HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-420-2019
Submission Date : 23-02-2019 01:51:39 AM
Applicant Type : Company
Project Type: ONGOING




ANSAL PROPERTIES & INFRASTRUCTURE LIMITED
115, ANSAL BHAWAN, 16, KG MARG, NEW DELHI-110001
01123352550
9855300506 (Number Shared by Promoter in Public)
ansalapireraharyana@gmail.com
http://ansalapi.com
XXXX006D
L45101DL1967PLC004759
 
 


 
 


 
 







GREEN ESCAPE-ZONE-04 (TOWER-14-15-16-17)
VILLAGE AKBARPUR BAROTA, JHATERI ROAD, SECTOR-35
RAI ST
SONIPAT
9996882414 (Number Shared by Promoter in Public)
asheem@ansalapi.com
ASHEEM SHARMA
9996882414 (Number Shared by Promoter in Public)
asheem@ansalapi.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
17442031-07-2017224005.20HDFC BANK LIMITED. HRERA Panchkula







1.613 (Acre)
1.75
1.75
30.65 (Acre)
License No. 1125- 1126 of 2006 dated 02.09.2006 is valid upto 01.09.2019.
Yes







7875.75 Lakhs
1161.26 Lakhs
4019.58 Lakhs
195.73 Lakhs
2499.18 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0.00
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0.389
3CONSTRUCTION OF ROADS 0.307
4PAVEMENTS 0.00
5PARKS AND PLAYGROUNDS 0.850
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0.068
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
Total1.614




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSPWD B&RYes
WATER SUPPLYHSVPYes
ELECTRICITYUHBVNLYes
SEWAGE DISPOSALHSVPYes
STORM WATER DRAINAGEHSVPYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS45.27SUBMITTED TO TOWN & COUNTRY PLANNING
2WATER SUPPLY SYSTEM72.78SUBMITTED TO TOWN & COUNTRY PLANNING
3STORM WATER DRAINAGE21.32SUBMITTED TO TOWN & COUNTRY PLANNING
4ELECTRICITY SUPPLY SYSTEM0.00AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL44.30SUBMITTED TO TOWN & COUNTRY PLANNING
6STREET LIGHTING5.87AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0.00YET TO BE PREPARED
8PLAYGROUNDS AND PARKS6.20SUBMITTED TO TOWN & COUNTRY PLANNING
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


NA (date)
31-03-2014 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartments Total number of plots/apartments in the project Total size of the plots/carpet area of the apartments Plots/apartments booked/ sold upto the date of application Yet to be sold/ booked No. of towers to be/ being constructed for booked apartments
1 APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER-14 92.65 49 4539.85 45 4 1
2 APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER-15 92.65 53 4910.45 50 3 1
3 APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER-16 92.65 49 4539.85 47 2 1
4 APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER-17 60.00 53 3180 51 2 1
Total20417170.15193114






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
TOWERS-1445UNDER CONSTRUCTION.
TOWER-1550UNDER CONSTRUCTION.
TOWER-1647UNDER CONSTRUCTION.
TOWER-1751UNDER CONSTRUCTION.


01-02-2015
31-08-2018
31-12-2022
01-11-2016
0
31-12-2022
ANNEXURE C
ANNEXURE-C ADDED.


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
01-11-2016
0
31-12-2022
YES.
ANNEXURE-ADDED.


0
0
158
52
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments281.37281.37281.37281.37
Shops0000
Plots0000

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments281.37281.37281.37281.37
Shops0000
Plots0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments281.37281.37281.37281.37
Shops0000
Plots0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments281.37281.3780.39
Shops000
Plots000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3.173.173.173.17
Water Supply System5.095.095.095.09
Sewerage treatment & garbage disposal3.103.103.103.10
Electricity Supply System0000
Storm Water Drainage1.491.491.491.49
Parks and Playgrounds0.430.430.430.43
Clubhouse/community centres0000
Shopping area0000
Other0.410.410.410.41

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3.173.173.173.17
Water Supply System5.095.095.095.09
Sewerage treatment & garbage disposal3.103.103.103.10
Electricity Supply System0000
Storm Water Drainage1.491.491.491.49
Parks and Playgrounds0.430.430.430.43
Clubhouse/community centres0000
Shopping area0000
Other0.410.410.410.41

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3.173.173.173.17
Water Supply System5.095.095.095.09
Sewerage treatment & garbage disposal3.103.103.103.10
Electricity Supply System0000
Storm Water Drainage1.491.491.491.49
Parks and Playgrounds0.430.430.430.43
Clubhouse/community centres0000
Shopping area0000
Other0.410.410.410.41

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3.173.170.91
Water Supply System5.095.091.46
Sewerage treatment & garbage disposal3.103.100.89
Electricity Supply System000
Storm Water Drainage1.491.490.43
Parks and Playgrounds0.430.430.12
Clubhouse/community centres000
Shopping area000
Other0.410.410.12












