HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-2107-2026
Submission Date : 29-07-2026 07:19:13 PM
Applicant Type : Firm
Project Type: NEW


SSM PEAK ASSOCIATE REALTY LLP
B1-21, 1ST FLOOR, SECTOR 11, MAIN MATHURA ROAD, FARIDABAD, HARYANA
8826957800 (Number Shared by Promoter in Public)
ssmpeakassociaterealty@gmail.com
ACD6313
AFDFS3515G

















LAVENDER ESTATE
VILLAGE PALWAL SECTOR 7
PALWAL
PALWAL
9971992185 (Number Shared by Promoter in Public)
ssmpeakassociaterealty@gmail.com
ROHITASH TAYAL
9971992185 (Number Shared by Promoter in Public)
ssmpeakassociaterealty@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
11177919-05-2026167000HDFC BANK DEMAND DRAFTHRERA Panchkula







7.35625 (Acre)
1.0 FOR RESIDENTIAL AND 1.5 FOR COMMERCIAL
1.0
7.35625 (Acre)
LICENSE NO. 56 OF 2026 DATED 02.04.2026 (VALID UPTO 01.04.2031)
Yes







8144.86 Lakhs
3930.38 Lakhs
0.00 Lakhs
2361.91 Lakhs
1852.57 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 3.3547
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0
3CONSTRUCTION OF ROADS 2.45555
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0.5560
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0.7400
12ANY OTHER 0
13COMMERCIAL 0.25
Total7.35625




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYDHBVNLNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS425.14AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM354.29AS PER PROJECT REPORT
3STORM WATER DRAINAGE283.43AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM472.38AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL519.62AS PER PROJECT REPORT
6STREET LIGHTING236.19AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS70.86YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


02-04-2026 (date)
NA (date)
15-07-2026
01-04-2031
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 88.21 1
2 85.57 1
3 132.47 6
4 131.40 1
5 125.15 6
6 125.01 26
7 83.25 2
8 113.33 8
9 125.01 8
10 107.87 48
11 108.28 3
12 149.88 6
Total116


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements22.3822.38
Water Supply System18.6518.65
Sewerage treatment & garbage disposal27.3527.35
Electricity Supply System24.8624.86
Storm Water Drainage14.9214.92
Parks and Playgrounds3.733.73
Clubhouse/community centres00
Shopping area00
Other12.4312.43

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements22.3822.3822.3822.38
Water Supply System18.6518.6518.6518.65
Sewerage treatment & garbage disposal27.3527.3527.3527.35
Electricity Supply System24.8624.8624.8624.86
Storm Water Drainage14.9214.9214.9214.92
Parks and Playgrounds3.733.733.733.73
Clubhouse/community centres0000
Shopping area0000
Other12.4312.4312.4312.43

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements22.3822.3822.3822.38
Water Supply System18.6518.6518.6518.65
Sewerage treatment & garbage disposal27.3527.3527.3527.35
Electricity Supply System24.8624.8624.8624.86
Storm Water Drainage14.9214.9214.9214.92
Parks and Playgrounds3.733.733.733.73
Clubhouse/community centres0000
Shopping area0000
Other12.4312.4312.4312.43

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements22.3822.3822.3822.38
Water Supply System18.6518.6518.6518.65
Sewerage treatment & garbage disposal27.3527.3527.3527.35
Electricity Supply System24.8624.8624.8624.86
Storm Water Drainage14.9214.9214.9214.92
Parks and Playgrounds3.733.733.733.73
Clubhouse/community centres0000
Shopping area0000
Other12.4312.4312.4312.43

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements22.3822.3822.3822.38
Water Supply System18.6518.6518.6518.65
Sewerage treatment & garbage disposal27.3527.3527.3527.35
Electricity Supply System24.8624.8624.8624.86
Storm Water Drainage14.9214.9214.9214.92
Parks and Playgrounds3.733.733.733.73
Clubhouse/community centres0000
Shopping area0000
Other12.4312.4312.4312.43

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements22.38
Water Supply System18.65
Sewerage treatment & garbage disposal27.35
Electricity Supply System24.86
Storm Water Drainage14.92
Parks and Playgrounds3.73
Clubhouse/community centres0
Shopping area0
Other12.43












No
No
HDFC BANK LIMITED, SCO 70 SECTOR 15, FARIDABAD HARYANA-121007
99907700000100
HDFC0001568
110240189
001568
Sh. Rahul Gupta R/o 1492 Sec 14 Faridabad
Uploaded in Upload Section











Yes
Yes
Yes
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO. 56 OF 2026ALREADY BEEN OBTAINED02-04-2026
II. DEMARCATION CUM ZONING PLAN ALREADY BEEN OBTAINED15-05-2026








Yes


Yes


THE PROVISIONS OF RERA ACT AND RULES SHALL BE INCORPORATED IN THE DRAFT AGREEMENT TO SELL.













