HRERA GurugramTemp Project Id : RERA-GRG-PROJ-172-2019
Submission Date : 31-01-2019 09:40:20 AM
Applicant Type : Company
Project Type: NEW




PYRAMID INFRATECH PRIVATE LIMITED
H-38, M2K WHITE HOUSE, SECTOR 57, GURUGRAM, HARYANA-122002
01244274045
9811000240 (Number Shared by Promoter in Public)
SUNIL@PYRAMIDINFRATECH.COM
http://pyramidinfratech.com
XXXX801B
U45400HR2008PTC038509
 
 


 
 


 
 


 
 







PYRAMID FUSION HOMES
VILLAGE PALRA SECTOR 70A
BADSHAHPUR ST
GURUGRAM
1244274045
9811000240 (Number Shared by Promoter in Public)
CUSTOMERCARE@PYRAMIDINFRATECH.COM
KRISHNA GOPAL
1244274045
9811000284 (Number Shared by Promoter in Public)
KRISHNA.G@PYRAMIDINFRATECH.COM








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
182155629-01-20191057530KOTAK MAHINDRA BANK LIMITEDHRERA Gurugram
282155529-01-2019461957KOTAK MAHINDRA BANK LIMITEDHRERA Gurugram







5.11875 (Acre)
2.25
2.25
5.11875 (Acre)
84 OF 2018
No
Address     SEATING 4, UNIT NO.119, FIRST FLOOR VARDHMAN STAR CITI MALL SECTOR-7 DWARKA DELHI 110075
Annexure-B- COLLABORATOR/DEVELOPER
BEFORE GRANT OF LICENSE
Yes
COLLABORATION NO.7583 DATED 14.03.2018
No
Yes
Yes







15034 Lakhs
2850 Lakhs
8290 Lakhs
364 Lakhs
3530 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS3608.658
3CONSTRUCTION OF ROADS5877.21
4PAVEMENTS0
5PARKS AND PLAYGROUNDS4357.481
6GREEN BELTS0
7VEHICLE PARKINGS3602.177
8ELECTRICITY SUB-STATION94.057
9CLUB HOUSE199.68
10SEWAGE AND SOLID WASTE TREATMENT FACILITY295.19
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER1872.805
13AREA807.555
Total20714.813




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS37SUBMITTED TO HUDA
2WATER SUPPLY SYSTEM69.5SUBMITTED TO HUDA
3STORM WATER DRAINAGE42.72SUBMITTED TO HUDA
4ELECTRICITY SUPPLY SYSTEM0YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL64.58SUBMITTED TO HUDA
6STREET LIGHTING7.51SUBMITTED TO HUDA
7SECURITY AND FIRE FIGHTING20.37SUBMITTED TO HUDA
8PLAYGROUNDS AND PARKS6SUBMITTED TO HUDA
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15RAIN WATER HARVESTING10SUBMITTED TO HUDA
16SEWERAGE34SUBMITTED TO HUDA
17MAINTENACE EXPENSES28.40SUBMITTED TO HUDA
18UNDERGROUND TANK35SUBMITTED TO HUDA
19PARKING8SUBMITTED TO HUDA


23-01-2019 (date)
23-01-2019 (date)
30-05-2019
16-05-2023
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings54.9193627
Apartment/Shops/Other Buildings53.9331887
Apartment/Shops/Other Buildings53.723947
Apartment/Shops/Other Buildings55.605947
Apartment/Shops/Other Buildings21.045251
Apartment/Shops/Other Buildings10.52141
Apartment/Shops/Other Buildings21.045141





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments436.21
Shops0
Plots0

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments930.94914.22950.42848.42
Shops0000
Plots0000

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1036.36782.59861.47961.15
Shops0000
Plots0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments803.71927.06998.58916.88
Shops0000
Plots0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments790.59643.57699.18704.10
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter (2022)
Apr-JuneJuly-SepOct-DecJan-Mar












Yes
No
KOTAK MAHINDRA BANK LIMITED
7812685807
KKBK0000261
110485002
000261
DINESH KUMAR AND BRAHM DUTT











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
No
Yes
Yes
Yes
No
Yes
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE COPYALREADY BEEN OBTAINED10-12-2018
II. NOC FROM HUDA/GMDA FOR USE OF STP WATER FOR CONSTRUCTIONALREADY BEEN OBTAINED03-01-2019
III. FOREST NOCALREADY BEEN OBTAINED03-10-2018
IV. AIRPORT HEIGHT CLEARANCE NOCAPPLIED FOR BUT YET TO RECEIVE24-01-2019
V. SERVICES ESTIMATES AND PLANSAPPLIED FOR BUT YET TO RECEIVE30-01-2019








Yes


Yes









PYRAMID INFRATECH P LTD, URBAN HOMES, VILLAGE PALRA, SECTOR-70A, HARYANA,
9.875
1613
0
1613
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
21370.9321370.9318739.38
Cost of the apartments15449.6315449.6315220.63
Cost of the infrastructure1443.081443.080
Others costs4478.214478.213518.75


33530.15 Lakhs
770.09 Lakhs
0 Lakhs
0 Lakhs
No
19-02-2016
18-01-2020




PYRAMID INFRATECH P LTD, URBAN HOMES-II, VILLAGE BADHA, SECTOR-86, HARYANA,
5.2875
863
0
854
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
9564.719564.717222.33
Cost of the apartments6771.416771.415657.64
Cost of the infrastructure740.19740.190
Others costs2053.112053.111564.69