Particulars Remarks, if any
i. No. of Flats/Apartments constructed204Tower-14/15/16/17 to be consturcted.
ii. No. of Flats/ Apartments booked193Construction to be start.
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter4911.08 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter2029.05 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter2882.03 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter2882.03 LakhsAs per Sr. No. V.
vii. Amount invested in the project upto the date of application3038.61 Lakhs
Land cost (If any)1161.26 Lakhs
Apartments4019.58 Lakhs
Infrastructure195.73 Lakhs
EDC/ Taxes Etc.2499.18 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession4637.34 Lakhs
(a) In respect of existing allottees0 LakhsAs per Sr. No. VIII.
(b) In respect of rest of the project0 LakhsAs per Sr. No. VIII.
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
27250.00 LakhsLoan raised from Bank of Maharasthtra on entire township of 30.65 acres having 37 2/19/2019 https://haryanarera.gov.in/view_project/project_preview 19/32 Towers. and Peninsula Brookfield NCD of 200 Cr on entire township area of 30.65 acres having 37 Towers.
x. Total liabilities against the project up-to-date. (Annex details in folder C) 26480.00 LakhsRs. 38.80 Cr & Interesdt over due approx 12.00 Cr. and Rs. 200 Cr & Interest approx 64 Crore.



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS37.7245.27
II. WATER SUPPLY SYSTEM60.6572.78
III. STORM WATER DRAINAGE17.7721.32
IV. ELECTRICITY SUPPLY SYSTEM00
V. SEWAGE TREATMENT & GARBAGE DISPOSAL36.9244.30
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.5.166.20
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM00
XVII. OTHER FACILITIES AS PER PROJECT REPORT4.895.87









Yes
Yes
BANK OF MAHARASHTRA
60289880678
MAHB0000343
110014003
003
Mr. Chander, AG-24B, Ansal Highway Plaza, NH-1, Kundli Sonipat-132028
Uploaded in upload section.











No
No
Yes
Yes
Yes
No
No
No
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. NOC FIRE FIGHTING SCHEMEALREADY BEEN OBTAINED13-11-2014
II. ELECTRICAL SCHEME APPROVAL AND LOAD APPROVALALREADY BEEN OBTAINED01-02-2008
III. FOREST NOCALREADY BEEN OBTAINED02-06-2008
IV. ACCESS PERMISSION FROM PWDALREADY BEEN OBTAINED15-09-2011
V. AIRPORT AUTHORITY OF INDIA NOCALREADY BEEN OBTAINED03-08-2012
VI. SERVICE ESTIMATE PLAN APPROVALALREADY BEEN OBTAINED22-06-2013
VII. ENVIRONMENTAL CLEARANCEALREADY BEEN OBTAINED30-10-2007
VIII. NOC FROM CENTRAL GROUND WATER AUTHORITYALREADY BEEN OBTAINED14-03-2008
IX. CONSENT TO ESTABLISHALREADY BEEN OBTAINED14-03-2008
X. BUILDING PLAN APPROVALALREADY BEEN OBTAINED31-03-2014
XI. ZONING PLAN APPROVALALREADY BEEN OBTAINED20-03-2007
XII. LICENSE NO. 1125 & 1126 OF 2006ALREADY BEEN OBTAINED02-09-2006
XIII. OCCUPATION CERTIFICATE FOR BALANCE TOWERSYET TO FILE FOR APPROVALNA








Yes


Yes


Annexed in Folder - F.







SUSHANT GREENS (22.63 ACRES) PANIPAT
22.63
0.00
200
0.00
74
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
11111.1710318.618842.74
Cost of the apartments000
Cost of the infrastructure2057.551264.44241.71
Others costs9054.179054.179054.17


