9910612499 (Number Shared by Promoter in Public)
shankar.mukkavilli@ril.com
http://www.modeleconomictownship.com
XXXX037Q
U70109HR2006PLC036416
MET CITY, POCKET C & D, 35.669 ACRES (RESIDENTIAL POCKET)
SECTOR-8, FATEHPUR & YAKUBPUR
BADLI
JHAJJAR
01243527369
9998987100 (Number Shared by Promoter in Public)
rakesh.b.sinha@ril.com
RAKESH B SINHA
01243527369
9998987100 (Number Shared by Promoter in Public)
rakesh.b.sinha@ril.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
453733
30-09-2022
735000
HDFC BANK
HRERA Panchkula
2
4642936
15-07-2026
14934
ICICI BANK
HRERA Panchkula
35.669 (Acre)
2.64
2.64
1296.75625 (Acre)
16 of 2018, 11
of 2021, 64
of 2022 ,47 of 2026
Yes
12130.65 Lakhs
3478.29 Lakhs
0 Lakhs
8518.21 Lakhs
134.15 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
17.50
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
15.429
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
2.740
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
13
PUBLIC UTILITY
0
Total
35.669
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
DTCP, HARYANA
Yes
WATER SUPPLY
DTCP, HARYANA
Yes
ELECTRICITY
UHBVN
Yes
SEWAGE DISPOSAL
DTCP, HARYANA
Yes
STORM WATER DRAINAGE
DTCP, HARYANA
Yes
LAYOUT
DTCP HARYANA
Yes
LICENSE FOR PROJECT
DTCP HARYANA
Yes
ZONING PLAN
DTCP HARYANA
Yes
SERVICE PLAN ESTIMATE
DTCP HARYANA
No
ENVIRONMENTAL CLEARANCE
MOEF
Yes
CTE PERMISSION
HARYANA STATE POLLUTION CONTROL BOARD
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
2286.45
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
942.14
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
697.78
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
1398.36
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
630.71
AS PER PROJECT REPORT
6
STREET LIGHTING
126.04
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
48.06
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
15
PMC CONSULTANCY GATE COMMUNITY FACILITY CONTINGENCY SITE OVERHEADS ETC
2388.67
AS PER PROJECT REPORT
16
STATUTORY CHARGES
134.15
AS PER PROJECT REPORT
13-03-2026 (date)
13-03-2026 (date)
01-12-2022
30-11-2027
Sr. No
Plot Area(In Square Meter)
Number of plots in the project
1
27.500
2
2
58.861
5
3
61.788
37
4
90.448
1
5
92.870
9
6
92.938
10
7
94.529
4
8
108.997
2
9
109.319
91
10
109.412
5
11
109.480
76
12
109.734
1
13
109.802
1
14
110.285
2
15
120.589
2
16
123.462
2
17
129.129
44
18
129.960
62
19
130.032
24
20
131.116
2
21
132.464
4
22
133.243
4
23
133.463
2
24
133.644
4
25
144.090
5
26
144.400
2
27
149.898
2
28
149.920
9
29
149.937
21
30
150.000
131
31
1560.300
1
Total
567
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
Shops
0
Plots
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
2108.74
Water Supply System
868.74
Sewerage treatment & garbage disposal
576.16
Electricity Supply System
1283.71
Storm Water Drainage
642.30
Parks and Playgrounds
44.33
Clubhouse/community centres
0
Shopping area
0
Other
0
Consultancy Fees Site Overheads Community Facilities Etc
2301.32
Statutory charges
131.38
Street Lighting
116.22
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
29.62
29.62
Water Supply System
0
12.23
12.23
Sewerage treatment & garbage disposal
0
9.09
9.09
Electricity Supply System
0
19.11
19.11
Storm Water Drainage
0
9.25
9.25
Parks and Playgrounds
0
0.62
0.62
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
0
6.41
6.41
Street lighting
1.64
1.64
PMC and Consultancy and Gate and Community facility and contingency etc
8.15
8.15
Statutory Charges
0.46
0.46
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
29.62
29.62
29.62
29.62
Water Supply System
12.23
12.23
12.23
12.23
Sewerage treatment & garbage disposal
9.09
9.09
9.09
9.09
Electricity Supply System
19.11
19.11
19.11
19.11
Storm Water Drainage
9.25
9.25
9.25
9.25
Parks and Playgrounds
0.62
0.62
0.62
0.62
