As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
616332
29-07-2026
248000
YES BANK LIMITED
HRERA Panchkula
6.90 (Acre)
0
0
6.90 (Acre)
40 of 2026 (03-03-2026)
No
Address GURUGRAM
Address REWARI
Address DELHI
Address REWARI
Address REWARI
Annexure-B- ANNEXURE B-COLLABORATION AGREEMENT AND GPA EXECUTED, ANNEXED IN FOLDER B
YES, COLLABORATION AGREEMENT AND GPA MADE BEFORE GRANT OF LICENSE, ANNEXED IN FOLDER B
Yes
COLLABORATION AGREEMENT NO. 3198 DATED 24/07/2025 WITH GPA NO. 64 AND COLLABORATION AGREEMENT NO. 2948 DATED 15/07/2025 WITH GPA NO. 58 ANNEXED IN FOLDER B
No
Yes
Yes
1132.78 Lakhs
0 Lakhs
0 Lakhs
641.10 Lakhs
491.68 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
3.868
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
1.66
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0.521
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.690
12
ANY OTHER
0.161
Total
6.9
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
HSVP
No
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
HSVP
No
STORM WATER DRAINAGE
HSVP
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
134.00
SUBMITTED TO HUDA
2
WATER SUPPLY SYSTEM
176.00
SUBMITTED TO HUDA
3
STORM WATER DRAINAGE
66.00
SUBMITTED TO HUDA
4
ELECTRICITY SUPPLY SYSTEM
0
SUBMITTED TO HUDA
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
111.00
SUBMITTED TO HUDA
6
STREET LIGHTING
29.00
SUBMITTED TO HUDA
7
SECURITY AND FIRE FIGHTING
0
SUBMITTED TO HUDA
8
PLAYGROUNDS AND PARKS
0
SUBMITTED TO HUDA
9
CLUB HOUSE/COMMUNITY CENTRE
0
SUBMITTED TO HUDA
10
SHOPPING AREA
0
SUBMITTED TO HUDA
11
RENEWABLE ENERGY SYSTEM
0
SUBMITTED TO HUDA
12
SCHOOL
0
SUBMITTED TO HUDA
13
HOSPITAL/DISPENSARY
0
SUBMITTED TO HUDA
14
ANY OTHER
5.00
SUBMITTED TO HUDA
15
OTHERS
120.00
SUBMITTED TO HUDA
05-03-2026 (date)
NA (date)
01-09-2026
31-05-2029
Sr. No
Plot Area(In Square Meter)
Number of plots in the project
1
146.1
49
2
147.3
54
3
135.2
4
Total
107
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)