HRERA GurugramTemp Project Id : RERA-GRG-PROJ-2275-2026
Submission Date : 02-07-2026 11:40:15 AM
Applicant Type : Company
Project Type: ONGOING




NB BUILDCON PVT. LTD
48, BASANT LOK, VASANT VIHAR, NEW DELHI
9810074845
9810074845 (Number Shared by Promoter in Public)
sunil@crsinvestment.com
Https://www.crsinvestment.com
XXXX280E
U45201DL2006PTC146913
 
 


 
 


 
 







GOKULAM
SECTOR 7, SOHNA, GURUGRAM
SOHNA
GURUGRAM
9810074845
9810074845 (Number Shared by Promoter in Public)
sunil@crsinvestment.com
SUNIL MEHTA
9810074845
9810074845 (Number Shared by Promoter in Public)
sunil@crsinvestment.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
112116030-06-2026100000THE FEDERAL BANK LIMITED, HRERA Gurugram







9.4427 (Acre)
0.00
0.00
10.4125 (Acre)
168 OF 2022 dated 21.10.2022 by Director, Town and Country Planning.
Yes







10502.33 Lakhs
3990.11 Lakhs
0.00 Lakhs
1899.71 Lakhs
4612.51 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD 20434.277
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0.00
3CONSTRUCTION OF ROADS 8283.51
4PAVEMENTS 0.00
5PARKS AND PLAYGROUNDS 3579.85
6GREEN BELTS 0.00
7VEHICLE PARKINGS 0.00
8ELECTRICITY SUB-STATION 999.57
9CLUB HOUSE 0.00
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0.00
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 4222.49
12ANY OTHER 0.00
13STP 399.83
14UNDERGROUND WATER TANK 199.91
15MILK AND VEGETABLE BOOTH 27.11
16COMMERCIAL 1673.37
Total39819.917




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSYes
WATER SUPPLYHSVPYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHSVPYes
STORM WATER DRAINAGEHSVPYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS228.40AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM270.80AS PER PROJECT REPORT
3STORM WATER DRAINAGE90.62AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM0.00AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL132.13AS PER PROJECT REPORT
6STREET LIGHTING26.55AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING30.60AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS34.24AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0.00AS PER PROJECT REPORT
10SHOPPING AREA0.00AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0.00AS PER PROJECT REPORT
12SCHOOL0.00AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0.00AS PER PROJECT REPORT
14ANY OTHER160.90AS PER PROJECT REPORT
15STP212.90AS PER PROJECT REPORT
16UNDERGROUND WATER TANK108.00AS PER PROJECT REPORT
17ELECTRICAL SUB STATION528.50AS PER PROJECT REPORT
18CONSTRUCATION OF CIRCULATION ROAD76.07AS PER PROJECT REPORT


NA (date)
NA (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartments Total number of plots/apartments in the project Total size of the plots/carpet area of the apartments Plots/apartments booked/ sold upto the date of application Yet to be sold/ booked No. of towers to be/ being constructed for booked apartments
1 PLOT Type A 135.000 14 1890 13 1 0
2 PLOT Type B 145.720 4 582.88 0 4 0
3 PLOT Type C 146.199 24 3508.776 11 13 0
4 PLOT Type D 144.960 4 579.84 4 0 0
5 PLOT Type E 131.724 7 922.068 7 0 0
6 PLOT Type F 111.481 20 2229.62 20 0 0
7 PLOT Type G 126.000 12 1512 12 0 0
8 PLOT Type H 150.000 40 6000 38 2 0
9 PLOT Type J1 104.118 1 104.118 1 0 0
10 PLOT Type J2 111.402 1 111.402 1 0 0
11 PLOT Type J3 118.689 1 118.689 1 0 0
12 PLOT Type J4 125.972 1 125.972 1 0 0
13 PLOT Type J5 133.256 1 133.256 1 0 0
14 PLOT Type J6 140.543 1 140.543 1 0 0
15 PLOT Type K 145.170 1 145.17 0 1 0
16 PLOT Type L 142.500 1 142.5 0 1 0
17 PLOT Type M 149.191 1 149.191 1 0 0
18 PLOT Type N 135.707 1 135.707 0 1 0
19 PLOT Type N1 126.189 1 126.189 1 0 0
20 PLOT Type P 141.510 1 141.51 0 1 0
21 PLOT Type Q 141.476 1 141.476 0 1 0
22 PLOT Type R 141.525 1 141.525 0 1 0
23 PLOT Type S 141.623 1 141.623 0 1 0
24 PLOT Type T 126.333 1 126.333 0 1 0
25 PLOT Type E1-E3 128.102 3 384.306 1 2 0
26 PLOT Type E4 129.04 1 129.04 1 0 0
27 PLOT Type D1 147.1600 1 147.16 0 1 0
28 PLOT Type E12 129.6360 1 129.636 1 0 0
29 PLOT Type H18, H19 146.6000 2 293.2 2 0 0
30 PLOT Type COMMERCIAL 1673.6274 1 1673.6274 0 1 0
Total15022107.3574118320






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
N/A00


N/A
N/A
N/A
01-06-2026
0
30-11-2026


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT1180
01-06-2026
95
30-06-2026
TOTAL 150 UNIT (149 RESIDENTIAL PLOTS AND 1 COMMERCIAL PLOT). 118 RESIDENTIAL PLOTS ARE SOLD.
THE PROMOTER SHALL OBTAIN CC IS ON OR BEFORE 30TH AUGUST, 2027 AND HANDING OVER THE POSSESION ON OR BEFORE 1ST SEPTEMBER, 2027.