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
6.41
6.41
6.41
6.41
PMC and Consultancy and Gate and Community facility and contingency etc
8.15
8.15
8.15
Statutory Charges
0.46
0.46
0.46
Street lighting
1.64
1.64
1.64
Yes
No
ICICI BANK LTD, HIGHWAY MART, RELIANCE MET LTD., SCO-22, 23 & 24 SECTOR-7A, ON SH-15, DADRI TOE, JHAJJAR, HARYANA 124515 DADRI TOE, HARYANA, INDIA
459405000041
ICIC0004594
124229056
4594
Shri Shrivallabh Goyal
Attached in Folder D
Yes
Yes
Yes
No
No
No
No
No
No
No
Yes
Yes
Yes
Yes
Yes
No
Yes
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSES FOR PROJECT (11 OF 2021)
ALREADY BEEN OBTAINED
12-03-2021
II. CONSENT TO ESTABLISH PERMISSION
ALREADY BEEN OBTAINED
17-05-2021
III. ENVIRONMENT CLEARANCE
ALREADY BEEN OBTAINED
12-05-2026
IV. SERVICE PLAN ESTIMATE
ALREADY BEEN OBTAINED
10-04-2024
V. APPROVED LAYOUT PLAN
ALREADY BEEN OBTAINED
13-03-2026
VI. LICENSES FOR PROJECT (47 OF 2026)
ALREADY BEEN OBTAINED
13-03-2026
VII. LICENSES FOR PROJECT (16 OF 2018)
ALREADY BEEN OBTAINED
23-02-2018
VIII. LICENSES FOR PROJECT (64 OF 2022)
ALREADY BEEN OBTAINED
25-05-2022
IX. ELECTRICITY PLAN
APPLIED FOR BUT YET TO RECEIVE
12-07-2026
Yes
Yes
NA
INDUSTRIAL COLONY FOR 125.36 ACRES SECTOR – 2B, IN VILLAGE SHEOJIPURA, DIST. JHAJJAR
125.36
0
87
0
83
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
8765
11420.42
7558.92
Cost of the apartments
0
0
0
Cost of the infrastructure
8382
10830.15
6973.28
Others costs
383
590.27
585.64
51048 Lakhs
262 Lakhs
0 Lakhs
0 Lakhs
No
31-03-2027
31-03-2027
MET CITY POCKET SECTOR 2A, 49.584 ACRES IN VILLAGE SHEOJIPURA, DIST. JHAJJAR
49.584
0
523
0
481
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
6425
9697.62
8216.81
Cost of the apartments
0
0
0
Cost of the infrastructure
6305
9472.32
7991.51
Others costs
120
225.30
225.30
45126 Lakhs
1962 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2028
31-12-2028
INDUSTRIAL COLONY OF 258.44 ACRES SECTOR-3, IN VILLAGE DADRI TOE AND BIR DADRI, DIST. JHAJJAR
258.44
0
121
0
113
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
14246.08
25904.90
24801.85
Cost of the apartments
0
0
0
Cost of the infrastructure
13251.88
24431.33
23328.28
Others costs
994.20
1473.57
1473.57
46274 Lakhs
194 Lakhs
0 Lakhs
0 Lakhs
No
30-06-2023
30-06-2026
MET HABITAT, 20.395 ACRES, SECTOR-3 IN VILLAGE DADRI TOE, DIST. JHAJJAR
20.395
0
105
0
68
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
2635
5185.11
4836.69
Cost of the apartments
0
0
0
Cost of the infrastructure
2593
5138.36
4789.94
Others costs
42
46.75
46.75
17446 Lakhs
897 Lakhs
0 Lakhs
0 Lakhs
No
31-03-2028
31-03-2028
INDUSTRIAL COLONY OF 580.722 ACRES IN SECTOR-4, 5, 7A, 7B, VILLAGE DADRI TOE YAKUBPUR AND SONDHI, DIST. JHAJJAR
580.722
0
385
0
359
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
54813
54531.31
45582.74
Cost of the apartments
0
0
0
Cost of the infrastructure
53038
51777.47
42879.19
Others costs
1775
2753.84
2703.55
113801 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
11-05-2024
11-02-2027
A COMMERCIAL PLOT (HIGHWAY MART) OF 4.96 ACRES, PART OF INDUSTRIAL TOWNSHIP OF 1296.75625 ACRES IN VILLAGE YAKUBPUR, DIST. JHAJJAR
4.96
0
69
0
38
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
1124
1645.75
1631.98
Cost of the apartments
0
0
0
Cost of the infrastructure
1108
1611.70
1597.93
Others costs
16
34.05
34.05
2765 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
01-06-2024
01-06-2026
INDUSTRIAL COLONY OF 85.703 ACRES SECTOR-10A, IN VILLAGE SONDHI, DIST. JHAJJAR
85.703
0
52
0
47
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
6535.811
8725.99
6891.41
Cost of the apartments
0
0
0
Cost of the infrastructure
6366.12
8558.06
6723.48
Others costs
169.69017
167.93
167.93
34540 Lakhs
70 Lakhs
0 Lakhs
0 Lakhs
No
30-11-2027
30-11-2027
INDUSTRIAL COLONY OF 148.69 ACRES SECTOR-11, IN VILLAGE NIMANA, DIST. JHAJJAR.
