HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-2060-2026
Submission Date : 12-05-2026 10:44:09 PM
Applicant Type : Company
Project Type: NEW




SUNBREEZE BUILDERS AND DEVELOPERS PRIVATE LIMITED
HOUSE NO 15&54; FIRST FLOOR BLOCK-C POCKET-9 SECTOR-7 ROHINI METRO STATION NEW DELHI EAST DELHI-110085 IN
01143710710
7838778899 (Number Shared by Promoter in Public)
SUNBREEZEBUILDERS@GMAIL.COM
https://amvgroup.in
XXXX886K
U7010DL2005PTC144228
 
 


 
 


 
 


 
 


 
 







SHUBHANGAN FV
NIZAMPUR ROAD ,SECTOR-40
PANIPAT
PANIPAT
9306163267 (Number Shared by Promoter in Public)
SUNBREEZEBUILDERS@GMAIL.COM
TARUN RAHEJA
9306163267 (Number Shared by Promoter in Public)
SUNBREEZEBUILDERS@GMAIL.COM








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1012-05-2026398000BANK OF INDIAHRERA Panchkula







18893.64 (Sqr/mtrs)
2
2
18893.64 (Sqr/mtrs)
35 OF 2019
Yes







17345.15 Lakhs
480.84 Lakhs
16118.67 Lakhs
0 Lakhs
745.64 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 18125.50
3CONSTRUCTION OF ROADS 0
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
13COMMERCIAL 768.09
Total18893.59




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSSELF (INTERNAL)No
WATER SUPPLYSELF (INTERNAL)Yes
ELECTRICITYUHBVNYes
SEWAGE DISPOSALSELF (INTERNAL)Yes
STORM WATER DRAINAGESELF (INTERNAL)Yes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS0AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM0AS PER PROJECT REPORT
3STORM WATER DRAINAGE0AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM0AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL0AS PER PROJECT REPORT
6STREET LIGHTING0AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS0AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER0AS PER PROJECT REPORT


29-10-2024 (date)
29-10-2024 (date)
01-07-2021
31-03-2028
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 141.50 2
2 113.39 3
3 134.44 4
4 109.67 46
5 112.60 2
6 149.81 48
7 106.14 2
8 143.99 8
9 102.00 2
10 149.63 14
11 143.31 5
12 123.12 1
13 128.01 6
Total143


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings127.55260
Apartment/Shops/Other Buildings201.6930
Apartment/Shops/Other Buildings155.8850
Apartment/Shops/Other Buildings164.6120
Apartment/Shops/Other Buildings166.2940
Apartment/Shops/Other Buildings80.202840
Apartment/Shops/Other Buildings57.131040
Apartment/Shops/Other Buildings46.33300





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments7185.97
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments500700800
Shops000
Plots000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1100120014001400
Shops0000
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1152
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter (2028)
Apr-JuneJuly-SepOct-DecJan-Mar












Yes
Yes
BANK OF INDIA, GT ROAD,PANIPAT, HARYANA
675122510000001
BKID0006751
132013002
006751
ANIL WADHWA (C-102,SAI BABA APARTMENT,SECTOR-9,ROHINI,DELHI-110085)
UPLOADED











Yes
Yes
Yes
Yes
No
Yes
No
Yes
Yes
Yes


Yes
Yes
Yes
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE 35 OF 2019ALREADY BEEN OBTAINED01-03-2019
II. DEMARACATION CUM ZONING PLANALREADY BEEN OBTAINED29-10-2024
III. CTEALREADY BEEN OBTAINED02-05-2023
IV. PERMISSION CERTIFICATE_HWRAALREADY BEEN OBTAINED29-02-2024
V. ELECTRIFICATION PLAN_UHBVNALREADY BEEN OBTAINED13-01-2026








Yes


Yes


GIST OF IMPORTANT PROVISIONS OF BBA ENCLOSED







SHUBHANGAN (VILLAGE NIZAMPUR,SECTOR-40,HARYANA 132103)
9.4811
458
33
277
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
3639.029770.3510472.51
Cost of the apartments000
Cost of the infrastructure2404.907854.418556.57
Others costs1234.121915.941915.94


