HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-2138-2026
Submission Date : 08-08-2026 01:59:43 PM
Applicant Type : Company
Project Type: NEW




AMBALA HOME LAND DEVELOPERS PRIVATE LIMITED
K.NO 8/13/2 ARJUN NAGAR AMBALA CANTT HARYANA INDIA 133001
9888153433 (Number Shared by Promoter in Public)
Ambala.homeland@gmail.com
XXXX315N
U70109HR2020PTC086056
 
 


 
 


 
 


 
 


 
 







SERENE CITY
VILLAGE MACHHONDA SECTOR 28
AMBALA
AMBALA
9888153433 (Number Shared by Promoter in Public)
Ambala.homeland@gmail.com
IQBAL KAUR
9888153433 (Number Shared by Promoter in Public)
iqbalkaur6023@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
182015618-07-2026131000PUNJAB NATIONAL BANK HRERA Panchkula







5.98125 (Acre)
1.0 FOR RESIDENTIAL 1.5 FOR COMMERCIAL
1
5.98125 (Acre)
THE LICENCE NO 67 OF 2026 GRANTED BY DTCP ON DATED 20.04.2026 WHICH IS VALID UPTO 19.04.2031
No
Address     R/O VILLAGE MACHHONDA ,P.O. KULDIP NAGAR ,DISTT: AMBALA
Annexure-B- COLLABORATION AGREEMENT EXECUTED BETWEEN THE LANDOWNERS AND THE DEVELOPERS UNDER COLLABORATION REGISTRATION NO. 2165 DATED 28-10-2020 AND LICENSE NO. 67 OF 2026 GRANTED BY DTCP FOR 5.98125 ACRES.
YES THE AGREEMENT EXECUTED BEFORE THE GRANT OF LICENSE.
Yes
THE LANDOWNER HAD APPROACHED THE DEVELOPER TO OBTAIN THE LICENSE AND CONVERSION OF LAND USE FOR THE DEVELOPMENT, RESIDENTIAL PLOTTING, OR ANY OTHER USE AS MAY BE PERMITTED IN ACCORDANCE WITH THE EXISTING POLICIES, NOTIFICATIONS, RULES, OR BYE-LAWS OF THE AUTHORITY OF THE STATE OF HARYANA, AND TO CARRY OUT THE DEVELOPMENT AND CONSTRUCTION WORKS OF THE SAID APPROPRIATE PROJECT AS PER THE TERMS OF THE LICENSE/CONVERSION OF THE LAND USE THAT MAY BE GRANTED BY THE RELEVANT AUTHORITY/DEPARTMENT OF THE STATE, AND THE DEVELOPER HAS AGREED TO THE SAME
No
Yes
Yes







1765.25 Lakhs
957.45 Lakhs
0 Lakhs
448.59 Lakhs
359.21 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 3.2152
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0
3CONSTRUCTION OF ROADS 1.57855
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0.4557
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0.5981
12ANY OTHER 0
13AREA UNDER COMMERCIAL 0.1337
Total5.98125




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYUHBVNNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS122.55AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM70.87AS PER PROJECT REPORT
3STORM WATER DRAINAGE52.08AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM59.97AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL68.14AS PER PROJECT REPORT
6STREET LIGHTING21.93AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS19.32AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15BOUNDARY WALL33.73AS PER PROJECT REPORT


21-04-2026 (date)
NA (date)
01-09-2026
19-04-2031
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 149.88 5
2 177.17 16
3 135.49 8
4 140.35 12
5 104.27 12
6 102.72 2
7 144.99 7
8 142.17 1
9 149.19 15
10 102.51 27
Total105


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements6.160
Water Supply System5.140
Sewerage treatment & garbage disposal3.613.14
Electricity Supply System2.102.65
Storm Water Drainage2.412.14
Parks and Playgrounds00
Clubhouse/community centres00
Shopping area00
Other00
Street lighting2.20
Boundary wall1.20

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements5.925.188.497.46
Water Supply System5.295.485.145.98
Sewerage treatment & garbage disposal3.153.523.240
Electricity Supply System3.453.483.423.96
Storm Water Drainage2.122.623.833.42
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Boundary wall1.301.261.241.52
Street lighting2.263.202.081.26

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements7.687.907.657.90
Water Supply System4.984.254.854.15
Sewerage treatment & garbage disposal3.123.583.193.46
Electricity Supply System3.853.823.473.12
Storm Water Drainage3.523.293.483.51
Parks and Playgrounds001.901.26
Clubhouse/community centres0000
Shopping area0000
Other0000
Street lighting1.281.26
Boundary wall1.651.261.951.16

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements7.976.515.465.28
Water Supply System4.124.344.164.14
Sewerage treatment & garbage disposal3.503.143.423.42
Electricity Supply System4.154.184.134.21
Storm Water Drainage3.1503.253.26
Parks and Playgrounds1.301.681.401.60
Clubhouse/community centres0000
Shopping area0000
Other0000
Street lighting1.241.26
Boundary wall1.251.241.333.24

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements5.495.685.295.69
Water Supply System4.164.6900
Sewerage treatment & garbage disposal3.125.094.104.12
Electricity Supply System5.354.6300
Storm Water Drainage3.1402.502.14
Parks and Playgrounds1.151.202.232.00
Clubhouse/community centres0000
Shopping area0000
Other0000
Boundary wall2.652.242.262.36
Street lighting1.231.981.12

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements5.195.65
Water Supply System00
Sewerage treatment & garbage disposal4.104.12
Electricity Supply System00
Storm Water Drainage2.162.14
Parks and Playgrounds1.602.00
Clubhouse/community centres00
Shopping area00
Other00
Boundary wall2.262.36
Street lighting1.56












Yes
No
ICICI BANK LIMITED, LIC BUILDING, JAGADHARI ROAD,AMBALA CANTT, HARYANA 133001
777705891433
ICIC0000498
133229004
000498
IQBAL KAUR W/O DALJIT SINGH R/O 39 40 ARJUN NAGAR NANHERA 104 KULDEEP NAGAR AMBALA HARYANA 133004
NON DEFAULT CERTIFICATE ATTACHED IN UPLOAD SECTION











Yes
Yes
Yes
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LAYOUT PLAN ALREADY BEEN OBTAINED21-04-2026
II. DEMARCATION CUM ZONING PLANALREADY BEEN OBTAINED16-07-2026








Yes


Yes


THE PROVISION OF RERA ACT AND RULES SHALL BE INCORPORATED IN THE DRAFT AGREEMENT













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 01-08-2026 View Document
2 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 01-08-2026 View Document
3 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 01-08-2026 View Document
4 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 06-08-2026 View Document
5 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 06-08-2026 View Document