HRERA GurugramTemp Project Id : RERA-GRG-PROJ-2311-2026
Submission Date : 22-09-2026 02:01:22 PM
Applicant Type : Company
Project Type: NEW




RIVERDAY INFRASTRUCTURE PRIVATE LIMITED
12A FLOOR, TOWER 2 M3M INTERNATIONAL FINANCIAL CENTER, SECTOR 66, GURGAON, GURUGRAM, HARYANA
1246600000
8929012754 (Number Shared by Promoter in Public)
secretarial@smartworlddevelopers.com
https://riverdayinfrastructure.com/
XXXX273J
U70100HR2021PTC098078
 
 


 
 


 
 


 
 







SMARTWORLD SKY ARC AVENUE
SECTOR 69
BADSHAHPUR ST
GURUGRAM
01246600000
8929012754 (Number Shared by Promoter in Public)
secretarial@smartworlddevelopers.com
BHARAT VIGMAL
01246600000
8929012754 (Number Shared by Promoter in Public)
secretarial@smartworlddevelopers.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
151309722-09-2026456894ICICI BANK LIMITEDHRERA Gurugram
251309822-09-202644621ICICI BANK LIMITEDHRERA Gurugram







2.2896 (Acre)
5.120
0.09
11.66875 (Acre)
Licence no 90 of 2024 dated 18.07.2024
No
Address     41ST FLOOR, TOWER-1, M3M INTERNATIONAL FINANCIAL CENTER, SECTOR-66, GURUGRAM
Annexure-B- ANNEXURE-B - COLLABORATOR VIDE REGISTERED DEVELOPMENT RIGHTS AGREEMENT
BEFORE THE GRANT OF LICENSE
Yes
THE SUMMARY OF THE AGREEMENTS ARE ATTACHED IN FOLDER-A
No
Yes
Yes







8505.82 Lakhs
2265.75 Lakhs
310.37 Lakhs
3726.79 Lakhs
2202.91 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0.2865
3CONSTRUCTION OF ROADS 0.3169
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0.3293
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 1.3569
Total2.2896




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDANo
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS11.47AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM5.13AS PER PROJECT REPORT
3STORM WATER DRAINAGE3.05AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM0AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL3.05AS PER PROJECT REPORT
6STREET LIGHTING3.22AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING4.26AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS5.72AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER0AS PER PROJECT REPORT
15STP7.74AS PER PROJECT REPORT
16GAS WORKS4.13AS PER PROJECT REPORT
17UNDERGROUND TANK5.35AS PER PROJECT REPORT
18RAIN WATER HARVESTING3.02AS PER PROJECT REPORT
19ELECTRICAL SUB STATION75.94AS PER PROJECT REPORT
20CONSULTANCY100.38AS PER PROJECT REPORT
21INFRA ESTABLISHMENTS77.91AS PER PROJECT REPORT


08-09-2026 (date)
21-09-2026 (date)
01-10-2026
30-09-2031
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings74.2612
Apartment/Shops/Other Buildings90.4912
Apartment/Shops/Other Buildings135.0812
Apartment/Shops/Other Buildings138.4412
Apartment/Shops/Other Buildings143.4512
Apartment/Shops/Other Buildings160.5512
Apartment/Shops/Other Buildings168.8712
Apartment/Shops/Other Buildings169.6722
Apartment/Shops/Other Buildings170.9332
Apartment/Shops/Other Buildings177.1612
Apartment/Shops/Other Buildings188.3512
Apartment/Shops/Other Buildings317.5512
Apartment/Shops/Other Buildings345.8812
Apartment/Shops/Other Buildings603.4852
Apartment/Shops/Other Buildings735.4612
Apartment/Shops/Other Buildings229.6212
Apartment/Shops/Other Buildings339.1122
Apartment/Shops/Other Buildings353.0412
Apartment/Shops/Other Buildings377.7162
Apartment/Shops/Other Buildings407.6822
Apartment/Shops/Other Buildings429.3042
Apartment/Shops/Other Buildings434.8912
Apartment/Shops/Other Buildings459.25122
Apartment/Shops/Other Buildings487.7912
Apartment/Shops/Other Buildings499.8222
Apartment/Shops/Other Buildings500.5612
Apartment/Shops/Other Buildings513.5622
Apartment/Shops/Other Buildings532.7322
Apartment/Shops/Other Buildings569.7962
Apartment/Shops/Other Buildings599.7362
Apartment/Shops/Other Buildings646.7212





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0
Shops0
Plots0
Apartment OR Shops OR Other Buildings3.88

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000
Apartment OR Shops OR Other Buildings45.2879.69137.77195.38

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000
Apartment OR Shops OR Other Buildings263.92323.70327.72345.28

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000
Apartment OR Shops OR Other Buildings372.30377.55350.02239.51

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000
Apartment OR Shops OR Other Buildings154.21135.14109.2792.18

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments000
Shops000
Plots000
Apartment OR Shops OR Other Buildings85.3065.9922.69




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000.10
Sewerage treatment & garbage disposal0000.03
Electricity Supply System0000
Storm Water Drainage0000.06
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
INFRA ESTABLISHMENTS7.79
CONSULTANCY50.19

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0.210.310.360.46
Sewerage treatment & garbage disposal0.090.150.180.21
Electricity Supply System0000
Storm Water Drainage0.120.180.210.27
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
INFRA ESTABLISHMENTS11.6915.5815.5810.13
ELECTRICAL SUB STATION3.804.566.08
RAIN WATER HARVESTING0.060.150.210.30
UNDERGROUND TANK0.110.210.370.54
GAS WORKS0.411.03
STP0.15
CONSULTANCY50.19

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0.720.720.620.41
Sewerage treatment & garbage disposal0.270.300.340.37
Electricity Supply System0000
Storm Water Drainage0.300.370.460.46
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
RAIN WATER HARVESTING0.360.420.450.45
STP0.390.540.700.77
GAS WORKS1.440.830.41
UNDERGROUND TANK0.800.800.640.54
ELECTRICAL SUB STATION7.5911.3911.399.11
INFRA ESTABLISHMENTS7.799.35

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements00.691.031.49
Water Supply System0.310.260.150.15
Sewerage treatment & garbage disposal0.370.270.180.09
Electricity Supply System0000
Storm Water Drainage0.270.150.060.03
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
ELECTRICAL SUB STATION7.596.833.803.80
STP0.931.161.160.77
UNDERGROUND TANK0.430.320.270.21
RAIN WATER HARVESTING0.270.180.090.03
SECURITY AND FIRE FIGHTING0.100.20

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.722.292.291.15
Water Supply System0.100.100.050.05
Sewerage treatment & garbage disposal0.060.030.030.03
Electricity Supply System0000
Storm Water Drainage0.030.030.030.80
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
STP0.460.230.150.15
SECURITY AND FIRE FIGHTING0.321.071.070.76
PLAYGROUNDS AND PARKS0.860.861.431.43
STREET LIGHTING0.80
UNDERGROUND TANK0.11
RAIN WATER HARVESTING0.03

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0.80000
Water Supply System0.05000
Sewerage treatment & garbage disposal0.03000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
SECURITY AND FIRE FIGHTING0.74
PLAYGROUNDS AND PARKS1.14
STREET LIGHTING1.61
STP0.15












Yes
Yes
KOTAK MAHINDRA BANK, UNIT NO.8 AND 9, SEVA CORPORATE PARK, MG ROAD, GURGAON, HARYANA
4054806885
KKBK0000261
110485003
0261
1. Gaurav Bansal-C-501, Lions Society, Opposite Tau Devi Lal Park, Sector 56, Gurgaon Sector 56, Gurgaon, Haryana - 122011 2. Rajat Jain-Villa no 44, Tulip Lvory, Gurgaon, Sector 70, Badshahpur, Gurgaon, Haryana-122101 3. Vivek Singhal-Flat No 7A, Tower 1, Fairway West, M3M Golf Estate, Sector 65, Badshahpur , Gurgaon, Haryana-122101 4. Anuj Kumar Goel- House No- C-25, Street No-1, Near Sunrise Public School, Bhajanpura, North East, Delhi- 110053 5. Anil Mittal H No 723, Sector 31 Gurugram 6.Meenal Sood-C-81A, Moti Nagar, Ramesh Nagar H.O, West Delhi, Delhi 110015
Uploaded