11577.60 Lakhs
1895.8 Lakhs
0 Lakhs
0 Lakhs
No
30-06-2021
30-03-2026




SHUBHANGAN 2(VILLAGE NIZAMPUR,SECTOR-40,HARYANA 132103)
8292.930
0
37
0
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
688.230211.83
Cost of the apartments000
Cost of the infrastructure208.850211.83
Others costs479.3800


0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
01-05-2025
31-05-2028










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEGOOD QUALITY TILE IN LIVING / DINING SPACE / BEDROOMS,ANTI-SKID CERAMIC TILES IN BATHROOM, KITCHEN,BALCONIES & COMMON AREAS,VITRIFIED TILES (SIZE 24” * 48” OR ABOVE)
2WALL FINISHING DETAILSACRYLIC EMULSION PAINTS,WEATHERPROOF ACRYLIC EMULSION PAINTS,CERAMIC TILE DADO UPTO 7’ IN BATHROOMS AND 2’ OVER COUNTER IN KITCHEN
3KITCHEN DETAILSANTI-SKID CERAMIC TILE FLOORING (SIZE 24” * 24” OR ABOVE), CERAMIC TILE DADO UPTO 7’ (SIZE 24” * 48”),SEMI MODULAR KITCHEN ,STAINLESS KITCHEN SINK WITH DRAIN BOARD AND SINK MIXER,COUNTERTOP GOOD QUALITY GRANITE,COUNTER WASHBASIN AS PER SPECIFICATIONS
4BATHROOM FITTINGSGOOD QUALITY C.P. AND SANITARY FITTINGS OF JAQUAR OR EQUIVALENTS
5WOOD WORK ETCMELAMINE POLISHED TEAK WOOD FRAMES WITH DESIGNER FLUSH DOORS IN INTERIOR
6DOORS AND WINDOS FRAMESUPVC SLIDING WINDOW AND GLAZING IN EXTERIOR,MELAMINE POLISHED TEAK WOOD FRAMES WITH DESIGNER FLUSH DOORS IN INTERIOR,UPVC SLIDING WINDOWS AND GLAZING AND PROVISION OF MOSQUITO MESH
7GLASS WORKNA
8ELECTRIC FITTINGSMODULAR ELECTRICAL SWITCHES, SOCKETS AND ELECTRICAL FITTINGS
9CONDUCTING AND WIRING DETAILSCOPPER WIRING,GOOD QUALITY MODULAR SWITCHES,MCB AND DB AS PER ISI STANDARD
10CUPBOARD DETAILSPREMIUM QUALITY CUPBOARDS IN ALL BEDROOMS
11WATER STORAGECOMPLETE WATER HARVESTING SYSTEM,IN-HOUSE WATER TREATMENT & BOOSTING STATION,UNDERGROUND AND OVERHEAD WATER TANK FOR EACH VILLA
12LIFT DETAILSAUTOMATED ELEVATOR OF REPUTED BRAND WITH STAINLESS STEEL INTERIORS
13EXTERNAL GLAZINGSAS PER ARCHITECT
13.1WINDOWS/GLAZINGSAS PER ARCHITECT
14DOORSWOODE FLUSH DOOR
14.1MAIN DOORSSELECTED GOOD QUALITY LOCKSET AND SUITABLE HARDWARE FOR WINDOWS AND DOORS
14.2INTERNAL DOORSFLUSH DOOR
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSLED LIGHTS, FANS AND EXHAUST FANS,COPPER WIRING,GOOD QUALITY MODULAR SWITCHES,MCB AND DB AS PER ISI STANDARD,TV, TELEPHONE POINTS AT APPROPRIATE PLACES
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMEAS PER ARCHITECT
20INTERNAL FINISHINGAS PER ARCHITECT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORGOOD QUALITY TILE IN LIVING / DINING SPACE / BEDROOMS,ANTI-SKID CERAMIC TILES IN BATHROOM, KITCHEN,BALCONIES & COMMON AREAS,VITRIFIED TILES (SIZE 24” * 48” OR ABOVE)
1 . 2 WALLSACRYLIC EMULSION PAINTS,WEATHERPROOF ACRYLIC EMULSION PAINTS,CERAMIC TILE DADO UPTO 7’ IN BATHROOMS AND 2’ OVER COUNTER IN KITCHEN
1 . 3 CEILINGOBD
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORGOOD QUALITY TILE IN LIVING / DINING SPACE / BEDROOMS,ANTI-SKID CERAMIC TILES IN BATHROOM, KITCHEN,BALCONIES & COMMON AREAS,VITRIFIED TILES (SIZE 24” * 48” OR ABOVE)