17688.05 Lakhs
644.40 Lakhs
0 Lakhs
0 Lakhs
No
22-01-2016
21-01-2020




PYRAMID INFRATECH P LTD, URBAN 67A, VILLAGE BADSHAHPUR, SECTOR-67A, HARYANA,
9.83125
1330
0
1326
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
18389.6618389.663940.77
Cost of the apartments11377.9911377.992067.04
Cost of the infrastructure2478.942478.940
Others costs4532.744532.741873.73


11177.54 Lakhs
25495 Lakhs
8900 Lakhs
6451 Lakhs
No
13-01-2018
12-02-2022




PYRAMID INFRATECH P LTD, PYRAMID ELITE, VILLAGE NAWADA FATEHPUR, SECTOR-86, HARYANA,
5.6125
810
0
0
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
16698166980
Cost of the apartments8070166980
Cost of the infrastructure1412166980
Others costs3716166980


20503 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
15-01-2019
14-05-2023










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSETILES/IPS
2WALL FINISHING DETAILSOBD/COLOUR WASH
3KITCHEN DETAILS2 FEET TILE ON WALL, OBD/COLOUR WASH ON REMAING WALL, TILE/STONE ON KITCHEN COUNTER.
4BATHROOM FITTINGSCP/PVC FITTINGS
5WOOD WORK ETCN/A
6DOORS AND WINDOS FRAMESHARDWOOD/ MS Z-SECTION/ FIBRE/ COMPOSITE/ ALUMINIUM/ FRAME WINDOWS ETC.
7GLASS WORKIN EXTERNAL WINDOWS
8ELECTRIC FITTINGSISI MARK
9CONDUCTING AND WIRING DETAILSISI MARK
10CUPBOARD DETAILSN/A
11WATER STORAGEOVER HEAD TANK ABOVE BUILDING AND UGT TANK
12LIFT DETAILS2 LIFTS AS PER SANCTIONED PLAN
13EXTERNAL GLAZINGSN/A
13.1WINDOWS/GLAZINGSGLAZED WINDOWS 4 MM GLASS
14DOORSFLUSH DOOR
14.1MAIN DOORSFLUSH DOOR
14.2INTERNAL DOORSFLUSH DOOR
15AIR CONDITIONINGN/A
16ELECTRICAL FITTINGSSTANDARD
17CNG PIPE LINEN/A
18PROVISION OF WIFI AND BROADBAND FACILITYN/A
19EXTERNAL FINISHING/COLOUR SCHEMECEMENT PAINT/COLOUR WASH
20INTERNAL FINISHINGOBD/COLOUR WASH
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORTILES/IPS
1 . 2 WALLSOBD/COLOUR WASH
1 . 3 CEILINGOBD/COLOUR WASH
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORTILES/IPS
2 . 2 WALLSOBD/COLOUR WASH
2 . 3 CEILINGOBD/COLOUR WASH
2 . 4 MODULAR WARDROBESN/A
3 . MASTER TOILET
3 . 1 FLOORTILES/IPS
3 . 2 WALLSOBD/COLOUR WASH
3 . 3 CEILINGOBD/COLOUR WASH
3 . 4 COUNTERSN/A
3 . 5 SANITARY WARE/CP FITTINGSCP/PVC
3 . 6 FITTING/FIXTURESCHINAWARE
4 . BED ROOMS
4 . 1 FLOORTILES/IPS
4 . 2 WALLSOBD/COLOUR WASH
4 . 3 CEILINGOBD/COLOUR WASH
4 . 4 WARDROBESN/A
5 . TOILET
5 . 1 FLOORTILES/IPS
5 . 2 WALLSOBD/COLOUR WASH
5 . 3 CEILINGOBD/COLOUR WASH
5 . 4 COUNTERSN/A
5 . 5 SANITARY WARE/CP FITTINGSCP/PVC
5 . 6 FIXTURESCHINAWARE
6 . KITCHEN
6 . 1 FLOORTILES/IPS
6 . 2 WALLSOBD/COLOUR WASH
6 . 3 CEILINGOBD/COLOUR WASH
6 . 4 COUNTERSSTONE/TILES
6 . 5 FIXTURESCP/PVC
6 . 6 KITCHEN APPLIANCESN/A
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORTILES/IPS
7 . 2 WALLS & CEILINGOBD/COLOUR WASH
7 . 3 TOILETN/A
7 . 4 BALCONYOBD/COLOUR WASH
8 . SIT-OUTS
8 . 1 FLOORTILES/IPS
8 . 2 WALLS & CEILINGOBD/COLOUR WASH
8 . 3 RAILINGSRCC
8 . 4 FIXTURESN/A












Sr. No.Document DescriptionDate of Document UploadView Document
1A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS16-02-2019 View Document
2DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.16-02-2019 View Document
3NOC HEIGHT CLEARANCE 16-02-2019 ------
4NOC STP WATER16-02-2019 ------
5COPY OF LICENSE ALONG WITH SCHEDULE OF LAND31-01-2019 View Document
6SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN31-01-2019 View Document
7DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD31-01-2019 View Document
8DEMARCATION PLAN31-01-2019 View Document
9ZONING PLAN31-01-2019 View Document
10IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN31-01-2019 View Document
11CASH FLOW STATEMENT OF THE PROPOSED PROJECT31-01-2019 View Document
12NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT31-01-2019 View Document
13IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN31-01-2019 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 EXTENSION NO. 10 of 2023 DATED 08.05.2023 15-06-2023 View Document
2 Occupation Certificate 20-09-2024 View Document