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
245.02 Lakhs
vii. Amount invested in the project upto the date of application
550.25 Lakhs
Land cost (If any)
324.73 Lakhs
Apartments
0 Lakhs
Infrastructure
139.74 Lakhs
EDC/ Taxes Etc.
85.78 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
1052.24 Lakhs
(a) In respect of existing allottees
242.35 Lakhs
(b) In respect of rest of the project
809.89 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
162.15
70.86
II. WATER SUPPLY SYSTEM
134.24
10.31
III. STORM WATER DRAINAGE
69.06
6.59
IV. ELECTRICITY SUPPLY SYSTEM
39.01
10
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
86.52
15.95
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
4.16
0.36
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
0
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
121.35
25.67
Yes
No
PUNJAB AND SIND BANK, GREEN PARK, NEW DELHI
00401100041370
PSIB0000040
110023036
000040
1. Naresh Kumar Malik , Add:-H.No.486, Sector-8, Faridabad
2. Ajay Madan Add: - C-6/51, SDA, Hauj Khas , South West Delhi
Yes
Yes
Yes
No
No
No
No
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Statutory Approvals
Statutory Approvals Status
Date
I. SERVICE ESTIMATE PLAN
ALREADY BEEN OBTAINED
05-03-2019
II. NOC FRO POLLUTION CONTROL BOARD
ALREADY BEEN OBTAINED
25-06-2018
III. APPROVAL FOR ELECTRIFICATION LAYOUT PLAN
ALREADY BEEN OBTAINED
01-05-2018
IV. ZONING PLAN APPROVED
ALREADY BEEN OBTAINED
07-11-2017
V. DEMARCATION APPROVED
ALREADY BEEN OBTAINED
NA
VI. NOC FROM FOREST DEPARTMENT
APPLIED FOR BUT YET TO RECEIVE
NA
Yes
Yes
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT