HRERA GurugramTemp Project Id : RERA-GRG-PROJ-2215-2026
Submission Date : 06-04-2026 02:20:45 PM
Applicant Type : Company
Project Type: NEW




DREAMWAYS INFRA PROJECTS PRIVATE LIMITED
A-802, 8TH FLOOR , PIONEER URBAN SQUARE, SECTOR-62, GOLF COURSE EXTENSION ROAD, GURUGRAM HARYANA -122001
8920685271 (Number Shared by Promoter in Public)
dreamwaysinfra@gmail.com
Https://dreamwaysinfra.com/
XXXX203A
U45500HR2020PTC088466
 
 


 
 


 
 







AQVA THE RESERVE
SECTOR 5, SOHNA, GURUGRAM
SOHNA
GURUGRAM
8920685271 (Number Shared by Promoter in Public)
dreamwaysinfra@gmail.com
MR URAV
8800925256 (Number Shared by Promoter in Public)
dreamwaysinfra@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
150006703-04-2026275000ICICI BANKHRERA Gurugram
250006722-04-2026143455ICICI BANKHRERA Gurugram







5.06875 (Acre)
100
100
5.06875 (Acre)
05 of 2026 Dated 08.01.2026
No
Address     3RD FLOOR(ROAD SIDE), 100 FOOTA ROAD, CHATTARPUR ENCLAVE, NEW DELHI, DELHI 110074
Address     A-609, PIONNER URBAN SQUARE SECTOR 62, GURGAON, HARYANA 122001
Address     PLOT NO. 54, KHASRA NO. 54/10/11/1/9, JONAPUR, SOUTH DELHI, DELHI 110047
Annexure-B- COLLABORATOR
BEFORE
Yes
AS PER CLAUSE
No
Yes
Yes







8727.91 Lakhs
7062.28 Lakhs
0.00 Lakhs
601.00 Lakhs
1064.63 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 3.2950
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0
3CONSTRUCTION OF ROADS 1.3938
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0.3800
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0.6187
Total5.6875




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSALREADY CONNECTEDYes
WATER SUPPLYHSVPYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHSVPYes
STORM WATER DRAINAGEHSVPYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS56.00AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM32.00AS PER PROJECT REPORT
3STORM WATER DRAINAGE17.00AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM45.00AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL32.00AS PER PROJECT REPORT
6STREET LIGHTING8.00AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS6.50YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15STP95.00AS PER PROJECT REPORT
16UNDERGROUND WATER TANK 21.00AS PER PROJECT REPORT
17RAIN WATER HARVESTING 12.00AS PER PROJECT REPORT
18ELECTRICAL SUB STATION150.00AS PER PROJECT REPORT
19CIRCULUR ROAD 27.00AS PER PROJECT REPORT
20SITE ESTABLISHMENT COST 99.50AS PER PROJECT REPORT


08-01-2026 (date)
NA (date)
01-04-2026
31-12-2029
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 144.01 16
2 144.54 13
3 122.89 3
4 148.85 29
5 144.07 17
6 781.19 1
Total79


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements8.4011.2011.20
Water Supply System4.806.406.40
Sewerage treatment & garbage disposal4.806.406.40
Electricity Supply System2.252.259.00
Storm Water Drainage2.553.403.40
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000
Site Establishment Cost24.8824.8824.88
Rain Water Harvesting2.402.402.40
Circular Road2.702.702.70
Street lighting1.60

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements5.602.802.802.80
Water Supply System3.2016.0016.0016.00
Sewerage treatment & garbage disposal3.201.601.601.60
Electricity Supply System9.009.002.252.25
Storm Water Drainage1.700.850.850.85
Parks and Playgrounds01.951.950.33
Clubhouse/community centres0000
Shopping area0000
Other0000
Rain Water Harvesting0.600.600.600.60
Circular Road2.702.702.702.70
Electrical Sub Station37.5037.5037.5037.50
Street lighting1.601.600.800.80
STP19.0019.0019.0019.00
Underground Water Tank4.204.204.202.10
Site Establishment Cost24.88

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements2.802.802.802.80
Water Supply System16.0016.0016.0016.00
Sewerage treatment & garbage disposal1.601.601.601.60
Electricity Supply System2.252.252.252.25
Storm Water Drainage0.850.850.850.85
Parks and Playgrounds0.330.330.330.33
Clubhouse/community centres0000
Shopping area0000
Other0000
Underground Water Tank1.051.051.051.05
Rain Water Harvesting0.600.600.600.60
Circular Road1.351.351.351.35
Street lighting0.400.400.400.40
STP4.754.754.754.75

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements000
Water Supply System000
Sewerage treatment & garbage disposal000
Electricity Supply System000
Storm Water Drainage000
Parks and Playgrounds0.330.330.33
Clubhouse/community centres000
Shopping area000
Other000
Circular Road1.351.35
Underground Water Tank1.051.05












Yes
Yes
ICICI BANK LTD DG 01 & DG 09 PIONEER URBAN SQUARE SECTOR 62 GOLF COURSE EXTENSION ROAD, GURGAON, HARYANA 122001
777705150820
ICIC0007073
122229020
7073
Abhishek Kundu R/o Flat No. B 2301 IREO Grand Arch Apartment, Golf Course Extension Road, Sector 58, Gurgaon, Sector 56, Gurgaon, Haryana 122011 & Kamal Ambawta R/O 448/1, Jona Pur, South Delhi, Delhi 110047
Attached











Yes
Yes
Yes
No
No
No
No
No
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
No
Statutory Approvals Statutory Approvals StatusDate
I. ZONING PLANALREADY BEEN OBTAINED09-03-2026
II. ELECTRICAL LOADALREADY BEEN OBTAINED08-10-2025
III. FOREST NOCALREADY BEEN OBTAINED06-10-2025
IV. ASSURANCE OF WATER SUPPLYALREADY BEEN OBTAINED27-03-2026
V. ASSURANCE OF STORM WATERALREADY BEEN OBTAINED27-03-2026
VI. ASSURANCE OF SEWERAGE CONNECTIONALREADY BEEN OBTAINED27-03-2026
VII. LICENSEALREADY BEEN OBTAINED08-01-2026
VIII. LAYOUT PLANALREADY BEEN OBTAINED08-01-2026
IX. APPROVAL OF SERVICE PLAN ESTIMATEAPPLIED FOR BUT YET TO RECEIVE24-03-2026








Yes


Yes


As Per Norms













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 ASSURANCE OF WATER SUPPLY 03-04-2026 ------
2 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 03-04-2026 View Document
3 SERVICE PLAN AND ESTIMATES 05-04-2026 ------
4 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 03-04-2026 View Document
5 BANK UNDERTAKING 03-04-2026 ------
6 LOI 03-04-2026 ------
7 LC-IV 03-04-2026 ------
8 COLLABORATION AGREEMENT 03-04-2026 ------
9 ELECTRICAL LOAD 03-04-2026 ------
10 FOREST NOC 03-04-2026 ------
11 ASSURANCE OF STORM WATER 03-04-2026 ------
12 ASSURANCE OF SEWERAGE CONNECTION 03-04-2026 ------
13 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 03-04-2026 View Document
14 DEMARCATION PLAN 03-04-2026 View Document
15 ZONING PLAN 03-04-2026 View Document
16 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 03-04-2026 View Document
17 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 03-04-2026 View Document
18 JAMABANDI 28-04-2026 ------
19 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 28-04-2026 View Document
20 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 28-04-2026 View Document
21 MUTATION LATEST CERTIFIED 28-04-2026 ------
22 NCZ AFFIDAVIT 28-04-2026 ------
23 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 28-04-2026 View Document
24 AKS-SHIJRA 28-04-2026 ------
25 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 28-04-2026 View Document
26 AFFIDAVIT 4(2)(L)(D) 28-04-2026 ------
27 LAND COST - AFFIDAVITS 30-04-2026 ------
28 PLOT ALLOCATION- AQVA 30-04-2026 ------
29 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 28-04-2026 View Document
30 NEC 28-04-2026 ------
31 DREAMWAYS - BBA 30-04-2026 ------