HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-446-2019
Submission Date : 30-03-2019 02:46:39 AM
Applicant Type : Company
Project Type: ONGOING




M/S. OMAXE LTD.
SHOP NO. 19-B, FIRST FLOOR, OMAXE CELEBRATION MALL, SOHNA ROAD, GURGAON-122001, HARYANA
01141896680
9876911201 (Number Shared by Promoter in Public)
haryana_rera@omaxe.com
http://www.omaxe.com
XXXX171H
L74899DL198PLC035389
 
 


 
 


 
 


 
 


 
 


 
 


 
 







PROJECT AREA 5.6125 ACRES AFFORDABLE RESIDENTIAL PLOTTED COLONY
VILLAGE MAINA, SUNARI KALAN, SUNARI KHURD, SECTOR-22D, DISTRICT ROHTAK, HARYANA
ROHTAK
ROHTAK
9876911201 (Number Shared by Promoter in Public)
haryana_rera@omaxe.com
SUMIT MITTAL
9876911201 (Number Shared by Promoter in Public)
haryana_rera@omaxe.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
13381329-07-2017114000AXIS BANK LTDHRERA Panchkula







5.6125 (Acre)
0
0
5.6125 (Acre)
27 of 2017
Yes







1754.59 Lakhs
735.00 Lakhs
0 Lakhs
451.00 Lakhs
568.59 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD2.89271
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS1.71479
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0
6GREEN BELTS0.4400
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0.565
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total5.6125




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHARYANA URBAN DEVELOPMENT AUTHORITYNo
WATER SUPPLYHARYANA URBAN DEVELOPMENT AUTHORITYNo
ELECTRICITYHARYANA URBAN DEVELOPMENT AUTHORITYNo
SEWAGE DISPOSALHARYANA URBAN DEVELOPMENT AUTHORITYNo
STORM WATER DRAINAGEHARYANA URBAN DEVELOPMENT AUTHORITYNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS97.85YET TO BE PREPARED
2WATER SUPPLY SYSTEM77.61YET TO BE PREPARED
3STORM WATER DRAINAGE46.13YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM56.64YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL81.8YET TO BE PREPARED
6STREET LIGHTING0YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS14.76YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


NA (date)
NA (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1PLOT Type PLOT SIZE 1137.788800
2PLOT Type PLOT SIZE 2128100100
3PLOT Type PLOT SIZE 3136.958350
4PLOT Type PLOT SIZE 484.57433410
5PLOT Type PLOT SIZE 5916600
6PLOT Type PLOT SIZE 666.669090






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
00


N/A
N/A
N/A
01-07-2017
88
31-12-2019


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
01-07-2017
88
31-12-2019


0
0
0
0
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements026.612017
Water Supply System003740.61
Sewerage treatment & garbage disposal6.310040
Electricity Supply System002025
Storm Water Drainage015.310.410
Parks and Playgrounds00104.76
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal12
Electricity Supply System11.64
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0












Particulars Remarks, if any
i. No. of Flats/Apartments constructed115
ii. No. of Flats/ Apartments booked50
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter658 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter135 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter460 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter63 Lakhs
vii. Amount invested in the project upto the date of application0 Lakhs
Land cost (If any)727.87 Lakhs
Apartments0 Lakhs
Infrastructure239.17 Lakhs
EDC/ Taxes Etc.568.59 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession218.96 Lakhs
(a) In respect of existing allottees0 Lakhs
(b) In respect of rest of the project0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS97.8534.24
II. WATER SUPPLY SYSTEM77.610
III. STORM WATER DRAINAGE46.1320.42
IV. ELECTRICITY SUPPLY SYSTEM56.640
V. SEWAGE TREATMENT & GARBAGE DISPOSAL81.823.49
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.14.760
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM00
XVII. OTHER FACILITIES AS PER PROJECT REPORT00









Yes
Yes
AXIS BANK LIMITED, D-81, MALVIYA NAGAR, NEW DELHI-110017
917020074061582
UTIB0000206
110211024
206
1. Ms. Sulekha Mandahar 2. Mr. Rajesh Kumar Kushwaha 3. Ms.Vijaya laxmi Purohit 4. Mr. Vinit Goyal Add.:Omaxe House , L.S.C. BUILDING NO. 7, KALKA JI , NEW DELHI - 110019
Attached