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENCE ALREADY BEEN OBTAINED18-07-2024
II. EP APPROVAL ALREADY BEEN OBTAINED23-07-2026
III. FOREST NOC ALREADY BEEN OBTAINED01-05-2024
IV. ASSURANCE STP TREATED WATER ALREADY BEEN OBTAINED04-09-2024
V. ASSURANCE DRINKING WATER ALREADY BEEN OBTAINED05-07-2024
VI. ASSURANCE SEWERAGE CONNECTION ALREADY BEEN OBTAINED05-07-2024
VII. AAI NOC ALREADY BEEN OBTAINED14-03-2023
VIII. BR-III ALREADY BEEN OBTAINED21-09-2026
IX. LOI ALREADY BEEN OBTAINED13-03-2024








Yes


Yes


As Per HRERA Rules







SMARTWORLD SKY ARC
6.97635
952
0
893
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
255841.11255841.1189097.69
Cost of the apartments147001.72147001.7249208.05
Cost of the infrastructure9028.169028.160.00
Others costs99811.2399811.2339889.64


154545.59 Lakhs
312399.79 Lakhs
0.00 Lakhs
0.00 Lakhs
No
31-05-2032
31-05-2032




TRUMP RESIDENCES GURGAON
0.633
298
0
223
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
136001.28136001.2845715.87
Cost of the apartments62363.1262363.1226528.88
Cost of the infrastructure2508.542508.540.00
Others costs71129.6271129.6219186.99


66337.14 Lakhs
169334.06 Lakhs
0.00 Lakhs
0.00 Lakhs
No
30-09-2032
30-09-2032










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILES|KAJARIA, SOMANY OR SIMILAR
2WALL FINISHING DETAILSCOMBINATION OF OBD AND ACRYLIC EMULSION PAINT | ASIAN OR SIMILAR
3KITCHEN DETAILSANTISKID CERAMIC TILES | KAJARIA, SOMANY OR SIMILAR
4BATHROOM FITTINGSPLASTER + DADO UP TO 7FT | KAJARIA, SOMANY OR SIMILAR
5WOOD WORK ETCSEASONED WOOD | TREATED WOODEN FRAME
6DOORS AND WINDOS FRAMESALUMINIUM FRAMING SLIDING | SINGLE GLAZED/DOUBLE GLAZED AS PER WIND LOADS.
7GLASS WORKNA
8ELECTRIC FITTINGSPROVISIONS ONLY
9CONDUCTING AND WIRING DETAILSINSULATED WIRES OF 1,2,3 CORES | POLYCAB,HAVELLS OR AS PER IS CODES
10CUPBOARD DETAILSNA
11WATER STORAGEAS PER NORMS
12LIFT DETAILSLIFTS AS PER BUILDING PLANS
13EXTERNAL GLAZINGSEXTERNAL ALUMINIUM WITH GLASS | AS PER APPROVED MAKE
13.1WINDOWS/GLAZINGSGLASS WITH ALUMINIUM FRAMING SLIDING | AS PER APPROVED MAKE
14DOORSNA
14.1MAIN DOORSHARDWOOD DOOR FRAME WITH FLUSH DOOR/LAMINATE
14.2INTERNAL DOORSHARDWOOD DOOR FRAME WITH FLUSH DOOR/LAMINATE
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSAS PER APPROVED MAKE
17CNG PIPE LINESERVICE PROVIDER
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMEWATER PROOF PAINT
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES/LAMINATED WOODEN FLOOR/ CERAMIC TILES
1 . 2 WALLSPLASTER WITH OBD
1 . 3 CEILINGOBD AND PUTTY
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILES/LAMINATED WOODEN FLOORING
2 . 2 WALLSPLASTER AND OBD/ACRYLIC
2 . 3 CEILINGOBD AND PUTTY
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORANTISKID CERAMIC TILES
3 . 2 WALLSPLASTER AND DADO
3 . 3 CEILINGGRID FALSE CEILING/OBD
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSAS PER APPROVED MAKE
3 . 6 FITTING/FIXTURESAS PER APPROVED MAKE
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 22-09-2026 View Document
2 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 22-09-2026 View Document
3 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 22-09-2026 View Document
4 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 22-09-2026 View Document
5 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 22-09-2026 View Document
6 DEMARCATION PLAN 22-09-2026 View Document
7 ZONING PLAN 22-09-2026 View Document