1501.74 Lakhs
2275.78 Lakhs
16500.00 Lakhs
16500.00 Lakhs
No
31-12-2019
31-12-2019










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEDRG ROOM- VITRIFIED TILES, BED ROOM- LAMINATED WOOD, FLOORING-VITRIFIED TILES, KITCHEN- CERMIC TILES, COMMON AREAS- UDAIPUR GREEN/ KOTA STONE.
2WALL FINISHING DETAILSCEMENT PLASTER WITH PLASTIC EMULSION PAINT.
3KITCHEN DETAILSCERAMIC TILES UPTO 2 FEET ABOVE COUNTER AND OIL BOUND DISTEMPER IN BALANCE AREA, POLISHED GRANITE COUNTER.
4BATHROOM FITTINGSCP FITTINGS WITH SINGLE LEVER MIXER, DIREVERTER IN SHOWER AREA WITH WHITE CHINAWARE.
5WOOD WORK ETC1. DOOR CHOWKHATS- RED MIRANDI, 2. EXT. DOOR WINDOWSUPVC
6DOORS AND WINDOS FRAMES1. DOOR CHOWKHATS- RED MIRANDI, 2. EXT. DOOR WINDOWSUPVC
7GLASS WORKEXT. DOOR WINDOWS.
8ELECTRIC FITTINGSNIL
9CONDUCTING AND WIRING DETAILSPVC HEAVY DUTY CONDUIT PIPE/ INSULATED COPPER WIRING AS PER IS INSIDE THE APARTMENT.
10CUPBOARD DETAILSONLY NICHES FOR WARDROBES IN BEDROOMS.
11WATER STORAGEWATER CONNECTION FROM OH WATER TANK
12LIFT DETAILSPASSENGER LIFT FRO 10 PERSON-680 KG SERVICE LIFT FOR 15 PERSON - 1020 KG
13EXTERNAL GLAZINGSUPVC/ ALUMINIUM ANODIZED WINDOW WITH GLASS SHUTTER.
13.1WINDOWS/GLAZINGSUPVC/ ALUMINIUM ANODIZED WINDOW WITH GLASS SHUTTER.
14DOORSHARDWOOD (POLISHED DOOR SHUTTER. MOLDED DOOR SHUTTER
14.1MAIN DOORSHARDWOOD (POLISHED) DOOR SHUTTER
14.2INTERNAL DOORSMOLDED DOOR SHUTTER. OPTIONAL
15AIR CONDITIONINGOPTIONAL
16ELECTRICAL FITTINGSNIL
17CNG PIPE LINENIL
18PROVISION OF WIFI AND BROADBAND FACILITYYES, PROVIDED.
19EXTERNAL FINISHING/COLOUR SCHEMETEXTURE PAINT/ SEMI PERMANENT FINISH.
20INTERNAL FINISHINGPLASTIC EMULSION PAINT AND OIL BOUND DISTEMPER
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORDRG ROOM- VITRIFIED TILES, BED ROOM- LAMINATED WOOD, FLOORING-VITRIFIED TILES, KITCHEN- CERMIC TILES, COMMON AREAS- UDAIPUR GREEN/ KOTA STONE.
1 . 2 WALLSCEMENT PLASTER WITH PLASTIC EMULSION PAINT.
1 . 3 CEILINGCEMENT PLASTER WITH PLASTIC EMULSION PAINT.
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORDRG ROOM- VITRIFIED TILES, BED ROOM- LAMINATED WOOD, FLOORING-VITRIFIED TILES, KITCHEN- CERMIC TILES, COMMON AREAS- UDAIPUR GREEN/ KOTA STONE.
2 . 2 WALLSCEMENT PLASTER WITH PLASTIC EMULSION PAINT.
2 . 3 CEILINGOIL BOUND DISTEMPER ON CEILING.
2 . 4 MODULAR WARDROBES-
3 . MASTER TOILET
3 . 1 FLOORANTI SKID CERAMIC TILES
3 . 2 WALLSCEREMIC TILES UPTO 7FT HEIGHT.
3 . 3 CEILING-
3 . 4 COUNTERSGRANITE COUNTER
3 . 5 SANITARY WARE/CP FITTINGSSINGLE LEVER C.P. FITTING, EWC,
3 . 6 FITTING/FIXTURESTOWEL RING/ TOWEL ROD, PAPER HOLDER, EXHAUST FANS FITTED.
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES/ LAMINATED WOODEN FLOORING,
4 . 2 WALLSPLASTIC EMULSION PAINT.
4 . 3 CEILINGOBD.
4 . 4 WARDROBESNICHES WITH COMPLETE WOOD WORK.
5 . TOILET
5 . 1 FLOORANTI SKID CERAMIC TILES.
5 . 2 WALLSCERAMIC TILES UPTO 7FT.
5 . 3 CEILING-
5 . 4 COUNTERSGRANITE COUNTER.
5 . 5 SANITARY WARE/CP FITTINGSSINGLE LEVER C.P. FITTINGS, EWC.
5 . 6 FIXTURESTOWEL RING/ TOWEL ROD, PAPER HOLDER, EXHAUST FANS FITTED.
6 . KITCHEN
6 . 1 FLOORANTI SKID CERAMIC TILES.
6 . 2 WALLSCERAMIC TILES UPTO 2FT ABOVE COUNTER AND OIL BOUND DISTEMPER IN THE BALANCE AREA.
6 . 3 CEILINGOBD
6 . 4 COUNTERSPOLISHED GRANITE COUNTER.
6 . 5 FIXTURESMODULER KITCHEN WITH CHIMNEY & RO
6 . 6 KITCHEN APPLIANCESEXHAUST FAN FITTED.
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORANTI SKID CERAMIC TILES.
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYANTI SKID CERAMIC TILES, WEATHER PROOF PAINT/ TEXTURE PAINT.
8 . SIT-OUTS
8 . 1 FLOORANTI SKID CERAMIC TILES.
8 . 2 WALLS & CEILINGWEATHER PROOF PAINT/ TEXTURE PAINT.
8 . 3 RAILINGSN/A/
8 . 4 FIXTURESN/A












Sr. No.Document DescriptionDate of Document UploadView Document
1 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 23-02-2019 View Document
2 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 23-02-2019 View Document
3 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 23-02-2019 View Document
4 ZONING PLAN 23-02-2019 View Document
5 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 23-02-2019 View Document
6 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 23-02-2019 View Document