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENOT APPLICABLE BEING PLOTTED COLONY
2WALL FINISHING DETAILSNOT APPLICABLE BEING PLOTTED COLONY
3KITCHEN DETAILSNOT APPLICABLE BEING PLOTTED COLONY
4BATHROOM FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
5WOOD WORK ETCNOT APPLICABLE BEING PLOTTED COLONY
6DOORS AND WINDOS FRAMESNOT APPLICABLE BEING PLOTTED COLONY
7GLASS WORKNOT APPLICABLE BEING PLOTTED COLONY
8ELECTRIC FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
9CONDUCTING AND WIRING DETAILSNOT APPLICABLE BEING PLOTTED COLONY
10CUPBOARD DETAILSNOT APPLICABLE BEING PLOTTED COLONY
11WATER STORAGENOT APPLICABLE BEING PLOTTED COLONY
12LIFT DETAILSNOT APPLICABLE BEING PLOTTED COLONY
13EXTERNAL GLAZINGSNOT APPLICABLE BEING PLOTTED COLONY
13.1WINDOWS/GLAZINGSNOT APPLICABLE BEING PLOTTED COLONY
14DOORSNOT APPLICABLE BEING PLOTTED COLONY
14.1MAIN DOORSNOT APPLICABLE BEING PLOTTED COLONY
14.2INTERNAL DOORSNOT APPLICABLE BEING PLOTTED COLONY
15AIR CONDITIONINGNOT APPLICABLE BEING PLOTTED COLONY
16ELECTRICAL FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
17CNG PIPE LINENOT APPLICABLE BEING PLOTTED COLONY
18PROVISION OF WIFI AND BROADBAND FACILITYNOT APPLICABLE BEING PLOTTED COLONY
19EXTERNAL FINISHING/COLOUR SCHEMENOT APPLICABLE BEING PLOTTED COLONY
20INTERNAL FINISHINGNOT APPLICABLE BEING PLOTTED COLONY
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
1 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
1 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
2 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
2 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
2 . 4 MODULAR WARDROBESNOT APPLICABLE BEING PLOTTED COLONY
3 . MASTER TOILET
3 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
3 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
3 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
3 . 4 COUNTERSNOT APPLICABLE BEING PLOTTED COLONY
3 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
3 . 6 FITTING/FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
4 . BED ROOMS
4 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
4 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
4 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
4 . 4 WARDROBESNOT APPLICABLE BEING PLOTTED COLONY
5 . TOILET
5 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
5 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
5 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
5 . 4 COUNTERSNOT APPLICABLE BEING PLOTTED COLONY
5 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
5 . 6 FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
6 . KITCHEN
6 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
6 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
6 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
6 . 4 COUNTERSNOT APPLICABLE BEING PLOTTED COLONY
6 . 5 FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
6 . 6 KITCHEN APPLIANCESNOT APPLICABLE BEING PLOTTED COLONY
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
7 . 2 WALLS & CEILINGNOT APPLICABLE BEING PLOTTED COLONY
7 . 3 TOILETNOT APPLICABLE BEING PLOTTED COLONY
7 . 4 BALCONYNOT APPLICABLE BEING PLOTTED COLONY
8 . SIT-OUTS
8 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
8 . 2 WALLS & CEILINGNOT APPLICABLE BEING PLOTTED COLONY
8 . 3 RAILINGSNOT APPLICABLE BEING PLOTTED COLONY
8 . 4 FIXTURESNOT APPLICABLE BEING PLOTTED COLONY












Sr. No.Document DescriptionDate of Document UploadView Document
1 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 02-07-2026 View Document
2 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 02-07-2026 View Document
3 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 02-07-2026 View Document
4 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 27-07-2026 View Document
5 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 27-07-2026 View Document
6 PAYMENT PLAN 18-09-2026 View Document