0
0
0
0
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements223.83
Water Supply System270.80
Sewerage treatment & garbage disposal132.13
Electricity Supply System0.00
Storm Water Drainage88.81
Parks and Playgrounds34.24
Clubhouse/community centres0
Shopping area0
Other160.90

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.513.060
Water Supply System000
Sewerage treatment & garbage disposal000
Electricity Supply System000
Storm Water Drainage0.601.210
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000
STP0.702.1291.43
Underground Water Tank0.711.45
Electrical sub station3.497.08
Construction of circulation road0.761.52












Particulars Remarks, if any
i. No. of Flats/Apartments constructed150149 Residential Plots and 1 Commercial Plot
ii. No. of Flats/ Apartments booked118Residential Plots
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter7674.00197 LakhsValue of Booked Residential Plots
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter7415.08733 LakhsAmount Received for Booked Residential Plots
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter258.91464 LakhsAmount to be received for booked Residential Plots
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter258.91464 LakhsBalance amount for booked Residential Plots
vii. Amount invested in the project upto the date of application10476.68 Lakhs
Land cost (If any)3990.11 Lakhs
Apartments0.00 LakhsN/A
Infrastructure1899.71 Lakhs
EDC/ Taxes Etc.4586.86 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession25.65 Lakhs
(a) In respect of existing allottees0.00 Lakhs
(b) In respect of rest of the project25.65 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0.00 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0.00 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS228.40223.83
II. WATER SUPPLY SYSTEM270.80270.80
III. STORM WATER DRAINAGE90.6288.81
IV. ELECTRICITY SUPPLY SYSTEM00
V. SEWAGE TREATMENT & GARBAGE DISPOSAL132.13132.13
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER160.90160.90
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.34.2434.24
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM0.000.00
XVII. OTHER FACILITIES AS PER PROJECT REPORT982.62963.35









Yes
Yes
NB BUILDCON PRIVATE LIMITED COLLECTION ACCOUNT
006505007575
ICIC0000065
110229008
0065
NARESH KUMAR, A6/3,VASANT VIHAR,NEW DELHI 110057. NAKUL YADAV, A 6/3,Vasant Vihar, New Delhi
Yes











Yes
Yes
Yes
No
No
No
No
No
No
No


Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO 168 OF 2022ALREADY BEEN OBTAINED21-10-2022
II. LAYOUT CUM DEMARCATIONALREADY BEEN OBTAINEDNA
III. ZONING PLANALREADY BEEN OBTAINED06-09-2023
IV. SERVICE PLAN ESTIMATESALREADY BEEN OBTAINED24-02-2023








Yes


Yes















SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEN/A
2WALL FINISHING DETAILSN/A
3KITCHEN DETAILSN/A
4BATHROOM FITTINGSN/A
5WOOD WORK ETCN/A
6DOORS AND WINDOS FRAMESN/A
7GLASS WORKN/A
8ELECTRIC FITTINGSN/A
9CONDUCTING AND WIRING DETAILSN/A
10CUPBOARD DETAILSN/A
11WATER STORAGEN/A
12LIFT DETAILSN/A
13EXTERNAL GLAZINGSN/A
13.1WINDOWS/GLAZINGSN/A
14DOORSN/A
14.1MAIN DOORSN/A
14.2INTERNAL DOORSN/A
15AIR CONDITIONINGN/A
16ELECTRICAL FITTINGSN/A
17CNG PIPE LINEN/A
18PROVISION OF WIFI AND BROADBAND FACILITYN/A
19EXTERNAL FINISHING/COLOUR SCHEMEN/A
20INTERNAL FINISHINGN/A
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORN/A
1 . 2 WALLSN/A
1 . 3 CEILINGN/A
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORN/A
2 . 2 WALLSN/A
2 . 3 CEILINGN/A
2 . 4 MODULAR WARDROBESN/A
3 . MASTER TOILET
3 . 1 FLOORN/A
3 . 2 WALLSN/A
3 . 3 CEILINGN/A
3 . 4 COUNTERSN/A
3 . 5 SANITARY WARE/CP FITTINGSN/A
3 . 6 FITTING/FIXTURESN/A
4 . BED ROOMS
4 . 1 FLOORN/A
4 . 2 WALLSN/A
4 . 3 CEILINGN/A
4 . 4 WARDROBESN/A
5 . TOILET
5 . 1 FLOORN/A
5 . 2 WALLSN/A
5 . 3 CEILINGN/A
5 . 4 COUNTERSN/A
5 . 5 SANITARY WARE/CP FITTINGSN/A
5 . 6 FIXTURESN/A
6 . KITCHEN
6 . 1 FLOORN/A
6 . 2 WALLSN/A
6 . 3 CEILINGN/A
6 . 4 COUNTERSN/A
6 . 5 FIXTURESN/A
6 . 6 KITCHEN APPLIANCESN/A
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORN/A
7 . 2 WALLS & CEILINGN/A
7 . 3 TOILETN/A
7 . 4 BALCONYN/A
8 . SIT-OUTS
8 . 1 FLOORN/A
8 . 2 WALLS & CEILINGN/A
8 . 3 RAILINGSN/A
8 . 4 FIXTURESN/A












Sr. No.Document DescriptionDate of Document UploadView Document
1 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 25-06-2026 View Document
2 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 25-06-2026 View Document
3 DEMARCATION PLAN 25-06-2026 View Document
4 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 25-06-2026 View Document
5 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 25-06-2026 View Document
6 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 25-06-2026 View Document
7 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 25-06-2026 View Document
8 ZONING PLAN 25-06-2026 View Document
9 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 25-06-2026 View Document
10 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 25-06-2026 View Document