148.69
0
143
0
131
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
9920.24
14383.81
10420.25
Cost of the apartments
0
0
0
Cost of the infrastructure
9642.92
13858.03
9894.47
Others costs
277.32
525.78
525.78
79731 Lakhs
184 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2028
31-12-2028
MET CITY POCKET – E, SECTOR-8, 14.194 ACRES IN VILLAGE YAKUBPUR, DIST. JHAJJAR
14.194
0
281
0
272
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
1580
4043.21
3056.14
Cost of the apartments
0
0
0
Cost of the infrastructure
1545
3983.42
2996.35
Others costs
35
59.79
59.79
31906 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2028
31-12-2028
MET CITY POCKET – J & K, SECTOR-8, 54.638 ACRES IN VILLAGE YAKUBPUR & SONDHI, DIST. JHAJJAR
54.638
0
684
0
664
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
6052.12
10441.42
7421.45
Cost of the apartments
0
0
0
Cost of the infrastructure
5872.2
10166.78
7156.33
Others costs
172.92
274.64
265.12
42849 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
31-05-2027
31-05-2027
MET CITY POCKET – L, SECTOR-8, 79.756 ACRES IN VILLAGE YAKUBPUR, SONDHI & FATEHPUR, DIST. JHAJJAR
79.756
0
812
0
808
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
13237
14934.17
13918.67
Cost of the apartments
0
0
0
Cost of the infrastructure
12363
14585.38
13569.88
Others costs
874
348.79
348.79
33865 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
30-06-2026
30-06-2027
A COMMERCIAL PLOT (SUPERMART) OF 3.356 ACRES, PART OF INDUSTRIAL TOWNSHIP OF 1296.75625 ACRES IN VILLAGE YAKUBPUR, DIST. JHAJJAR
3.356
0
50
0
41
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
1124
1257.01
1080.59
Cost of the apartments
0
0
0
Cost of the infrastructure
1080.59
1236.83
1060.41
Others costs
16
20.18
20.18
4347 Lakhs
44 Lakhs
0 Lakhs
0 Lakhs
No
30-06-2027
30-06-2027
METROPOLIS BY MET CITY INDUSTRIAL COMPONENT
56.818
0
86
0
18
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
5653
9579.22
5619.89
Cost of the apartments
0
0
0
Cost of the infrastructure
5488
9414.17
5454.84
Others costs
165
165.05
165.05
7685 Lakhs
4138 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2028
31-12-2028
METROPOLIS BY MET CITY RESIDENTIAL COMPONENT
42.009
0
478
0
233
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
9124
10751.45
5508.66
Cost of the apartments
0
0
0
Cost of the infrastructure
9003
10627.49
5384.70
Others costs
123.79
123.96
123.96
14745 Lakhs
21571 Lakhs
0 Lakhs
0 Lakhs
No
30-06-2029
30-06-2029
MET CITY CELESTE, D-243 - D-252, POCKET C & D, SECTOR-08, VILLAGE FATEHPUR, MODEL ECONOMIC TOWNSHIP LIMITED
0.32
40
10
0
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
0
2214.32
956.32
Cost of the apartments
0
1865.01
643.84
Cost of the infrastructure
0
329.14
292.31
Others costs
0
20.17
20.17
0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
15-05-2024
30-06-2027
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following: