HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1996-2026
Submission Date : 20-03-2026 05:07:29 PM
Applicant Type : Firm
Project Type: NEW


SONIPAT DEVRU VENTURES LLP
C/O OMWATI, VIKAS NAGAR, NEAR REVLI NAHAR, ASADPUR NANDNAUR, SONIPAT, HARYANA-131027
01242386911
9818732288 (Number Shared by Promoter in Public)
somesh@balaji-group.com
ACJ7379
AFKFS6029L













THE ELITE ADDRESS
VILLAGE DEVRU SECTOR 91
SONIPAT
SONIPAT
9467941127 (Number Shared by Promoter in Public)
somesh@balaji-group.com
SANDEEP KUMAR
9467941127 (Number Shared by Promoter in Public)
somesh@balaji-group.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1020-03-2026250000ONLINE PAYMENT SHALL BE DONE. HRERA Panchkula







5.73125 (Acre)
1.0 for Plotted and 1.5 for Commercial
1.0
5.73125 (Acre)
License No. 253 of 2025 dated 22.12.2025 (Valid upto 21.12.2030)
Yes







3327.31 Lakhs
2021.31 Lakhs
0.00 Lakhs
716.41 Lakhs
589.591 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 2.9730
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0
3CONSTRUCTION OF ROADS 1.632250
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0.4300
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0.5730
12ANY OTHER 0
13COMMERCIAL 0.1230
Total5.73125




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS128.95AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM107.46AS PER PROJECT REPORT
3STORM WATER DRAINAGE85.97AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM143.28AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL157.61AS PER PROJECT REPORT
6STREET LIGHTING21.49AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS71.64AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


22-12-2025 (date)
NA (date)
23-03-2026
21-12-2030
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 74.797 15
2 90.098 1
3 91.288 2
4 77.012 4
5 121.345 4
6 122.623 4
7 118.214 3
8 149.938 12
9 147.225 16
10 116.651 10
11 148.036 24
Total95


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements6.796.796.79
Water Supply System5.665.665.66
Sewerage treatment & garbage disposal8.308.308.30
Electricity Supply System7.547.547.54
Storm Water Drainage4.524.524.52
Parks and Playgrounds3.773.773.77
Clubhouse/community centres000
Shopping area000
Other1.131.131.13

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements6.796.796.796.79
Water Supply System5.665.665.665.66
Sewerage treatment & garbage disposal8.308.308.308.30
Electricity Supply System7.547.547.547.54
Storm Water Drainage4.524.524.524.52
Parks and Playgrounds3.773.773.773.77
Clubhouse/community centres0000
Shopping area0000
Other1.131.131.131.13

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements6.796.796.796.79
Water Supply System5.665.665.665.66
Sewerage treatment & garbage disposal8.308.308.308.30
Electricity Supply System7.547.547.547.54
Storm Water Drainage4.524.524.524.52
Parks and Playgrounds3.773.773.773.77
Clubhouse/community centres0000
Shopping area0000
Other1.131.131.131.13

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements6.796.796.796.79
Water Supply System5.665.665.665.66
Sewerage treatment & garbage disposal8.308.308.308.30
Electricity Supply System7.547.547.547.54
Storm Water Drainage4.524.524.524.52
Parks and Playgrounds3.773.773.773.77
Clubhouse/community centres0000
Shopping area0000
Other1.131.131.131.13












Yes
No
ICICI BANK LTD., BESTECH SQUARE MALL SECTOR 57, GURGAON (100% COLLECTION ACCOUNT NUMBER MENTIONED AS PER BELOW)
777705127890
ICIC0001147
110229197
001147
Sh. Somesh Mittal R/o MG 1608B, The Magnolias, DLF Golf Links, Sector 42, Chakkarpur, Gurgaon
Uploaded.











Yes
Yes
Yes
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO. 253 OF 2025ALREADY BEEN OBTAINED22-12-2025
II. DEMARCATION-CUM-ZONING PLANALREADY BEEN OBTAINED28-01-2026








Yes


Yes


The RERA Act and Rules shall be incorporated in the draft agreement to sell.













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENOT APPLICABLE BEING PLOTTED COLONY
2WALL FINISHING DETAILSNOT APPLICABLE BEING PLOTTED COLONY
3KITCHEN DETAILSNOT APPLICABLE BEING PLOTTED COLONY
4BATHROOM FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
5WOOD WORK ETCNOT APPLICABLE BEING PLOTTED COLONY
6DOORS AND WINDOS FRAMESNOT APPLICABLE BEING PLOTTED COLONY
7GLASS WORKNOT APPLICABLE BEING PLOTTED COLONY
8ELECTRIC FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
9CONDUCTING AND WIRING DETAILSNOT APPLICABLE BEING PLOTTED COLONY
10CUPBOARD DETAILSNOT APPLICABLE BEING PLOTTED COLONY
11WATER STORAGENOT APPLICABLE BEING PLOTTED COLONY
12LIFT DETAILSNOT APPLICABLE BEING PLOTTED COLONY
13EXTERNAL GLAZINGSNOT APPLICABLE BEING PLOTTED COLONY
13.1WINDOWS/GLAZINGSNOT APPLICABLE BEING PLOTTED COLONY
14DOORSNOT APPLICABLE BEING PLOTTED COLONY
14.1MAIN DOORSNOT APPLICABLE BEING PLOTTED COLONY
14.2INTERNAL DOORSNOT APPLICABLE BEING PLOTTED COLONY
15AIR CONDITIONINGNOT APPLICABLE BEING PLOTTED COLONY
16ELECTRICAL FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
17CNG PIPE LINENOT APPLICABLE BEING PLOTTED COLONY
18PROVISION OF WIFI AND BROADBAND FACILITYNOT APPLICABLE BEING PLOTTED COLONY
19EXTERNAL FINISHING/COLOUR SCHEMENOT APPLICABLE BEING PLOTTED COLONY
20INTERNAL FINISHINGNOT APPLICABLE BEING PLOTTED COLONY
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
1 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
1 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
2 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
2 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
2 . 4 MODULAR WARDROBESNOT APPLICABLE BEING PLOTTED COLONY
3 . MASTER TOILET
3 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
3 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
3 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
3 . 4 COUNTERSNOT APPLICABLE BEING PLOTTED COLONY
3 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
3 . 6 FITTING/FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
4 . BED ROOMS
4 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
4 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
4 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
4 . 4 WARDROBESNOT APPLICABLE BEING PLOTTED COLONY
5 . TOILET
5 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
5 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
5 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
5 . 4 COUNTERSNOT APPLICABLE BEING PLOTTED COLONY
5 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
5 . 6 FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
6 . KITCHEN
6 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
6 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
6 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
6 . 4 COUNTERSNOT APPLICABLE BEING PLOTTED COLONY
6 . 5 FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
6 . 6 KITCHEN APPLIANCESNOT APPLICABLE BEING PLOTTED COLONY
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
7 . 2 WALLS & CEILINGNOT APPLICABLE BEING PLOTTED COLONY
7 . 3 TOILETNOT APPLICABLE BEING PLOTTED COLONY
7 . 4 BALCONYNOT APPLICABLE BEING PLOTTED COLONY
8 . SIT-OUTS
8 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
8 . 2 WALLS & CEILINGNOT APPLICABLE BEING PLOTTED COLONY
8 . 3 RAILINGSNOT APPLICABLE BEING PLOTTED COLONY
8 . 4 FIXTURESNOT APPLICABLE BEING PLOTTED COLONY












Sr. No.Document DescriptionDate of Document UploadView Document
1 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 09-03-2026 View Document
2 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 09-03-2026 View Document
3 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 09-03-2026 View Document
4 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 09-03-2026 View Document
5 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 09-03-2026 View Document
6 PAYMENT PLAN 07-05-2026 ------