MANSHA CITY
NUH ROAD, SECTOR-9 PALWAL
PALWAL
PALWAL
9215557253 (Number Shared by Promoter in Public)
MALIKASSOCIATES@GMAIL.COM
SURJIT SINGH
9215557253 (Number Shared by Promoter in Public)
MALIKASSOCIATES@GMAIL.COM
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
304776
17-07-2017
266500
INDIAN OVERSEAS BANK
HRERA Panchkula
8.76875 (Acre)
NA
0
8.76875 (Acre)
13 of 2017(26-04-2017)
Yes
2120.55 Lakhs
692.78 Lakhs
0 Lakhs
611.91 Lakhs
815.86 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
4.741
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
2.23415
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0.661
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.8736
12
ANY OTHER
0.259
Total
8.76875
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HUDA AUTHORITY
No
WATER SUPPLY
HUDA AUTHORITY
No
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
STATE POLLUTION CONTROL BOARD OF HARYANA
Yes
STORM WATER DRAINAGE
HUDA AUTHORITY
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
111.3
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
148.9
YET TO BE PREPARED
3
STORM WATER DRAINAGE
40.2
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
58.22
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
107.3
YET TO BE PREPARED
6
STREET LIGHTING
16.70
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
16.10
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
113.19
YET TO BE PREPARED
26-04-2017 (date)
NA (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
PLOT Type A
107.2
7
7
0
0
2
PLOT Type B
99.98
9
9
0
0
3
PLOT Type B1
90.00
9
9
0
0
4
PLOT Type C
105.46
7
7
0
0
5
PLOT Type C1
93.76
6
6
0
0
6
PLOT Type D
86.8
20
20
0
0
7
PLOT Type E1
120.0
8
8
0
0
8
PLOT Type E
126.0
13
0
13
0
9
PLOT Type F
105.6
64
32
32
0
10
PLOT Type G
82.8
17
0
17
0
11
PLOT Type G1
98.8
5
0
5
0
12
PLOT Type H
99.0
11
0
11
0
13
PLOT Type H1
89.7
15
0
15
0
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
0
0
N/A
N/A
N/A
26-04-2017
70
31-12-2019
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
98
DECEMBER 2019
26-04-2017
70
31-12-2019
PROJECT SHALL BE COMPLETED BY 31 DECEMBER 2019
0
0
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
4.5
5.04
3.32
Water Supply System
0
17.09
26.20
10.66
Sewerage treatment & garbage disposal
0
11.2
20.6
8.6
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
5.6
5.35
1.67
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0.63
1.81
1.74
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
191
PLOTS
ii. No. of Flats/ Apartments booked
98
PLOTS
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
1231.99 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
1032.63 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
199.36 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
199.36 Lakhs
vii. Amount invested in the project upto the date of application
1256.57 Lakhs
Land cost (If any)
692.78 Lakhs
Apartments
0 Lakhs
Infrastructure
476.11 Lakhs
EDC/ Taxes Etc.
87.68 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
863.98 Lakhs
(a) In respect of existing allottees
443.30 Lakhs
(b) In respect of rest of the project
420.68 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
111.3
96.04
II. WATER SUPPLY SYSTEM
148.9
91.25
III. STORM WATER DRAINAGE
40.2
25.76
IV. ELECTRICITY SUPPLY SYSTEM
58.22
58.22
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
107.3
65.6
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
16.10
16.10
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
0
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
129.89
123.14
Yes
Yes
STATE BANK OF INDIA, SECTOR-9 FARIDABAD
36903574338
SBIN0050582
110002756
050582
Mr. Naresh Kumar Malik, R/o H.No. 486, Sector-8 Faridabad
Mr. Baljeet Singh, R/o H.No. 1024, Sector-9 Faridabad
Yes
Yes
Yes
No
No
No
No
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Statutory Approvals
Statutory Approvals Status
Date
I. ZONING PLAN
ALREADY BEEN OBTAINED
16-06-2017
II. DEMARCATION PLAN
ALREADY BEEN OBTAINED
17-05-2017
III. APPROVAL FOR ELECTRIFICATION LAYOUT PLAN
ALREADY BEEN OBTAINED
23-11-2017
IV. NOC FROM POLLUTION CONTROL BOARD
ALREADY BEEN OBTAINED
17-02-2018
V. SERVICE ESTIMATE PLAN
ALREADY BEEN OBTAINED
27-10-2017
VI. NOC FROM FOREST DEPARTMENT
APPLIED FOR BUT YET TO RECEIVE
NA
Yes
Yes
MANSHA ROYAL FARMS, VILLAGE CHANDHUT, PALWAL
18210
18
93
11
81
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
570.73
570.73
468.83
Cost of the apartments
0
0
0
Cost of the infrastructure
324.63
324.63
244.51
Others costs
479.30
479.30
457.52
525.29 Lakhs
298.58 Lakhs
500.00 Lakhs
366.12 Lakhs
No
30-04-2017
30-04-2017
MANSHA FLOORS, SECTOR-6 PALWAL
100800
84
0
78
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
1412.18
1412.18
1184.48
Cost of the apartments
1079.59
1079.56
947.68
Cost of the infrastructure
0
0
0
Others costs
829.87
829.87
734.08
1958.56 Lakhs
289 Lakhs
0 Lakhs
0 Lakhs
No
31-03-2016
31-03-2016
MANSHA LUXURY FLOORS, FARIDABAD
10312
100
0
100
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
1839.88
1839.88
1790.44
Cost of the apartments
0
0
0
Cost of the infrastructure
1513.21
1513.21
1513.59
Others costs
1598.98
1598.98
1549.12
3094.44 Lakhs
200.26 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2017
31-12-2017
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT