HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-452-2019
Submission Date : 10-09-2019 04:08:12 AM
Applicant Type : Company
Project Type: ONGOING




TDI INFRASTRUCTURE LIMITED
10 SHAHEED BHAGAT SINGH MARG NEW DELHI
01149133333
9654728375 (Number Shared by Promoter in Public)
Op.dhingra@tdiinfracorp.com
http://www.tdigroup.net
XXXX799P
U70102DL1997PLC085551
 
 


 
 


 
 


 
 


 
 


 
 







ESPANIA- 2
SECTOR 19
SONIPAT
SONIPAT
9654728375 (Number Shared by Promoter in Public)
op.dhingra@tdiinfracorp.com
UMESH KUMAR SHARMA
9215310703 (Number Shared by Promoter in Public)
op.dhingra@tdiinfracorp.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
110159609-04-2019695000INDIAN BANK NEW DELHIHRERA Panchkula







10.8375 (Acre)
1.75
174.69
10.8375 (Acre)
70 of 2012
Yes







23407 Lakhs
645 Lakhs
9991 Lakhs
4654 Lakhs
8117 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS9329.73
3CONSTRUCTION OF ROADS11501
4PAVEMENTS10656
5PARKS AND PLAYGROUNDS0
6GREEN BELTS5830
7VEHICLE PARKINGS9709
8ELECTRICITY SUB-STATION545
9CLUB HOUSE615
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
13COMMERCIAL189
14SCHOOL1144.13
Total49518.86




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHUDANo
WATER SUPPLYHUDANo
ELECTRICITYUHBVNYes
SEWAGE DISPOSALHUDANo
STORM WATER DRAINAGEHUDANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS244AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM86AS PER PROJECT REPORT
3STORM WATER DRAINAGE450AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM666AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL75AS PER PROJECT REPORT
6STREET LIGHTING0AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING415AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS30AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE153AS PER PROJECT REPORT
10SHOPPING AREA20AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM35AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER0AS PER PROJECT REPORT
15RESIDENTIAL BUILDING9991AS PER PROJECT REPORT
16LIFT582AS PER PROJECT REPORT
17BASEMENT1551AS PER PROJECT REPORT
18EWS247AS PER PROJECT REPORT


12-12-2013 (date)
NA (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type 2BHK (HIGHRISE)63.06414814443
2APARTMENT/SHOPS/OTHER BUILDINGS Type 3BHK (HIGHRISE)82.1915014553
3APARTMENT/SHOPS/OTHER BUILDINGS Type 3BHK (LOWRISE)76.12205199621
4APARTMENT/SHOPS/OTHER BUILDINGS Type 3BHK (LOWRISE)78.12155153216






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
0WE HAVE CONSTRUCTED ALL TOWERS OF THE BOOKED/ SOLD APARTMENTS IN FOLDER C APPROX 95%


15-06-2013
30-06-2017
30-06-2019
01-07-2019
95
31-10-2020
REP-1 PART-C-X ATTACHED
ANNEXURE C


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT0NA
01-07-2019
95
31-10-2020
REP-1 PART-C-X ATTACHED
ANNEXURE C


435
42
700
899
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments00150150
Shops0000
Plots0000

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments100100560
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements00280
Water Supply System0000
Sewerage treatment & garbage disposal001010
Electricity Supply System005050
Storm Water Drainage0060
Parks and Playgrounds0055
Clubhouse/community centres003015
Shopping area0000
Other0000
lifts100
Boundary Wall4
Security Fire Fighting4
Basement1011
EWS44
Scurrility Fire Fighting4
Lifts80

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System2535290
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Renewal Energy System35












Particulars Remarks, if any
i. No. of Flats/Apartments constructed658
ii. No. of Flats/ Apartments booked649
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter22400 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter19766 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter2643 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter2643 LakhsAs on 31.03.2019
vii. Amount invested in the project upto the date of application0 Lakhs
Land cost (If any)645 Lakhs
Apartments9874 Lakhs
Infrastructure4654 Lakhs
EDC/ Taxes Etc.1358 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession860 Lakhs
(a) In respect of existing allottees2643 Lakhs
(b) In respect of rest of the project2195 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS00
II. WATER SUPPLY SYSTEM00
III. STORM WATER DRAINAGE00
IV. ELECTRICITY SUPPLY SYSTEM00
V. SEWAGE TREATMENT & GARBAGE DISPOSAL00
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.00
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM00
XVII. OTHER FACILITIES AS PER PROJECT REPORT00









