9910107920 (Number Shared by Promoter in Public)
crm@rof.co.in
https://www.rof.co.in
XXXX603L
U55101DL1999PTC098037
ROF AALAYAS PHASE II
SECTOR-102, GURUGRAM
GURGAON
GURUGRAM
01244399399
9560890400 (Number Shared by Promoter in Public)
crm@rof.co.in
MUKESH KUMAR
01244399399
9560890400 (Number Shared by Promoter in Public)
info@rof.co.in
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
21941
03-04-2019
400000
HDFC BANK LTD.
HRERA Gurugram
2
166084
20-05-2019
401518
OBC
HRERA Gurugram
3
166083
20-05-2019
515461
OBC
HRERA Gurugram
4.1125 (Acre)
9.9224 Acre
9.9217
4.1125 (Acre)
82 of 2018 (05-12-2023)
Yes
12141.535 Lakhs
2630 Lakhs
7000 Lakhs
1500 Lakhs
697 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
16643
3
CONSTRUCTION OF ROADS
3324
4
PAVEMENTS
7312
5
PARKS AND PLAYGROUNDS
2519
6
GREEN BELTS
608
7
VEHICLE PARKINGS
6135
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
70
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
38
Total
36649
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HUDA, GURUGRAM
Yes
WATER SUPPLY
GURUGRAM METROPOLITAN DEVELOPMENT AUTHORITY
Yes
ELECTRICITY
DAKSHIN HARYANA BIJLI VITRAN NIGAM
Yes
SEWAGE DISPOSAL
GURUGRAM METROPOLITAN DEVELOPMENT AUTHORITY
Yes
STORM WATER DRAINAGE
GURUGRAM METROPOLITAN DEVELOPMENT AUTHORITY
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
36.58
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
87.52
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
22.26
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
10.91
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
60.91
AS PER PROJECT REPORT
6
STREET LIGHTING
9.46
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
12.24
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
0
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
AS PER PROJECT REPORT
10
SHOPPING AREA
0
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
0
AS PER PROJECT REPORT
12
SCHOOL
0
AS PER PROJECT REPORT
13
HOSPITAL/DISPENSARY
0
AS PER PROJECT REPORT
14
ANY OTHER
40.08
AS PER PROJECT REPORT
05-04-2019 (date)
05-04-2019 (date)
05-07-2019
05-07-2023
Plot Area(In Square Meter)
Number of plots in the project
0
0
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
35677.130
595
6
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
300.24
569.06
Shops
0
0
0
Plots
0
0
0
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
814.17
2676.93
1007.33
1019.21
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
1019.21
919.34
618.72
358.44
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
254.18
270.86
180.57
113.03
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
34.68
10.45
Shops
0
0
Plots
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
Water Supply System
4.37
4.37
4.37
Sewerage treatment & garbage disposal
0
0
0
Electricity Supply System
0
0
0
Storm Water Drainage
0
0
0
Parks and Playgrounds
0
0
0
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
0
0
0
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
0
Water Supply System
4.37
8.75
8.75
8.75
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Fire Fighting
1.22
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
9.14
9.14
Water Supply System
8.75
8.75
8.75
8.75
Sewerage treatment & garbage disposal
0
12.18
12.18
12.18
Electricity Supply System
0
0
0
2.72
Storm Water Drainage
0
0
5.56
5.56
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
1.22
1.22
Fire Fighting and security
1.22
Street Light
2.83
Fire Fighting
1.22
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
9.14
9.14
Water Supply System
4.37
4.37
Sewerage treatment & garbage disposal
12.18
12.18
Electricity Supply System
2.72
5.45
Storm Water Drainage
5.56
5.56
Parks and Playgrounds
0
0
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
Street Light
3.31
3.31
Fire Fighting
3.06
UGT
13.01
Fire Fighting and security
3.06
STP
27.07
Yes
No
ORIENTAL BANK OF COMMERCE AT OVERSEAS BRANCH, UDYOG VIHAR, PHASE-V, GURUGRAM
12371131004225
ORBC0100987
110022188
100987
Pradeep Sharma
B. No. 80, 1st Floor, Sector-44, Gurugram-122003, HR
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. ASSURANCE FOR STP TREATED WATER
ALREADY BEEN OBTAINED
28-12-2018
II. ARAVALI NOC
ALREADY BEEN OBTAINED
21-02-2019
III. LETTER OF INTENT
ALREADY BEEN OBTAINED
26-10-2018
IV. DEMARCATION PLAN
ALREADY BEEN OBTAINED
19-12-2018
V. LICENSE
ALREADY BEEN OBTAINED
06-12-2018
VI. ZONING PLAN
ALREADY BEEN OBTAINED
07-12-2018
VII. HEIGHT CLEARANCE
ALREADY BEEN OBTAINED
06-03-2019
VIII. ASSURANCE OF DRINKING WATER SUPPLY
ALREADY BEEN OBTAINED
17-12-2018
IX. ENVIRONMENTAL CLEARANCE
APPLIED FOR BUT YET TO RECEIVE
19-03-2019
Yes
Yes
Affordable Group Housing Colony
ROF AALAYAS AT SECTOR-102, VILLAGE- DHANKOT, GURUGRAM, HARYANA
5.0
947
0
920
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
12800.00
16000.00
15730.00
Cost of the apartments
6705.92
8382.40
8242.00
Cost of the infrastructure
4471.04
5588.80
5496.00
Others costs
1620.48
2025.60
1992.00
16137.75 Lakhs
2265.13 Lakhs
2500.00 Lakhs
1700.00 Lakhs
No
26-03-2019
26-03-2019
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
CERAMIC/ VITRIFIED TILES
2
WALL FINISHING DETAILS
GYPSUM PLASTER
3
KITCHEN DETAILS
CERAMIC TILES, PAINT, GREEN MARBLE, SINK
4
BATHROOM FITTINGS
PART CERAMIC TILES, PART PAINT, FALSE CEILING
5
WOOD WORK ETC
DOORS
6
DOORS AND WINDOS FRAMES
BALCONY DOORS, WINDOWS- ALUMINIUM FRAMING WITH GLASS