Yes
No
No
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. GRANT OF LICENCE. LICENCE NO. 27 OF 2017 ALREADY BEEN OBTAINEDNA








Yes


Yes


Gist of the Agreement for Sale, Haryana The model agreement for sale as provided under HRERA rules, 2017 contains detailed information, procedure, events and consequences about: The promoter its competency to enter into agreement with allottee, land owners, project land and the sale deeds vide which the land was procured including details of requisite sanctions/approvals obtained from the concerned competent authorities including RERA, required for opening/launching of project for sale. The nature of the project i.e. residential/commercial/industrial/IT/any other including the details of cost, taxes, payment plan, specifications, area, amenities, appurtenances, time of completion etc. of unit being allotted under the agreement. Any discount to be provided on early payment by the allottee as per agreed terms and the authority of promoter and procedure about the change/modification in the existing plans, designs, specifications, amenities etc. The rights and obligations of allottee with respect to the allotted unit including cancellation, payment and manner of outstanding dues. The procedure regarding assignment of allotment rights. Time and procedure of possession of the allotted unit and consequences in case of failure of take over possession by the allottee. Compensation to the allottee by the promoter in case of default/defect on its part including delay in handing over possession. Events of default by the promoter and the allottee including delay or failure to make payment of due intsallments and consequences thereof.







AFFORDABLE PLOTTED COLONY, AREA MEASURING 8.46875 ACRES, SECTOR – 22D, ROHTAK, HARYANA.
8.46875
0
167
0
80
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
1538.2201212.85
Cost of the apartments000
Cost of the infrastructure000
Others costs000


320 Lakhs
743 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2019
31-12-2019




AFFORDABLE PLOTTED COLONY, AREA MEASURING 14.80625 ACRES, SECTOR – 22D, ROHTAK, HARYANA.
14.80625
0
302
0
109
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
2689.0302110.32
Cost of the apartments000
Cost of the infrastructure000
Others costs000


127 Lakhs
443 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2019
31-12-2019




COMMERCIAL SITE 1.07 ACRES IN PLOTTED COLONY 59.505, IN SECTOR- 15, BAHADURGARH, HARYANA.
1.07
45
11
37
11
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
7810627.01
Cost of the apartments000
Cost of the infrastructure000
Others costs000


1147 Lakhs
302 Lakhs
0 Lakhs
0 Lakhs
No
28-11-2017
30-12-2019




COMMERCIAL SITE 2.80 ACRES IN PLOTTED COLONY 88.407, IN SECTOR- 3,3A & 14, BAHADURGARH, HARYANA.
2.80
237
0
205
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
250101742.77
Cost of the apartments000
Cost of the infrastructure000
Others costs000


2703 Lakhs
3959 Lakhs
0 Lakhs
0 Lakhs
No
30-11-2018
31-12-2019










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1CASH FLOW STATEMENT OF THE PROPOSED PROJECT27-03-2019 View Document
2SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN28-03-2019 View Document
3NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT27-03-2019 View Document
4ZONING PLAN27-03-2019 View Document
5DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.28-03-2019 View Document
6A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS28-03-2019 View Document
7IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN27-03-2019 View Document
8COPY OF LICENSE ALONG WITH SCHEDULE OF LAND27-03-2019 View Document
9CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT27-03-2019 View Document
10DEMARCATION PLAN27-03-2019 View Document
11IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN28-03-2019 View Document
12DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD28-03-2019 View Document
13APPROVED PLANS OF BOOTHS ON COMMERCIAL PLOT28-01-2021 ------
14APPROVED PLANS OF BOOTHS ON COMMERCIAL PLOT(PIC 1)28-01-2021 ------
15APPROVED PLANS OF BOOTHS ON COMMERCIAL PLOT(PIC 2)28-01-2021 ------
16APPROVED PLANS OF BOOTHS ON COMMERCIAL PLOT(PIC 3)28-01-2021 ------












Sr. No.Document DescriptionDate of Document UploadView Document
1 CERTIFICATE OF EXTENSION 08-08-2022 View Document