Yes
Yes
INDIAN OVERSEAS BANK RAJIV CIRCLE NEW DELHI
120502000000203
IOBA0001205
110020028
1205
VED PRAKSH R/O C 116 GHANTA GHAR HARI NAGAR NEW DELHI
YES ATTACHED











No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE ALREADY BEEN OBTAINEDNA
II. ENVIRONMENT CLEARANCE ALREADY BEEN OBTAINEDNA








Yes


Yes















SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED /WOODEN FLOORING/ANTI SKIED TILES
2WALL FINISHING DETAILSOBD WITH WALL PUTTY
3KITCHEN DETAILSSINK WITH MIXTURE AND GRANITE/ MARBLE COUNTER
4BATHROOM FITTINGSEWC WITH CISTERN WASH BASHING AND SHOWER
5WOOD WORK ETCDOOR AND WINDOW
6DOORS AND WINDOS FRAMESWOODEN
7GLASS WORK4/5 MM FLOAT GLASS
8ELECTRIC FITTINGSISI MARK
9CONDUCTING AND WIRING DETAILSISI MARK
10CUPBOARD DETAILSNO
11WATER STORAGERCC OVER HEAD TANK
12LIFT DETAILSJHONSHAN MAKE
13EXTERNAL GLAZINGSWOODEN
13.1WINDOWS/GLAZINGSWOODEN
14DOORSSKIN MOLDED
14.1MAIN DOORSLAMINATED /SKIN MOLDED
14.2INTERNAL DOORSSKIN MOLDED
15AIR CONDITIONINGNO
16ELECTRICAL FITTINGSISI MARK
17CNG PIPE LINENO
18PROVISION OF WIFI AND BROADBAND FACILITYYES
19EXTERNAL FINISHING/COLOUR SCHEMEBERGER TEXTURE PAINT
20INTERNAL FINISHINGOBD ENAMEL PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSOBD PAINT
1 . 3 CEILINGOBD PAINT
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN FLOORING
2 . 2 WALLSOBD PAINT
2 . 3 CEILINGOBD PAINT
2 . 4 MODULAR WARDROBESNO
3 . MASTER TOILET
3 . 1 FLOORANTI SKIED TILES
3 . 2 WALLSGLAZED WALL TILES
3 . 3 CEILINGFALL CELINA
3 . 4 COUNTERSNO
3 . 5 SANITARY WARE/CP FITTINGSHINDWARE MAKE
3 . 6 FITTING/FIXTURESC. P. (HINDWARE MAKE )
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES
4 . 2 WALLSOBD PAINT
4 . 3 CEILINGOBD PAINT
4 . 4 WARDROBESNO
5 . TOILET
5 . 1 FLOORANTI SKIED TILES
5 . 2 WALLSGLAZED WALL TILES
5 . 3 CEILINGFALL CELINA
5 . 4 COUNTERSNO
5 . 5 SANITARY WARE/CP FITTINGSHINDWARE MAKE
5 . 6 FIXTURESC. P. (HINDWARE MAKE )
6 . KITCHEN
6 . 1 FLOORANTI SKIED VITRIFIED TILES
6 . 2 WALLSGLAZED WALL TILES/ OBD
6 . 3 CEILINGOBD
6 . 4 COUNTERSGRANITE/ MARBLE
6 . 5 FIXTURESC. P. (HINDWARE MAKE) AND SS SINK
6 . 6 KITCHEN APPLIANCESNO
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNO
7 . 2 WALLS & CEILINGNO
7 . 3 TOILETNO
7 . 4 BALCONYNO
8 . SIT-OUTS
8 . 1 FLOORANTI SKIED TILES
8 . 2 WALLS & CEILINGOBD/ TEXTURE PAINT
8 . 3 RAILINGSMS RAILING/BALUSTERS
8 . 4 FIXTURESBALCONY LIGHT












Sr. No.Document DescriptionDate of Document UploadView Document
1CASH FLOW STATEMENT OF THE PROPOSED PROJECT18-07-2019 View Document
2IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN17-07-2019 View Document
3DEMARCATION PLAN17-07-2019 View Document
4DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD17-07-2019 View Document
5A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS17-07-2019 View Document
6DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.18-07-2019 View Document
7SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN17-07-2019 View Document
8COPY OF LICENSE ALONG WITH SCHEDULE OF LAND17-07-2019 View Document
9ZONING PLAN17-07-2019 View Document
10IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN17-07-2019 View Document
11CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT18-07-2019 View Document
12NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT18-07-2019 View Document