2 . 2 WALLSACRYLIC EMULSION PAINTS,WEATHERPROOF ACRYLIC EMULSION PAINTS,CERAMIC TILE DADO UPTO 7’ IN BATHROOMS AND 2’ OVER COUNTER IN KITCHEN
2 . 3 CEILINGOBD
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORANTI-SKID CERAMIC TILES IN BATHROOM
3 . 2 WALLSCERAMIC TILE DADO UPTO 7’ IN BATHROOMS
3 . 3 CEILINGOBD
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSGOOD QUALITY C.P. AND SANITARY FITTINGS OF JAQUAR OR EQUIVALENTS
3 . 6 FITTING/FIXTURESGOOD QUALITY C.P. AND SANITARY FITTINGS OF JAQUAR OR EQUIVALENTS
4 . BED ROOMS
4 . 1 FLOORGOOD QUALITY TILE IN LIVING
4 . 2 WALLSOBD
4 . 3 CEILINGOBD
4 . 4 WARDROBESWOODEN
5 . TOILET
5 . 1 FLOORANTI-SKID CERAMIC TILES IN BATHROOM
5 . 2 WALLSCERAMIC TILE DADO UPTO 7’ IN BATHROOMS
5 . 3 CEILINGOBD
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSGOOD QUALITY C.P. AND SANITARY FITTINGS OF JAQUAR OR EQUIVALENTS
5 . 6 FIXTURESGOOD QUALITY C.P. AND SANITARY FITTINGS OF JAQUAR OR EQUIVALENTS
6 . KITCHEN
6 . 1 FLOORANTI-SKID CERAMIC TILE FLOORING (SIZE 24” * 24” OR ABOVE)
6 . 2 WALLS2’ OVER COUNTER IN KITCHEN
6 . 3 CEILINGOBD
6 . 4 COUNTERSGRANITE
6 . 5 FIXTURESGOOD QUALITY OF JAQUAR OR EQUIVALENT
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORGOOD QUALITY TILE ,VITRIFIED TILES
7 . 2 WALLS & CEILINGOBD
7 . 3 TOILETNA
7 . 4 BALCONYAS PER ARCHITECT
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 12-05-2026 View Document
2 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 12-05-2026 View Document
3 ENGINEER PROFILE 12-05-2026 View Document
4 ARCHITECT PROFILE 12-05-2026 View Document
5 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 12-05-2026 View Document
6 PROJECT REPORT 12-05-2026 View Document
7 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 12-05-2026 View Document
8 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 12-05-2026 View Document
9 COI,MOA AOA OF THE COMPANY 12-05-2026 View Document
10 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 12-05-2026 View Document
11 DRAINAGE LAYOUT 12-05-2026 View Document
12 LETTER OF ALLOTMENT 12-05-2026 View Document
13 DOMESTIC & FLUSHING WATER LAYOUT 12-05-2026 View Document
14 ROAD LAYOUT 12-05-2026 View Document
15 SEWER LAYOUT 12-05-2026 View Document
16 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 12-05-2026 View Document
17 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 12-05-2026 View Document
18 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 12-05-2026 View Document
19 WORK ARCHITECT CERTIFICATE 30.04.2026 12-05-2026 View Document
20 ORGANISATION CHART 12-05-2026 View Document
21 DEMARCATION PLAN 12-05-2026 View Document
22 ZONING PLAN 12-05-2026 View Document
23 BOARD RESOLUTION 12-05-2026 View Document
24 GIST OF IMPORTANT PROVISIONS OF BBA 12-05-2026 View Document
25 NET WORTH CERTIFICATE 12-05-2026 View Document
26 CA CERTIFICATE (A-H) 12-05-2026 View Document
27 LICENSE RENEWAL 12-05-2026 View Document
28 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 12-05-2026 View Document